COMMUNITY SERVICES & ENVIRONMENT COMMITTEE

 

 

 

 

 

TO:

Mayor and Members of Council

 

 

 

 

FROM:

Don McClean, Fire Chief     

 

 

 

 

PREPARED BY:

Shayne Mintz, Deputy Fire Chief

 

 

 

 

DATE OF MEETING:

February 9, 2004     

 

 

 

 

SUBJECT:

August 14, 2003 Blackout Report     

 

 

 


 

 

RECOMMENDATION:

 

THAT council receive this report for information.

 

AND that Council approve additional funding of $20,000 through the 2004 budget process for the purpose of Emergency Management in Markham.

 

 

PURPOSE:

 

The purpose of this report is to provide Council with a description of events arising from the major blackout that occurred on August 14, 2003, and to identify areas for improvement in the Town’s operations in order to adequately handle an event of this nature in future.

 

 

EXECUTIVE SUMMARY:

 

In August of 2003, the Town of Markham was struck with a widespread blackout that affected the continental northeast.

 

For the most part the Town’s employees responded well to the power outage. There are also some areas for improvement that have been identified as a result of that event.

 

 

BACKGROUND:

 

On August 14, 2003 at approximately 4:15 PM EST, Markham was struck with a widespread power outage that spread across Ontario, New York State, Ohio and parts of Michigan and Pennsylvania.

 

At that time the extent of the power outage was unknown and as it occurred at the end of the business day most staff were sent home. Fire Department and other Senior Town staff gathered at Fire Station 95 to monitor the situation, assess the extent of the problem and devise a strategy to maintain public safety and protection. Arrangements were made for additional water supplies through the Operations and Asset Management Department. One crew of firefighters was held back from going off duty providing an additional response crew. Corporate Communications created a temporary call centre lending support to Information Markham.

 

The effect of the power outage meant disruption to business operations and a general loss of communications capabilities within the Civic Centre and throughout the Town. Traffic congestion was a significant issue due to traffic signal disruptions.  At approximately 3:30 AM the following day power was restored to the majority of Markham. However, after power was re-established the power grid was not operating at full capacity and still in a fragile state. There was a continued threat of rolling blackouts as more communities were brought back onto the power grid.

 

Calls for the Fire and Emergency Services throughout the blackout period spiked by 400% over normal call volumes for that period. In total the Fire Services responded to 160 calls for help between 4:00 PM Thursday and 8:00 AM Sunday. The Fire/Police Services radio communications system had operational fluctuations in the early morning of August 15; however full service was restored by 7:00AM.

 

On the morning of Friday August 15, staff opened an Emergency Operations Centre in the Canada Room. The Call-Centre was in full operation and handled 694 calls with respect to both the emergency and Town services. All telephone systems throughout the Town were still not fully operational. Cellular telephone operations were intermittent, and pager service was non-existent for approximately four days. Most telephone systems were back in operation by Saturday. The ITS Department worked throughout the weekend maintaining computer systems and communications networks.  Also, low water supplies to portions of Markham were causing a potential threat to public safety and health.  There was a major concern that if the power outage continued many services and businesses would lose telephone systems and stored data once the UPS systems (battery backup) ran out.

 

Due to low water reserves, a water emergency was declared and conservation measures were implemented to allow water levels to stabilize by Friday evening. The threat of public safety was that (1) there would not be adequate water supply for firefighting; (2) that if the water levels dropped too far, the reservoir system would be subject to contamination due to backflow; and (3) that stagnant water in the distribution system could cause problems.

 

Corporate Communications developed messages on the water ban, power outage and conservation tips and faxed them to all media and special interest groups. Message boards at various Town facilities were also used to publicize the messages. In conjunction with the ITS Department the Town’s main phone greeting was continually updated throughout Friday and the weekend to advise callers of pertinent information as it became available. Broadcast voice

messages and e-mails were sent to inform staff of the situation. The Town web site had 86,176 hits over the weekend. The Town of Markham page of the Economist and Sun newspaper was also used as a forum to communicate public service announcements regarding the blackout, the ensuing water emergency and threat of rolling blackouts.

 

Vehicles with public address systems were dispatched to target communities advising residents of the water emergency and requested citizens to refrain from non-essential water use. Parking and by-law enforcement officers were deployed to advise businesses and residents of the water emergency.

 

Water levels continued to improve throughout the weekend bringing them to acceptable levels by Sunday August 17. The conservation measures were continued, as the threat of rolling blackouts could have resulted in water shortages reoccurring.

 

August 15 was a regular collection day for Waste Management and there was no interruption in service.

 

Over the weekend Town facilities were closed and all programs cancelled, except for those essential to health and safety. Services were reinstated on the following Monday, August 18, with efforts being made to conserve energy. The continued threat of rolling blackouts resulted in all town facilities lowering lighting, and decreasing or eliminating non-essential utilities such as air conditioning.

 

Markham staff also continued all public swim programs as well as operating the various splash pads throughout the town. Further arrangements were made to open three community centres as ‘Cooling Centres’ if further power interruptions occurred.

 

 

OPTIONS/DISCUSSION:

 

What went well?

 

For the most part Town staff responded well to the challenge of the blackout, the water shortage emergency and threat of rolling blackouts. A core group of staff worked throughout the night to ensure that the Town continued to operate safely.   Contingencies were set-up for every possible scenario.  Public Address systems on Operations vehicles were used to ensure an effective, reliable, direct and immediate communications means to the public.

 

CAO John Livey worked from Fire Station 95 to oversee the operation.  Fuel supplies were secured and shared with desperate facilities such as Woodhaven Nursing Home.  Contact was maintained with York Region and the Provincial operations centres.

 

A communication plan was developed and stakeholders were kept informed throughout the night. 

 

Staff kept Town functions working and also helped others where possible.  There were dozens of citizens who ran out of fuel on the long drive home and staff refuelled them with a few gallons to get them safely home.  Others were given advice on what to do and many citizens commented that they felt secure due to the presence of Town staff in their areas and on the roads.

 

 

What are areas for improvement?

 

Back-Up Power Capability In The Emergency Operations Centre – It is vital that an Emergency Operations Centre have a robust power supply as well as back-up power generation capabilities. Lack of power and back-up power in the Civic Centre required senior town staff to move the Emergency Operations Centre to Fire Station 95 after the blackout occurred. Staff is currently trying to make arrangements with Markham District Energy to have a direct power supply from their grid. While it is yet to be confirmed this option may be capable of providing the Civic Centre with a more reliable power supply.

 

 

Civic Centre rooms are not ideal for Emergency Operations Centre use – It was identified in post Blackout debriefings that Civic Centre Rooms, specifically the Canada Room may not be not ideal for use as an Emergency Operations Centre.

 

 

Desirable to have Emergency Operations Centre in Close Proximity to Fire Communications Centre – During the blackout Senior Town staff found it to be very beneficial to be close to the Fire Communications Centre. In addition to the comfort of having a more reliable communications system, a back-up generator also protects the Centre. However, as Station 95 is a fully staffed fire station, the current configuration is too small to use as an Emergency Operations Centre over a sustained period of time. If the power outage lasted for a longer duration, it is unlikely these facilities would have properly met the needs of the management team.

 

 

ITS Requires off-site Fault Tolerant Data Centre – As a result of the black-out the ITS Department did not have fault tolerant redundant systems or facilities in place to bring Town operations back to operation until after full power was restored. The Town would benefit from an off-site fault tolerant ITS system redundancy. Consideration is being given to resolving this issue through discussions with ITS.

 

 

Various Communications Modes Failed during Blackout – Some of our communications facilities failed during the blackout i.e. pagers did not work. Staff is investigating options for a more robust communications network technology that can operate throughout a power outage. The ITS Department is currently consulting with the Gartner Group on industry best practises. In the interim and as a short-term solution, consideration should be given to the acquisition (either lease or purchase) of additional communications technology such as satellite telephones or additional fire service portable radios. Once an opinion is received from consultants, these devices can be returned to the vendor or redeployed.

 

 

Emergency Alerting System Needs Improvement – It has become evident that Town staff should handle the Emergency Alerting System. The Emergency Plan in place during the blackout had the Emergency Alerting System being facilitated by the Town’s security service provider. It became evident that their systems also failed during the blackout and therefore were of little use to Town staff when it came time to open the Emergency Operations Centre.  Instead the fan occurred through direct calls to key staff and fire dispatch.

 

 

Staff need education and Training on Emergency Management – While staff response was good to the emergency, there is an awareness and general consensus that this was a ‘close call’ that could have been much more serious. Staff have identified a strong need and desire for training, orientation and familiarization in emergency management and departmental emergency plans. This training should be consistent with best practises in emergency management, as well as meet the requirement of new Emergency Management legislation passed in April of 2003.

 

 

Staff need to exercise Emergency Management scenarios annually – Staff have requested the opportunity to exercise, practise skills and gain knowledge through Emergency Management Training. Such exercises would be consistent with best practises in emergency management as well as meet the requirement of new Emergency Management legislation passed in April of 2003.

 

 

Emergency Management Program Committee to be created – In compliance with provincial legislation an Emergency Management Program Committee should be created. Participation on this committee should include, at a minimum, Managers and preferably Directors. These individuals will have authority to undertake projects and give direction to staff to participate in emergency management activities, such as training, developing department emergency plans and exercising their role in emergency management.

 

Public Awareness Campaign to continue – The public awareness campaign as recognized by the province, as a model for other communities to emulate should continue. Additional steps should also be investigated as to how the program may be improved.

 

2004 IMPROVEMENT PLAN:

 

In 2004 staff will undertake the following initiatives as a follow-up to the August 2003 blackout:

 

·        examine what is needed for a fault tolerant power supply and investigate the possibility and merits of acquiring a direct electrical feed from Markham District Energy

·        explore the option of moving the Emergency Operations Centre to a dedicated location away from the Civic Centre

·        study the option of combining the Fire Communications Centre with the Emergency Operations Centre in future

·        look into establishing a fault tolerant off-site data centre for ITS

 

Also, the ITS Department will be requested to report back and identify the most appropriate Emergency Communications technology based on discussion with Gartner consultant group.   Corporate Communications will be requested to work with Human Resources to develop a protocol identifying what staff should do in the event of an emergency, and develop a communications plan and a training proposal.

 

The Emergency Plan will be revised to reflect that the Emergency Alerting System will be channeled through the Town’s Fire Communications Centre instead of an outside provider.

 

Human Resources Department and Deputy Fire Chief as Community Emergency Management Co-ordinator will develop a training policy and corporate training plan for staff on the subject of Emergency Management.

 

Staff identified in the Emergency Plan will be scheduled to participate in an annual emergency exercise to practise skills and knowledge of Emergency Management. Such exercises will be done in consultation with CCC and the Deputy Fire Chief as Community Emergency Management Coordinator.

 

In order to accomplish these requirements under the provincial legislation a minimum of $20,000 in additional annual funding should be considered in the 2004 Operating Budget discussions in order to revise the Emergency Plan, update the Town’s Risk analysis and conduct training and exercises on an annual basis.

 

 

FINANCIAL CONSIDERATIONS:

 

While a budget has yet to be approved for 2004, Council agreed in May of 2003 to transfer funds from a Human Resources Department Account in the amount of $20,000 towards the Emergency Management Program. This funding was used for Hazard Identification and Risk Analysis Review, a revised Emergency Plan, a Critical Infrastructure Identification Process, training, and communications plan.  It is expected that this level of additional funding will be required on an annual basis as a result of the legislated requirements of the Emergency Readiness Act.  Staff request a $20,000 allocation of additional operating funding be considered during the 2004 Budget discussions.

 

 

 

 

 

__________________________________

Shayne Mintz,

Deputy Fire Chief

 

 

 

 

 

 

 

 

Don McClean, Fire Chief

 

Jim Sales, Commissioner of Community & Fire Services

 

 

 

Q:\commexec\REPORTS\Fire\Blackout - Feb04.doc