COMMUNITY SERVICES AND ENVIRONMENT COMMITTEE

 

 

 

 

 

 

TO:

Mayor and Members of Council

 

 

 

 

FROM:

Stan Bertoia, General Manager, Construction and Utilities

 

 

 

 

PREPARED BY:

Stan Lau, Senior Project Manager

 

 

 

 

DATE OF MEETING:

2004-May-10

 

 

 

 

SUBJECT:

Subsurface Utility Engineering (SUE) and funding contribution from Greater Toronto Sewer and Watermain Contractors Association

 

 

 


 

RECOMMENDATION:

That the staff report entitled “Subsurface Utility Engineering (SUE) and funding contribution from Greater Toronto Sewer and Watermain Contractors Association” be received;

 

And that Chisholm Fleming and Associates be authorized to perform a full Subsurface Utility Engineering investigation for the Doncaster/Henderson Watermain Replacement project at a cost of $32,000 with a funding contribution of $16,000 from the Greater Toronto Sewer and Watermain Contractors Association and $16,000, funded from 2004 Capital Account # 53-6150-6019-005 for the project.

PURPOSE:

This report is submitted to Council for information and approval of applying a full SUE investigation to the Doncaster/Henderson Watermain Replacement project.

 

BACKGROUND:

For new construction or replacement of underground infrastructures, often there are potential conflicts with existing utilities. When these existing infrastructures are buried, it is often discovered in the construction phase of a project, and the cost of the conflict resolution and the potential damages are high.

 

Existing subsurface utilities and their related structures constitute a significant portion of the infrastructures within the municipal road allowance. Inaccurate, incomplete and/or out-of-date information on the existence and location of the existing subsurface utilities reduces the engineer, the owner and the contractor’s abilities to make informed decisions and increase the potential for damages and claims during construction.

 

A convergence of new equipment and data processing technologies now allows for the cost effective collection, depiction, and management of existing utility information. These technologies encompass new surveying techniques, computer-aided-design and geographic information system. This convergence of technologies and the systematic use of the data derived from these technologies is known as Subsurface Utility Engineering (SUE).

 

DISCUSSION:

Subsurface Utility Engineering has emerged as a means to better characterize the quality of underground utility information and to manage the risks associated with construction activities. SUE has been applied successfully in the past 2 decades in the USA. To date, only a few projects in Ontario have used the SUE system. The Greater Toronto Sewer and Watermain Contractors Association (GTSWCA) is actively promoting this system as it benefits both the owners, the contractors as well as the general public.

 

Staff of the Construction and Utilities have met with the GTSWCA to enter into a partnership to apply SUE to the proposed Doncaster/Henderson Watermain Replacement as a pilot project. GTSWCA initially committed $10,000 as contribution towards the cost of SUE for this project.

 

The Doncaster Avenue/Henderson Avenue area is one of the older areas in the Town of Markham and very little underground utility information is available. Doncaster Avenue is mainly a commercial area and the underground utilities/connections could be very complicated. Applying SUE to the project will benefit the engineer in detail design and the contractor in minimizing the potential damages of existing utilities and extra claims during construction.

 

Construction and Utilities staff has discussed the application of SUE with Chisholm Fleming & Associates (CFA), the Town’s consulting engineer for the Doncaster watermain replacement project, and was advised that because of the magnitude of this watermain replacement project (1,700 m in length) and the lack of existing information, the $10,000 contribution from GTSWCA will not be sufficient to carryout a complete SUE investigation. The cost for a complete SUE investigation, including identifying the actual location and depth of service connections to all properties along the route of the proposed watermain is estimated at $35,000.

 

In further negotiation with CFA, the consultant has agreed to reduce the cost to $32,000, as well, the GTSWCA has agreed to share the cost on a 50/50 basis, and to increase their funding contribution from $10,000 to $16,000. The balance in the amount of $16,000 will be funded by the Town.

 

Staff feel that the additional cost (1.4% of the estimated project cost of $1,200,000) for implementing SUE to accurately identify all the potential conflict areas, and eliminate risk to the contractor may lead to a lower bid and construction cost.

 

It is therefore recommended that a full SUE investigation be carried out on the Doncaster/Henderson Watermain Replacement project at an additional engineering fee of $32,000, with $16,000 funded by GTSWCA and $16,000 funded by the Town.

 

FINANCIAL CONSIDERATIONS:

The Town’s portion of the cost, required to carry out a full SUE investigation is $16,000. This can be funded from the Doncaster/Henderson Watermain Replacement project, Account No. 53-6150-6019-005.

 

ENVIRONMENTAL CONSIDERATIONS:

No environmental consideration.

 

BUSINESS UNITS CONSULTED AND AFFECTED:

None

 

ATTACHMENTS:

None

 

 

 

_________________________________

Stan Bertoia, P. Eng.,

General Manager, Construction and Utilities

 

 

 

 

 

 

Peter Loukes, P. Eng.,

Director of Operations and Assest Management

 

Jim Sales

Commissioner of Community Services and Fire

 

 

 

Q:\Commission Share\Operations and Asset Management\Reports\2004\C & U\Capital Works R.O.W\SUE report.doc