Tender Award - Contract 170-T-04

Construction of Monarch Park

 

 

 


 

RECOMMENDATION:

THAT the staff report entitled “Tender Award - Contract 170-T-04 Construction of Monarch Parkbe received.

 

AND THAT the tender for the construction of Monarch Park be awarded to the lowest priced and acceptable bidder, Rutherford Contracting Ltd. in their bid amount of $449,985.29 inclusive of a $3,500.00 testing allowance and 7% GST. ($420,547.00 excluding GST);

 

AND THAT a contingency in the amount of $10,000.00 be approved for this project, the use of which will be guided by the Expenditure Control Policy;

 

AND THAT funds be provided from Planning and Urban Design Department’s 2002 Capital Budget, #81-5350-4712-005, Monarch Park, in the amount of $372,400.00;

 

AND THAT in accordance with the Expenditure Control Policy, the Treasurer recommends that the over expenditure of $58,147.00 in capital account #81-5350-4712-005, Monarch Park, be authorized with offsetting funds as follows to be transferred to Capital Account #81-5350-4712-005, Monarch Park:

·        In Planning and Urban Design Department’s 2004 Capital Account #81-5350-6253-005, Granite Sand Replacement, in the amount of $15,752.00

·        From the Development Charges Reserve Fund in the amount of $38,155.50

·        In Planning and Urban Design Department’s 2002 Capital Account #81-6900-4716-005, Supplemental Park Features in the amount of $4,239.50

 

AND FURTHER THAT upon payment of all invoices, any remaining funding be returned to its original funding source.

 

PURPOSE:

The purpose of this report is to award the contract for the expansion of Monarch Park on Waterbridge Lane, in Unionville.

 

BID INFORMATION, TENDER 118-T-04:

In 2002, Council approved a budget $380,000.00 for the construction of Monarch Park. Of this budget, the actual amount available for construction is $372,400.00 after accounting for a 2% Internal Capital Administration fee of $7,600.00. 

 

In August, 2004, tender 118-T-04 was issued in accordance with Purchasing By-law 143-2000.

The tender closed on August 11, 2004 with six companies submitting bids.

 

All bids received were substantially over budget including the lowest priced and acceptable bid which was approximately $125,000.00 over budget. The magnitude of this overage was not anticipated at the time of tender since the consulting landscape architect was confident that the park, as designed, would come in close to budget. Subsequent to the tender results, staff worked with the consulting landscape architect to reduce the scope of work in an attempt to bring the project closer to the original budget amount without compromising the intent of the design or the level of service. A second tender was issued on August 27, 2004 to the original six bidders.

 

BID INFORMATION, TENDER 170-T-04:

A second tender, 170-T-04, with revised drawings and specifications, was issued in accordance with Purchasing By-law 143-2000. A consulting landscape architect prepared the specifications. The Urban Design Section of the Planning and Urban Design Department of the Development Services Commission called the second tender for the construction of Monarch Park.

 

Advertised, place and date

Direct invite to original six bidders

Bids closed on

September 3, 2004

Number picking up bid documents

6

Number attending mandatory bidder’s site meeting

Not required

Number responding to bid

5

 

The tender closed on September 3, 2004 with five (5) companies submitting bids as follows:

Company

Bid (inclusive of testing allowance and 7% GST)

Bid (inclusive of testing allowance and exclusive  of GST)

Rutherford Contracting Ltd.

$449,985.29

$420,547 00

Griffith Property Services Ltd.

$488,192.85

$456,255.00

MTM Landscaping & Snow Plowing Inc.

$473,506.89

$442,529.00

Pine Valley Enterprises Inc.

$493,848.87

$461,541.00

Mopal Construction Ltd.

No bid bond submitted

Bid not read

The award is recommended to the lowest priced and acceptable bidder, Rutherford Contracting Ltd.

While the lowest bid remains over budget, staff believe that due to increases in labour and materials since 2002, and the unique technical aspects related to expanding the existing Monarch Park, the scope of work of this project cannot be further reduced or modified beyond those modifications already made after the first tender without seriously compromising the design of the park.

FINANCIAL CONSIDERATIONS:

Staff recommends that the tender for the construction of Monarch Park be awarded to the lowest priced and acceptable bidder, Rutherford Contracting Ltd. in their bid amount of $449,985.29 inclusive of a $3,500.00 testing allowance and 7% GST. ($420,547.00 excluding GST).

 

Staff also recommends that a contingency in the amount of $10,000.00 be approved, the use of which will be guided by the expenditure control policy.

 

Funds are to be provided from Planning and Urban Design Department’s 2002 Capital Budget, #81-5350-4712-005, Monarch Park, in the amount of $372,400.

 

In accordance with the Expenditure Control Policy, the Treasurer recommends that the over expenditure of $58,147.00 in capital account #81-5350-4712-005, Monarch Park, be authorized with offsetting funds as follows to be transferred to Capital Account #81-5350-4712-005, Monarch Park:

·        In Planning and Urban Design Department’s 2004 Capital Account #81-5350-6253-005, Granite Sand Replacement, in the amount of $15,752.00

·        From the Development Charges Reserve Fund in the amount of $38,155.50

·        In Planning and Urban Design Department’s 2002 Capital Account #81-6900-4716-005, Supplemental Park Features in the amount of $4,239.50

 

Staff also recommends that upon payment of all invoices any remaining funding be returned to its original funding source.

 

BUSINESS UNITS CONSULTED AND AFFECTED:

The Finance and Purchasing Departments have reviewed this report and support the recommendations identified herein.

 

 

 

 

 

 

 

Valerie Shuttleworth, M.C.I.P., R.P.P.

Director of Planning and Urban Design

 

Jim Baird, M.C.I.P., R.P.P.

Commissioner of Development Services

 

Q:\Development\Design\linda\Parks\170-T-04 Award Report - Monarch Park.doc