` |
COMMITTEE OF THE
WHOLE |
|
|
|
|
|
|
|
|
TO: |
Mayor and Members of Council |
|
|
|
|
FROM: |
Peter Loukes, Director, Operations |
|
|
|
|
PREPARED BY: |
same as above |
|
|
|
|
DATE OF MEETING: |
|
|
|
|
|
SUBJECT: |
|
|
|
|
RECOMMENDATION:
THAT the report entitled “
AND THAT Staff be directed to continue to
monitor the damage caused by the storm and to report back to Council regularly
on the status.
PURPOSE:
Staff has prepared this report to affirm the
details of the August 19th storm event that have been presented to
Council in verbal presentations on August 29th, September 1st
and 27th.
The purpose of this report is to provide
Council with information on;
BACKGROUND:
The following
provides a background of the events and activities on
Thunderstorm Warnings issued for Markham and major storm grates
inspected
Operations Staff continually
monitor weather conditions throughout the year, utilizing Environment Canada’s
observation station at
The storm on August 19th formed from severe weather in
According to our
research on the events of that day, severe weather was being forecast for
Storm Drainage Systems
Like all municipalities in
Generally storm sewers are designed
to accommodate a 5 year design storm which would operate without surcharge
during a 100 year storm event. Inlet
control devices are utilized to control the flow of water into the storm sewer
system to prevent surcharging during major storm events. Major storm systems are designed to
accommodate a 100 year design storm that convey overland flows to storm water
management ponds and/or natural or manmade conveyance systems without threat of
flooding to private property.
Intense rainfall in some areas of
There are several rain gauges
located around the Town and monitored and maintained by different
agencies. Here are the results of the
rainfalls on August 19th from those gauges.
Location |
Operated by |
Rainfall Observed |
Period |
|
Region
of |
105mm
(4.13 in) |
3 hours |
Armadale
CC |
Town of
|
98 mm
(3.85 in) |
2 hours |
Civic
Centre |
Town of
|
75mm
(2.95 in) |
2 hours |
|
Environment
|
54mm
(2.13 in) |
All day |
Royal
Orchard & Bayview |
Private |
133mm (5.24) |
2 hours |
Yonge
& Steeles |
Private |
175mm (6.89) |
All day |
Based on the Town’s storm design
criteria the rainfall expected from a 100 year return storm would be estimated
at 68mm (or 2.68 inches) in 2 hours and 73mm (or 2.87 inches) in 3 hours. For all rain stations south of
DISCUSSION:
Widespread Damage
The majority of the damage to the infrastructure was restricted to the area south of Highway 407, with localized areas throughout the Town. Thornhill received the bulk of the damage, which consisted of flooded roads, watercourses, stormwater management ponds, basements, trees blown down, or eroded to the extent that they fell.
Immediate action taken by Operations staff
On the evening of August 19th, Operations staff responded to a great number of flooding calls; streets flooding, basements flooded, manhole covers displaced, culverts blocked, storm grates covered with debris, shoulders/driveways eroded and trees down. Once the rain and flooding subsided, work crews cleared felled trees and branches from roads, cleaned storm and catch basin grates to remove any restrictions and replaced manhole lids.
Where staff either found or were informed by residents of potential hazardous conditions where roads, bridges, and pathways were washed out, they undertook to place barricades, and signage identifying lane closures, and or unsafe conditions. These locations were monitored throughout the weekend to ensure barriers remained in-place.
Upgraded Standby
Workforce put in place
On the evening of the storm, nineteen Operations staff remained on duty and kept the Operations phone line open to assist the Contact Centre and Information Markham with overflow calls and respond to emergencies.
The staff was coordinated to
respond to the storm throughout the evening of
Contractors who provide various equipment and services were put on notice that they may be required that evening or throughout the weekend. On the evening of the storm loaders and backhoes were mobilized to clear the major storm grates of debris and to assist with drainage
Emergency Operations
Centre Activated
The Town Emergency Plan was activated and through consultation with the Mayor, a selected portion of the Markham Control Group (MCG) was put on alert and asked to assemble at the Emergency Operations Centre on Saturday, August 20th. The MCG, chaired by Commissioner Sales, co-ordinated the ongoing response, identified damaged areas and additional resources required to reinstate our infrastructure. Additional meetings were held the following week and the chair has been updating Council and senior staff on a regular basis.
Follow up and ongoing repairs to infrastructure
To date the Operations Department
has completed numerous repairs to address road base failures and damaged
asphalt surfaces throughout sections of the Town located between
Waterworks staff have completed sewer flushing and visual inspection of sanitary systems in the hardest hit areas.
The Operations Department has
several locations where the effects of the storm have caused severe damage to
watercourses, pedestrian bridges and pathways.
The Operations and Asset Management group will continue to work with
external agencies including the
|
|
|
Director, Operations |
|
Jim
Sales, Commissioner, Community and Fire Services |
Q:\Commission Share\Operations and Asset Management\Reports\2005\Peter Loukes\August 19.Storm Report for Peter.doc