FINANCE AND ADMINISTRATIVE COMMITTEE

 

 

 

 

 

TO:

Mayor and Members of Council

 

 

 

 

FROM:

Stan Bertoia, General Manager, Construction and Utilities

Catherine Conrad, Town Solicitor

 

 

 

 

PREPARED BY:

Stan Lau, Senior Project Manager

Ophir Bar-Moshe, Assistant Town Solicitor

 

 

 

 

DATE OF MEETING:

2003-November-17

 

 

 

 

SUBJECT:

169-T-03 Jennings Gate Estates Municipal Water System-Tender Award

 

 

 


RECOMMENDATION:

That the staff report entitled “ 169-T-03 Jennings Gate Estates Municipal Water System-Tender Award” be received;

 

That the contract for Jennings Gate Estates Municipal Water System be awarded to Kapp Contracting Ltd. for the amount of $928,602.71 (inclusive of 7%G.S.T.) being the lowest acceptable bid received ($893,888.59 inclusive of 3% G.S.T.);

 

THAT tender 169-T-03 Jennings Gate Estate, Municipal Water System be awarded to the lowest priced bidder, Kapp Contracting Inc. in their tender amount of $928,602.71 inclusive of $80,000.00 contingency and 7% GST ($893,888.59 inclusive of $80,000.00 contingency and 3% GST);

 

That the Jennings Gate Estates Municipal Water System proceed and the total cost of the work in the estimated amount of $1,047,290 be recovered by imposing an equal fee against each of the property owners abutting the works in accordance with Section 391 of the Municipal Act 2001;

 

That the cost for construction, engineering, easements and all related administration costs at a total estimates amount of $1,047,290 be front-ended by the Town from the Waterworks reserve and recovered from the benefiting property owners with appropriate interest;

 

That any cash compensation from the Region of York be considered as funding contribution to the Town or property owners and the total project cost be adjusted accordingly;

 

That the actual construction cost, the easement cost, all the engineering and related administrative and financing costs front-ended by the Town form part of the total project cost and recovered in accordance with the requirements of Section 391 of the Municipal Act and the by-law approved by Council;

That the Jennings Gate Estates Municipal Water System proceed and the total cost of the work in the estimated amount of $1,082,000  be1,082,000 be recovered by imposing an equal fee against each of the property owners abutting the works in accordance with Section 391 of the Municipal Act 2001;.

 

And that the actual construction cost, the easement cost, all the engineering and related administrative and financing costs front-ended by the Town form part of the total project cost and recovered in accordance with the requirements of Section 391 of the Municipal Act and the by-law approved by Council.

 

 

That the necessary Fee By-law and other necessary documents for the Jennings Gate Estates Municipal Water System be prepared in accordance with the requirements of Section 391 of the Municipal Act, 2001;

 

That the contract with Mitchell Hatt & Associates Inc. be extended in accordance with Purchasing By-Law 143-2000, Section 14 (1) (c) which states “…the extension of an existing contract would prove more cost-effective or beneficial”.  The extended contract will provide site supervision and contract administration services for the project at an estimated cost of  $50,000

 

That Finance Department be authorized to arrange the necessary financing for the project;

 

[And report back on recovery provisions in the proposed by-law, interest rate, etc.….]

 

And that the actual construction cost, the easement cost, all the engineering and related administrative and financing costs front-ended by the Town form part of the total project cost and recovered in accordance with the requirements of Section 391 of the Municipal Act and the by-law approved by Council.

 

PURPOSE:

The purpose of this report is to obtain Council’s approval to proceed with the Jennings Gate Estates Municipal Water System and recover the costs of such works in accordance with Section 391 of the Municipal Act.

 

BACKGROUND:

In December 2002, the Ratepayers Association of Jennings Gate Estates submitted an informal residents survey requesting the Town to proceed with the design of a municipal watermain system for Jennings Gate Estates under the Local Improvement Act (LIA). Based on the informal survey, 51out of the 61 homeowners (84%) were in support of the watermain request. Residents also indicated their preference for equal cost sharing per property instead of charges based on individual frontage (Appendix A).

 

At its meeting of February 25, 2003, Council approved a staff report entitled “Jennings Gate Estates Municipal Water system”. The report recommended the hiring of an engineering consultant to design and prepare a tender for the project. The report also indicated that when the contract price is known, staff will advise the residents of Jennings Gate Estates of the total estimated project cost and the amountcost to be levied against the property owners. The residents were to be requested to submit a formal petition whether to proceed with construction of the work or not.

 

In April this year, staff retained Mitchell Hatt & Associates Inc. to prepare the design and tender documents for the project. Tender was called and four bids were received and opened by the Town Clerk on September 3, 2003.

 

Based on the lowest, acceptable tender price and adding all the estimated engineering, easement and administration costs in accordance with the Local Improvement requirements, the estimated per metre frontage cost and the cost for each lot based on the Local Improvement requirements was calculated and is shown in Appendix B.  Since the Local Improvement Act has strict guidelines on the calculation of frontage charges that can be levied, there is a wide range of costs to the property owners varying from $11,000 to $23,000 per lot.

 

OPTIONS/DISCUSSION

Implementation Options

There are three options available to the Town for undertaking the watermain and raising the cost for the work:

 

1.   Local Improvement charges in accordance with Ontario Regulation 119/03 made under the Municipal Act, 2001;

 

2.   Special service charges under Section 326 of the Municipal Act, 2001; or

 

3.   A fee under s.391 of the Municipal Act, 2001

 

Option 1: Local Improvement Charges

The Town may pass a by-law to raise all or any part of the cost of local improvement work by imposing special charges on lots abutting on the work. Local improvement charges are assessed against owners according to the extent of their frontage by imposing an equal charge per meter frontage.

 

 

There are four ways in which local improvement work may be undertaken:

1.      By a sufficient petition in favour of the work;

2.      By Council without a petition;

3.      By Council on health grounds;

4.      By Council without petition with the approval of the Ontario Municipal Board (“OMB”)[1]

 

1 In the absence of a sufficient petition in favour of the work, a municipality may seek the approval of the OMB to protect itself from possible petition against the work which would prevent it from undertaking the work for at least two years.

 

A sufficient petition in favour of the work would eliminate the threat that the work will have to be stopped because of a petition against the work. 

 

A local improvement by-law must contain an estimated cost of the work, the owners’ share of the cost and the municipality’s share of the cost. Any changes to the works after a by-law is approved have to be approved by the OMB.

 

Before passing a by-law to undertake the work, Council must:

 

1.      procure a report prepared by an engineer and provide for the preparation of the assessment roll. Once Council adopts the engineer’s report, it can enact a by-law authorizing the work; and

 

2.      give notice of its intention to pass the by-law to the public and the owners of the lots liable to be specially charged.

 

After the work is completed and its exact cost is known, a special assessment roll is prepared for imposing the charges. The special assessment is then reviewed by a court of revision and confirmed or modified. Homeowners who object to the proposed assessment have a right to a hearing before the court of revision. The court has power to modify the roll and any reductions made in the assessment to the owners will be added to the Town’s share of the cost.  If the court of revision certifies the roll prior to the completion of the work, the municipality will be responsible for the difference between the actual and estimated cost.

 

Where the special assessment roll is certified, a by-law passed for borrowing money or imposing special charges with respect to the work cannot be quashed, set aside or be found invalid on the basis that it is illegal or for any other defect in it.

 

Advantages re Local Improvements

 

1.      Local improvement charges amount to a tax and have a priority lien status. They can be collected in the same manner as taxes;

 

2.      Allows ratepayers an opportunity to challenge the proposed local improvement roll.

 

Disadvantages re Local Improvements

 

1.      Process: Cumbersome process requiring the Town to give notice to the landowners of its intention to pass a by-law to undertake the work. Prior to the charges being imposed, the Town will have to give notice of a hearing by a court of revision (see 3 below) respecting any objections to the proposed roll;

 

2.      Mandatory municipal cost: The Town in this case will have to pay for the entire cost of fire hydrants, which is estimated at $74,000;

 

3.      Changes to charges: The Town will need to establish a court of revision to hear any objections or revisions to the proposed local improvement roll. A notice of such hearing has to be given to the public and landowners involved. The court of revision has power to modify the roll. Any reductions made in the owners’ assessment are required to be added to the Town’s share of the cost;

 

4.      Calculation of Charges: Applying the legislative scheme will not result in an equal charge per lot. The Regulation requires that owners abutting directly on the work be assessed according to the extent of their frontage by imposing an equal special charge per meter frontage. Reductions or increases in charges are permitted in certain cases. For example:

 

(i)                  reductions must be made in the case of a corner lot that has flankage and frontage and all or part of the work that abuts the flankage is of no benefit to the lot;

 

(ii)                reductions or increases must be made in the case of triangular or irregularly shaped lots having regard to the situation, value and area of the lot as compared with the other lots based on a just and equitable basis.

 

The Regulation does not allow a municipality to increase the charges for regularly shaped lots. In order to impose an equal charge on each of the 61 lots in Jennings Gate, the Town would have to increase the charges imposed on regularly shaped lots that have a lower than average frontage (e.g. lots 13-16, 40, 49, 55 and 56). This is not authorized under Regulation 119/03.

 

Based on the lowest, acceptable tender price and adding the estimated engineering, easement and administration costs, the estimated per metre frontage cost and the cost for each lot based on the Local Improvement requirements was calculated and is shown in Appendix B.  Since the Local Improvement Act has strict guidelines on the calculation of frontage charges that can be levied, there is a wide range of costs to the property owners varying from $11,000 to $23,000 per lot.

 

There are a total of 61 lots in the Jennings Gate Estates and the total chargeable frontage, based on the subdivision by-law, is 3209 metres. In accordance with the Local Improvement Act, the Town is responsible for approximately $74,000 of the estimated cost for installation of fire hydrants.

 

Option 2: A Special Service Charge

Section 326 of the Municipal Act, 2001 allows a municipality to enact a by-law to impose a special service charge to raise the cost of providing a water system. Such bylaw has to identify the service, determine the costs and designate the area where the charge would apply.

 

Charges are levied by by-law as a separate tax rate on the assessed value of each rateable property in the area designated in the by-law.

 

Advantages re Special Charge

1.      Special charges are a form of tax and therefore have priority lien status. Unpaid charges could be collected by way of a tax sale;

2.      There is no statutory appeal mechanism to challenge the by-law (application to the courts to quash the by-law is possible, but will not likely succeed if the legislative scheme was adhered to);

3.      Unlike local improvement charges, there is no mandatory municipal share of the costs;

 

Disadvantage re Special Charge

1.      Applying the legislative scheme will not result in an equal charge per lot. Charges are based on assessment values. The assessment value in the case of Jennings Gate varies considerably. For example, one of the lots is assessed at $604,000 while another is assessed at over $1.7 million;

 

Option 3: Fees By-law

Section 391 of the Municipal Act, 2001 allows a municipality to pass a by-law to impose a fee for capital costs related to sewage or water services on a class of persons that will receive a benefit from such services. Unlike a local improvement charge or special service charge, a fee imposed pursuant to section 391 does not have to be based on frontage or assessed value. This provision would enable the Town to impose a fixed charge on each of the lots in question.  

 

A fee by-law may provide for interest charges and other penalties for fees that are due and unpaid. Fees may be added to the tax roll and collected in the same manner as taxes. They do not however have a priority lien status and a tax sale is not available. 

 

Advantages re Fees By-law

1.      Simplified process. Council has to pass a by-law in accordance with s.391 of the Municipal Act, 2001;

2.      Unlike local improvement charges, there is no mandatory municipal share of the costs;

3.      A flat and equal fee could be charged on each of the 61 lots in Jennings Gate notwithstanding that they differ in frontage, size, or assessed value;

4.      No application can be made to the Ontario Municipal Board on the grounds that the fee imposed is unfair or unjust;

 

Disadvantages re Fees By-lawFees and charges imposed by a municipality do not have priority lien status and a tax sale is not available for unpaid fees. However, all other collection tools are still available to the Town.  Because such fees are added to the tax roll, any future purchasers who request a tax certificate from the Town would be notified of such fees. In such cases, any outstanding fees will likely be settled prior to the property being conveyed or assumed by the new owner. Risk of non-recovery of fees would also be mitigated depending on the number of owners who choose to pay the entire fee in a lump sum payment.

It is understood that the majority of the residents in Jennings Gate Estates are of the opinion that an equal fee should be imposed on each of the 61 lots involved. If this is the primary objective and the Town is willing to accept the risk associated with such fees not having priority lien status as described above, then it is recommended that the Town should proceed with Option 3 and enact a fee by-law.   In all three options, although the homeowners have to pay their share of the project cost, they do not have to connect to the municipal watermain, and can keep the well for drinking purposes.

 

Construction Tender

All bids were issued in accordance with the purchasing by-law 143-2000. The award is being awarded to the lowest priced bidder.

Advertised, place and date

Daily Commercial News and Electronic Tender Network (ETN)

Bids closed on

September 3, 2003

Number picking up bid documents

5

Number responding to bid

4

 

Four companies submitted qualified bids. 

Companies

Inclusive of $80,000 contingency & 7% GST

Inclusive of $80,000 contingency & 3% GST

Kapp Contracting Ltd.

$   928,602.71

$   893,888.59

Trisan Construction

$1,224,910.32

$1,179,119.28

Power Contracting Limited

$1,350,513.34

$1,300,026.86

Hollingworth Construction*

$1,564,201.97

$1,505,727.13

 

All tenders were checked for errors and omissions.  *Hollingworth’s bid was corrected for mathematical error.  Reference checks were made on the previous performance of Kapp Contracting Ltd. and the result was satisfactory.  Therefore, it is recommended that the contract be awarded to the lowest priced bidder Kapp Contracting Ltd. in the amount of $928,602.71 inclusive of $80,000.00 contingency and 7% GST ($893,888.59 inclusive of $80,000.00 contingency and 3% GST).

 

Total Project Costs

Using the lowest tendered price, the estimated total project costs are summarized below: Construction…………………………………………………………$893,890* (3% GST)

Engineering Fees (Design)…………….…………………………….$  48,400   

Engineering Fees (Inspection/Contract admin.)……………………...$ 50,000               

Easement Costs (Ontario Hydro/Private owner)……………………..$ 20,000

Easement Admin./Registration Fees……………………………….…$  8,000  

Admin. Cost (Town staff)…………………………………………….$ 20,000   

Admin. Costs (Tendering, Advertising, Notices, etc)………………….$ 7,000             

                                                                                Total Project Cost……………….$1,047,290                                                    

         * Service connection from the main to property line is included in the construction cost.There are a total of 61 lots in the Jennings Gate Estates and the total chargeable frontage, based on the subdivision by-law, is 3209 metres. If calculated in accordance with the Local Improvement Act, the Town is responsible for approximately $74,000 of the estimated cost for installation of fire hydrants.

 

Implementation Options

There are three options available to the Town for undertakingundertaking the watermain works in question and raising the cost for theof such work:

 

1.   Local Improvement charges in accordance with Ontario Regulation 119/03 made under the Municipal Act, 2001;

 

2.   Special service charges under Section 326 of the Municipal Act, 2001; or

 

3.   A fee under s.391 of the Municipal Act, 2001

 

Option 1: Local Improvement Charges

The Town may pass a by-law to raise all or any part of the cost of local improvement work by imposing special charges on lots abutting on the work. Local improvement charges are assessed against owners according to the extent of their frontage by imposing an equal charge per meter frontage.

 

There are four ways in which local improvement work may be undertaken:

 

1.By a sufficient petition in favour of the work;

1.By Council without a petition;

1.By Council on health grounds;

1.By Council without petition with the approval of the Ontario Municipal Board (“OMB”)[2]

 

A sufficient petition in favour of the work would eliminate the threat that the work will have to be stopped because of a petition against the work. 

 

A local improvement bBy-law must contain an estimated cost of the work, the owners’ share of the cost and the municipality’s share of the cost. Any changes to the works after a bBy-law is approved have to be approved by the OMB.

 

Before passing a bBy-law to undertake the work, Council must:

 

1.procure a report prepared by an engineer and provide for the preparation of the assessment roll. Once Council adopts the engineer’s report, it can enact a bBy-law authorizing the work; and

 

1.give notice of its intention to pass the by-law to the public and the owners of the lots liable to be specially charged.

 

After the work is completed and its exact cost is known, a special assessment roll is prepared for imposing the charges. The special assessment is then reviewed by a court of revision and confirmed or modified. Homeowners who object to the proposed assessment have a right to a hearing before the court of revision. The court has power to modify the roll and any reductions made in the assessment to the owners will be added to the Town’s share of the cost.  If the court of revision certifies the roll prior to the completion of the work, the municipality will be responsible for the difference between the actual and estimated cost.

 

Where the special assessment roll is certified, a by-law passed for borrowing money or imposing special charges with respect to the work cannot be quashed, set aside or be found invalid on the basis that it is illegal or for any other defect in it.

 

Advantages re Local Improvements

 

1.Local improvement charges amount to a tax and have a priority lien status. They can be collected in the same manner as taxes;

 

1.Allows ratepayers an opportunity to challenge the proposed local improvement roll.

 

Disadvantages re Local Improvements

 

1.Process: Cumbersome process requiring the Town to give notice to the landowners of its intention to pass a by-law to undertake the work. Prior to the charges being imposed, the Town will have to give notice of a hearing by a court of revision (see 3 below) respecting any objections to the proposed roll;

 

1.Mandatory municipal cost: The Town in this case will have to pay for the entire cost of fire hydrants, which is estimated at $74,000;

 

1.Changes to charges: The Town will need to establish a court of revision to hear any objections or revisions to the proposed local improvement roll. A notice of such hearing has to be given to the public and landowners involved. The court of revision has power to modify the roll. Any reductions made in the owners’ assessment are required to be added to the Town’s share of the cost;

 

1.Calculation of Charges: Applying the legislative scheme will not result in an equal charge per lot. The Regulation requires that owners abutting directly on the work be assessed according to the extent of their frontage by imposing an equal special charge per meter frontage. Reductions or increases in charges are permitted in certain cases. For example:

 

(i)reductions must be made in the case of a corner lot that has flankage and frontage and all or part of the work that abuts the flankage is of no benefit to the lot;

 

(i)reductions or increases must be made in the case of triangular or irregularly shaped lots having regard to the situation, value and area of the lot as compared with the other lots based on a just and equitable basis.

 

The Regulation does not allow a municipality to increase the charges for regularly shaped lots. In order to impose an equal charge on each of the 61 lots in Jennings Gate, the Town would have to increase the charges imposed on regularly shaped lots that have a lower than average frontage (e.g. lots 13-16, 40, 49, 55 and 56). This is not authorized under Regulation 119/03.

 

Option 2: A Special Service Charge

Section 326 of the Municipal Act, 2001 allows a municipality to enact a by-law to impose a special service charge to raise the cost of providing a water system. Such bylaw has to identify the service, determine the costs and designate the area where the charge would apply.

 

Charges are levied by by-law as a separate tax rate on the assessed value of each rateable property in the area designated in the by-law.

 

Advantages re Special Charge

 

1.Special charges are a form of tax and therefore have priority lien status. Unpaid charges could be collected by way of a tax sale;

 

1.There is no statutory appeal mechanism to challenge the by-law (application to the courts to quash the by-law is possible, but will not likely succeed if the legislative scheme was adhered to);

 

1.Unlike local improvement charges, there is no mandatory municipal share of the costs;

 

 

 

 

 

Disadvantage re Special Charge

 

1.Applying the legislative scheme will not result in an equal charge per lot. Charges are based on assessment values. The assessment value in the case of Jennings Gate varies considerably. For example, one of the lots is assessed at $604,000 while another is assessed at over $1.7 million;

 

Option 3: Fees By-law

Section 391 of the Municipal Act, 2001 allows a municipality to pass a by-law to impose a fee for capital costs related to sewage or water services on a class of persons that will receive a benefit from such services. Unlike a local improvement charge or special service charge, a fee imposed pursuant to section 391 does not have to be based on frontage or assessed value. This provision would enable the Town to impose a fixed charge on each of the lots in question.  

 

A fee by-law may provide for interest charges and other penalties for fees that are due and unpaid. Fees may be added to the tax roll and collected in the same manner as taxes. They do not however have a priority lien status and a tax sale is not available. 

 

Advantages re Fees By-law

 

1.Simplified process. Council has to pass a by-law in accordance with s.391 of the Municipal Act, 2001;

1.Unlike local improvement charges, there is no mandatory municipal share of the costs;

1.A flat and equal fee could be charged on each of the 61 lots in Jennings Gate notwithstanding that they differ in frontage, size, or assessed value;

1.No application can be made to the Ontario Municipal Board on the grounds that the fee imposed is unfair or unjust;

 

Disadvantages re Fees By-law

 

1.Fees and charges imposed by a municipality do not have priority lien status. A tax sale is not available for unpaid fees.

 

It is understood that the majority of the residents in Jennings Gate Estates are of the opinion that an equal fee should be imposed on each of the 61 lots involved. If this is the primary objective and the Town is willing to accept the risk associated with such fees not having priority lien status as described above, then it is recommended that the Town should proceed with Option 3 and enact a fee by-law. 

 

Retaining of Consultant

TDue to staff shortage, the service of an outside engineering consultant is required to provide site supervision and contract administration is required for this project.  Since Mitchell Hatt Associates Inc. was the consulting engineer for the design and preparation of tender documents for the project, it is recommended that the firm be retained to provide the site supervision and contract administration services in accordance with Purchasing By-Law 143-2000, Section 14 (1) (c) which states “…the extension of an existing contract would prove more cost-effective or beneficial”.

 

The estimated fees of $50,000 (approx. 5% of construction cost) by Mitchell Hatt Associates Inc. for provision of site supervision and contract administration is considered reasonable for projects of this size and nature.

 

Abandonment of existing wells

Some residents have asked whether they would be allowed to retain their existing water well, after connecting to the municipal water system, for the purposes of watering the lawn, refilling the swimming pool etc. Staff have consulted with the Ministry of Environment and the York Region Health Unit and have been advised that at present, there are no Provincial Regulation/Policy or Directive requiring the residents to abandon their wells, as long as they are not connected to the municipal water system and are maintained and in use.

Therefore, although staff have concerns regarding private cross connection by the property owners (intentionally or unknowingly) and possible contamination of the municipal water system, or potential ground water contamination from the septic tile beds, the Town or MOE cannot force the residents to decommission their existing wells.

 

The estimated fees of $50,000 (approx. 5% of construction cost) by Mitchell Hatt Associates Inc. for provision of site supervision and contract administration is considered reasonable for projects of this size and nature.

 

FINANCIAL CONSIDERATIONS:

TSince the Town is required to front-end the cost of this project in the estimated amount of $1,047,290 and recover the cost from the local residents. The project can be funded from Waterworks  reserve and paid back with appropriate interest (or approx. $17,170 per lot based on onetime payment, no interest).  In addition, there will be easements required to loop the watermain on Hydro One and a privately owned land.  These associated costs have been estimated and included in the total project cost.  Residents would have the option of paying the full amount at the time of connection or over 10 years with interest payable at the 10 Year Region of York Debenture Interest Rate.

 

Region of York Financial Mitigation

With respect to the proposed phase II trunk sanitary sewer construction on 16th Avenue by the Region of York and its potential impact on the existing wells in Jennings Gate Estates, the Town is currently in negotiation with ROY for cash compensation. Any such cash settlement will be considered as funding contribution to the Town or property owners and the total project cost will be adjusted accordingly.

 

ENVIRONMENTAL CONSIDERATIONS:

No adverse environmental impact is expected since all works are located within the existing Rights-oOf-Way.

 

 

 

 

 

 

BUSINESS UNITS CONSULTED AND AFFECTED:

The Clerks Department and the Legal Department have been consulted,  on this project and have provided input and reviewed this reportt.  The Finance Department has reviewed and concurredred with this report.

 

 

 

 

 

 

Should Council approve this project, the Clerks Department in consultation with the Legal and Finance Department will be required to prepare and publish the Fees By-law with all the terms and conditions in accordance with Section 391 of the Municipal Act 2001.

 

 

ATTACHMENTS:

Appendix ‘A’ – Letter from Ratepayers Association

Appendix ‘B’ – Frontage Charges Table

 

 

 

 

__________________________________                     ________________________________  

Stan Bertoia, P. Eng.                                                         Catherine M. Conrad

General Manager, Construction and Utilities                        Town Solicitor

 

 

 

 

 

 

 

Peter Loukes, P.Eng.

 

Jim Sales

Director of of Operations and Asset Management        Commissioner of Community and Fire

                                                                                           Services

Q:\Finance and Administration\Finance\Purchasing\2003 File Management\Contract Management\169-T-03 Jennings Gate Muncipal Water System\169-T-03 Award Report F & A.doc

 



[1] In the absence of a sufficient petition in favour of the work, a municipality may seek the approval of the OMB to protect itself from a possible petition against the work which would prevent it from undertaking the work for at least two years.

[2] In the absence of a sufficient petition in favour of the work, a municipality may seek the approval of the OMB to protect itself from a possible petition against the work which would prevent it from undertaking the work for at least two years.