TO: |
Mayor and Members of Council |
|
|
|
|
FROM: |
Joel Lustig, Director, Financial and Client Services |
|
|
|
|
PREPARED BY: |
Jennifer Nelson, Manager, Development Finance |
|
|
|
|
DATE OF
MEETING: |
2004-Mar-22 |
|
|
|
|
SUBJECT: |
Markham Village Library Expansion Funding and Analysis |
|
|
|
RECOMMENDATIONS:
THAT the report “Markham Village Library Expansion Funding and Analysis” be received;
AND THAT
Council approve the design of Option 1 as recommended in the “Markham Village
Library Expansion” report presented at the Committee of the Whole on March 9,
2004;
AND THAT Council approve the renovation of the existing Library to be
undertaken at the same time as the new construction, at an estimated cost of
$2,266,000 (inclusive of 3% GST), to be funded from the proposed GST rebate of
approximately $1,150,000 and the remaining funding to be determined by the
Budget Sub-Committee through the review of the 2004 Budget;
AND FURTHER THAT the funding analysis on the
Recreation and Culture, Library and Fire Construction Program be received for
information purposes;
PURPOSE:
The purpose of this report is to identify the funding sources for Option 1 and 3 as presented to the Committee of the Whole on March 9, 2004, and to address the importance of considering and prioritizing the Recreation and Culture, Library and Fire Construction Programs that will be competing for the limited development charge, non-development charge, and operating budget dollars.
BACKGROUND:
At Committee of the Whole on March 9, 2004, Council was
presented with three options for the Markham Village Library Expansion. The recommendation of Council was “that
consideration of the matter be referred to the March 22, 2004 Finance and
Administrative Committee meeting for consideration; and that, at that time,
staff report on detailed funding alternatives including alternatives to support
Option 3 - expansion to the north with a link to the arena.”
FINANCIAL
CONSIDERATIONS:
The
Town of Markham has been in construction mode since 2002 and will continue to
be for the next several years. There
are limited funding sources available, both development charge and
non-development charge and the majority of the projects have an operating
impact. Option 3 of the Markham Village
Library Expansion should not be considered in isolation of the competing
requests that exist.
As
the projects identified below proceed, Council will be presented with many
recommendations and options for consideration. The challenge to Council in receiving these requests
independently, is weighing the benefit versus the impact that each request may
have on future projects. It is
imperative that Council prioritizes the construction program, and consider each
project with an awareness of the other competing priorities that exist.
There
are two main sources from which to fund the non-development charge component of
these projects: the tax base and
reserves. For example, the Hydro
reserve may be the solution for capital projects that require tax funding
however staff recommend that the use of Hydro reserves be deferred until the
results of the Reserve Study currently underway and the associated proposed
policies for the use of reserves have been provided to Council. The operating and capital budgets are both
constrained by the capacity to increase property taxes.
The Town of Markham currently has four projects either under
construction or approved in the capital budget:
·
Angus Glen Community Centre and Library;
·
Thornhill Community Centre Expansion Phase 1;
·
George Pingle House Renovation and Expansion;
·
Markham Museum Reception Centre;
In addition to the Markham Village Library Expansion, Council will be
facing decisions on the following construction projects in 2004:
Projects submitted for consideration in the 2004 capital budget that
are currently below the line, will also require a decision from Council. The two major projects are the Centennial
Community Centre Renovations, and the land acquisition for the proposed
Community Centre at Hwy 48 and 14th Avenue.
|
|
|
Funding
Sources
|
||
Project |
Est. Sq. Ft |
Total |
DC |
Non DC |
Net
Operating
Budget |
|
|
$000's |
$ 000's |
$ 000's |
$ 000's |
Recreation
Facilities: |
|
|
|
|
|
Centennial CC Renovation |
|
2,040 |
|
2,040 |
|
Milliken Mills CC Expansion |
14,000 |
3,178 |
2,860 |
318 |
100 |
Rouge River CC Renovations |
|
570 |
513 |
57 |
|
YMCA |
20,000 |
2,700 |
2,430 |
270 |
|
Hwy. 48/14th Ave CC |
145,000 |
33,930 |
30,537 |
3,393 |
1,030 |
East Community Centre |
150,900 |
35,310 |
31,780 |
3,530 |
1,070 |
East Olympic Pool |
80,000 |
28,000 |
25,200 |
2,800 |
600 |
Indoor Soccer Field & Gym |
61,800 |
15,326 |
13,793 |
1,533 |
450 |
Library
Facilities: |
|
|
|
|
|
Markham Village Library Renovation |
|
2,266 |
|
2,266 |
|
Milliken Mills Library Expansion |
6,300 |
1,430 |
1,287 |
143 |
300 |
East Markham Library |
20,000 |
4,680 |
|
4,680 |
950 |
Markham Centre Library |
60,000 |
15,300 |
13,770 |
1,530 |
2870 |
Fire
Stations: |
|
|
|
|
|
New Fire Station - Cornell |
10,000 |
2,270 |
2,270 |
|
1,500 |
New Fire Station - Cathedral |
10,000 |
2,340 |
2,340 |
|
1,500 |
New Fire Station - Markham Centre |
10,000 |
2,410 |
2,410 |
|
1,500 |
Other: |
|
|
|
|
|
Theatre Expansion |
|
7,100 |
|
7,100 |
60 |
Museum Master Plan Implementation (1) |
|
TBD |
|
|
TBD |
Outdoor Artificial Rink (1) |
|
TBD |
|
|
TBD |
Markham Centre (1) |
|
TBD |
|
|
|
Living Arts Centre (1) |
|
TBD |
|
|
TBD |
Parking Authority (1) |
|
TBD |
|
|
TBD |
|
588,000 |
158,850 |
129,190 |
29,660 |
11,930 |
OPTION
1—PRELIMINARY PROJECT COST ESTIMATE
Option 1 provides a two-storey addition with half basement to the south of the Existing Library. In order to analyze each element of Option 1, the following chart illustrates the elements/components of Option 1 as a construction project:
|
Element Description |
Preliminary Cost Estimate |
1 |
New Construction (the two upper levels of the addition plus the shell of the half-basement) and Site Work |
$3,821,300 |
2 |
Finishing the half-basement level of the addition to be occupied by the Library’s ATS |
$530,450 |
3 |
Renovation of the existing building’s 3 levels |
$2,266,000 |
|
TOTAL
|
$6,617,750 |
FUNDING
SOURCES:
|
|
|
|
|
|
|
|
|
|
|
Preliminary
Cost |
|
Funding Sources |
||||
|
Description |
Estimate |
|
DC
|
|
Reserve
|
|
Other
|
|
$3,821,300 |
|
$3,439,170 |
|
$382,130 |
|
|
|
|
Finishing for Library ATS |
$530,450 |
|
|
|
|
|
$530,450 |
|
Renovation of Existing building |
$2,266,000 |
|
|
|
|
|
$2,266,000 |
|
Total
|
$6,617,750 |
|
$3,439,170 |
|
$382,130 |
|
$2,796,450 |
|
|
|
|
|
|
|
|
|
The New Construction of the Library would be
funded 90% from Development Charges ($3,439,170) and the remaining 10%
($382,130) funded from a Reserve previously established to fund the mandatory
10% non-development Charge component of construction projects.
The finishing of the basement for the Library
ATS ($530,450) would be funded from the elimination of the annual operating
lease, until fully offset.
The renovation of the existing building
($2,266,000) would be funded from the proposed GST rebate of approximately
$1,150,000 and the remainder to be determined through the review of the 2004
budget by the Budget Sub-Committee.
OPTION
3—PRELIMINARY PROJECT COST ESTIMATE
Option 3 provides a two-storey addition on a slab-on-grade foundation, to the north of the Existing Library. It requires the construction of new public meeting rooms to replace the current public meeting rooms displaced by ATS moving into the existing basement. A north-south internal street links the Existing Arena and the new Library addition. In order to analyze each element of Option 3, the following chart illustrates the elements/components of Option 3 as a construction project:
|
Element Description |
Preliminary Cost Estimate |
|
BASE BUILDING & SITE WORK |
|
1 |
10,500 sq. ft. of new public library space as per the original projection |
$3,115,750 |
2 |
5,250 sq. ft. of new ground floor public meeting/program rooms required to replace the existing program rooms |
$1,236,000 |
|
RENOVATION OF EXISTING BUILDING |
$2,266,000 |
3 |
Renovation of the existing building’s 3 levels |
|
|
LINK TO ARENA |
$2,884,000 |
4 |
Link to the Arena, including alterations to the Arena and relocated services |
|
|
TOTAL
|
$9,501,750 |
The preliminary cost estimate for Element 4 ($2,884,000) contains the following items:
· New Link to Arena (Interior Street) |
$2,111,500 |
· Alterations to Existing Arena |
$515,000 |
· Relocation of Ice Making Equipment and New Façade to Transformer Vault |
$257,500 |
|
$2,884,000 |
FUNDING
SOURCES:
|
Preliminary
Cost |
|
Funding Sources |
||||
Description |
Estimate |
|
DC |
|
Reserve |
|
Other |
New Construction (incl. Site work) |
$4,351,750 |
|
$2,804,175 |
|
$311,575 |
|
$1,236,000 |
Renovation of Existing building |
$2,266,000 |
|
|
|
|
|
$2,266,000 |
Link to Arena
|
$2,884,000 |
|
$2,595,600 |
|
$288,400 |
|
|
|
$9,501,750 |
|
$5,399,775 |
|
$599,975 |
|
$3,502,000 |
|
|
|
|
|
|
|
|
The New Construction of the Library in Option 3 would be funded as follows:
The renovation of the existing building
($2,266,000) would be funded from the proposed GST rebate of approximately
$1,150,000 with the remainder to be determined through the review of the 2004
budget by the Budget Sub-Committee.
The 1999 Development Charge Background Study
identified 351,300 sq. ft for the construction/expansion of recreation
facilities over a ten-year period as noted in the chart below. Several of the facilities have been built,
or have been identified to be built, larger than what was estimated in the
Background study. As a result, the
additional square footage must be substituted from another Recreation
project. Currently, 129,070 sq. ft
remains to be funded from Development Charges, which is less than the square
footage anticipated for the construction of the East Community Centre. Therefore, it is not recommended that
recreation square footage be used to accommodate the link to the arena. The following chart illustrates the
Recreation facilities construction program:
|
Forecast in 1999 DC
Background
Study |
Actual Construction |
Impact |
|
|
|
Year
|
Sq Ft. |
Sq Ft. |
Sq Ft. |
|
Angus Glen CC |
2001 |
121,000 |
141,000 |
20,000 |
(a) |
Thornhill CC Expansion |
2002 |
20,000 |
27,000 |
7,000 |
(c) |
Centennial CC Expansion |
2003 |
25,300 |
23,185 |
(2,115) |
(c) |
Centennial CC Indoor Bocce
Court |
|
|
11,045 |
11,045 |
(c) |
Mt Joy/Greensborough |
2004 |
20,000 |
|
(20,000) |
(a) |
Milliken Mills Expansion |
2005 |
14,000 |
|
(14,000) |
(c) |
Berczy (substituted for
YMCA) |
2006 |
20,000 |
20,000 |
0 |
(b) |
East CC |
2007 |
131,000 |
0 |
(131,000) |
(c) |
|
|
|
|
|
|
Total Sq Ft For Recreation
Facilities |
|
351,300 |
222,230 |
129,070 |
|
Notes:
(a)
The additional 20,000 square feet constructed at Angus Glen Community
Centre was substituted for the Mt Joy/Greensborough Community Centre
(b)
The YMCA was allocated 20,000 square feet as a substitution for the
Berczy Community Centre
(c)
The additional 7,000 square feet at Thornhill Community Centre and
8,930 square feet at Centennial Community Centre (11,045-2,115) are a
substitution from the Milliken Mills Community Centre Expansion and/or the East
Community Centre
The 7,000 sq. ft link to the arena at Markham
Village Library would require a substitution in square footage from the
Milliken Mills library expansion and/or the Central East Library as noted in
the chart below. The funding of the
link would be 90% from Development Charges ($2,595,600) and the remaining 10%
($288,400) would be funded from a Reserve that was previously established to
fund the mandatory 10% non-development charge component of construction
projects. Alternatively, the link to
the arena could be totally funded from the tax base.
The current Library construction/expansion program
includes four facilities. The following illustrates the Library Facility
construction impact:
|
Forecast in 1999 DC
Background
Study |
Actual Construction |
Impact |
|
|
Year
|
Sq Ft. |
Sq Ft. |
Sq Ft. |
Angus Glen CC |
2001 |
30,000 |
30,000 |
0 |
Markham Village Expansion |
2002 |
10,500 |
10,500 |
0 |
Milliken Mills Expansion |
2005 |
6,300 |
0 |
(6,300) |
East Library |
2007 |
20,000 |
0 |
(20,000) |
|
|
|
|
|
Total Sq Ft For Library
Facilities |
|
66,800 |
40,500 |
(26,300) |
It should be noted that the cost of the Library’s construction program is
not fully recovered from development charges, therefore during the 2003 budget
discussions, an allocation of $500,000 from the tax base was approved and is
being set aside annually in a reserve for the non-DC funding that will be
required.
COMPARISON OF OPTION 1
VERSUS OPTION 3
|
|
Funding Sources |
|||
|
Preliminary Estimate |
DC |
Reserve |
Lease 2+ yrs |
Tax |
Option 1: |
|
|
|
|
|
New Construction |
3,821,300 |
3,439,170 |
382,130 |
|
|
Finishing for Library ATS |
530,450 |
|
|
530,450 |
|
Total for Option 1 |
$4,351,750 |
$3,439,170 |
$382,130 |
$530,450 |
$0 |
|
|
|
|
|
|
Option 3: |
|
|
|
|
|
10,500 sq ft expansion |
3,115,750 |
2,804,175 |
311,575 |
|
|
5,250 sq ft replacement of program rooms |
1,236,000 |
|
|
530,450 |
705,550 |
Total for Option 3 |
$4,351,750 |
$2,804,175 |
$311,575 |
$530,450 |
$705,550 |
|
|
|
|
|
|
Comparison of Option 1 vs 3 |
$0 |
$634,995 |
$70,555 |
$0 |
(705,550) |
|
|
|
|
|
|
The funding of the preliminary cost estimate for this option follows:
FUNDING
SOURCES:
|
Preliminary
Cost |
|
Funding Sources |
||||
Description |
Estimate |
|
DC |
|
Reserve |
|
Other |
New Construction (incl. Site work) |
$4,506,250 |
|
$2,943,225 |
|
$327,025 |
|
$1,236,000 |
Renovation of Existing building |
$2,266,000 |
|
|
|
|
|
$2,266,000 |
|
$6,772,250 |
|
$2,943,225 |
|
$327,025 |
|
$3,502,000 |
|
|
|
|
|
|
|
|
The New Construction of the Library in this
option would be funded as follows:
The renovation of the existing building
($2,266,000) would be funded from the proposed GST rebate of approximately
$1,150,000 with the remainder of the funding to be determined by the Budget
Sub-Committee through the review of the 2004 budget.
The construction of future facilities will
result in competing needs for development and non-development charge funding,
therefore staff recommend that Council approve the design of Option 1 as
suggested in the Markham Village Library Expansion report presented at the
Committee of the Whole on March 9, 2004. Option 3, with or without the link, is
not recommended, as it will require additional tax funding of at least
$634,995, and would require a transfer of development charge funding (and
square footage) from projects currently included in the Town’s existing
development charge background study.
ATTACHMENTS:
§ March 9, 2004 report to Committee of the Whole – Markham Village Library Expansion
|
Joel Lustig Director, Financial and Client
Services |
Q:\Finance and
Administration\Finance\SHARED\2004 Finance_Admin Cttee
Reports\0420-Funding MVLibrary
Expansion.doc