TO: |
Mayor and Members of Council |
|
|
|
|
FROM: |
Stan
Bertoia, General Manager, Construction & Utilities |
|
|
|
|
PREPARED BY: |
Ernie
Ting, Manager, Infrastructure |
|
|
|
|
DATE OF MEETING: |
2004-Apr-05 |
|
|
|
|
SUBJECT: |
Contract T34-98WW Routine & Emergency Sewer/Watermain Repairs Contract Extension |
|
|
|
RECOMMENDATION:
THAT the report
entitled “Contract T34-98WW, Routine & Emergency Sewer/Watermain Repairs,
Contract Extension” be received;
AND THAT “Contract T34-98WW, Routine & Emergency
Sewer/Watermain Repairs, Contract Extension” be extended from April 1, 2004 to
May 31, 2004 to the current contract provider, Finch Paving Ltd.
AND THAT Blanket Purchase Order B2 35 for Finch Paving be increased in a total amount of $144,450.00 inclusive of
7% GST ($135,000.00 inclusive of 3% GST) for the period January 1, 2004 to May
31, 2004;
PURPOSE:
The purpose of this report
is to extend the expiry date of contract T34-98WW from March 31, 2004 to May
31, 2004 and to increase the upset limit of Blanket Purchase Order B2 35 to
accommodate the costs of routine and emergency repair requirements up to this
period.
BACKGROUND:
Contract T34-98WW was awarded to Finch Paving for the Routine and
Emergency Sewer/Watermain Repairs for a period of two years from April 1, 2002
to March 31, 2004 in the amount of $409,000.00 inclusive of 7 % GST (393,710.27
inclusive of 3% GST). An increase to
the blanket in the amount of $250,000.00 inclusive of 7% GST (240,654.19
inclusive of 3%) was approved in May 2003 for a total award amount of
$659,000.00 inclusive of 7% GST ($634,364.46).
OPTIONS/DISCUSSION:
To date,
purchase order number B2 35 has been fully expended. The following is the cost estimate of future
work requirements for the period ending May 31, 2004.
Description
|
Estimate
|
Explanation |
Emergency and Routine
Repairs |
$144,450.00 incl. 7% GST
(Estimate based on 2003 Actual) |
For
details please refer to Attachment “A” |
The 2004/2005 contract is being tendered and
will closed on March 24, 2004. The new contract will
be in effect after the expiration date of May 31, 2004 of the existing
contract.
FINANCIAL CONSIDERATIONS:
The major scope of this
contract is emergency repairs of watermain breaks and sanitary sewers. The
contract cost over-run is a result of increased number and cost of emergency
and routine repairs. The increased cost of repairs was partially due to
severity of several breaks and change in repair procedures in order to comply
with water quality regulation. Increased inspection of appurtenances found a
number of repairs necessary to minimize risks and liabilities. These
contributed to the increased number of repairs for hydrants, valves and
sanitary sewer services adding more cost under this contract. Waterworks 2004
Operating Budget request has been increased to reflect the increased cost in
2003.
The Finance Department has
reviewed this report and concur with its content.
APPROVED BY:
Stan
Bertoia, P. Eng. |
Jim
Sales |
General
Manager, Construction and Utilities |
Commissioner, Community and Fire Services |
|
|
|
|
|
|
Peter
Loukes, P. Eng. |
|
Director,
Operations and Asset Management |
|
Q:\Commission
Share\Works\WATERWORKS\REPORTS\t34-98WW Contract Extension Award Report
0411.doc