FINANCE AND ADMINISTRATIVE COMMITTEE

 

 

 

 

 

TO:

Mayor and Members of Council

 

 

 

 

FROM:

Stan Bertoia, P. Eng., General Manager, Construction and Utilities

 

 

 

 

PREPARED BY:

Stan Lau, Senior Project Manager

 

 

 

 

DATE OF MEETING:

November 22, 2004

 

 

 

 

SUBJECT:

Settlers Park Landfill Site Management

 

 

 


RECOMMENDATION:

That the report entitled “Settlers Park Landfill Site Management” be received;

 

That Beatty & Associates be authorized to carry out a leachate plume assessment in the vicinity of the Settlers Park Landfill site at an estimated cost of $12,500;

 

That Beatty & Associates be authorized to carry out a detail design for an Aerobic Landfill Management Plan at the Settlers Park Landfill site at an estimated cost of $25,000;

 

That the cost for the detail design of the Aerobic Landfill Management Plan to an upset limit of $25,000 be funded from the corporate-wide contingency capital project and the cost for the leachate plume assessment in the estimated amount of $12,500 be funded from the Operations and Asset Management 2004 Capital Budget, Account No. 58-5399-6236-005;

 

That the tendering process be waived in accordance with Purchasing By-Law 143-2000, Section 14(1C) which states “…When the extension of an existing contract would prove more cost-effective or beneficial; ..”

 

That the Operations and Asset Management Department continue to manage and maintain the Gas Recovery Well System to ensure compliance with the Certificate of Approval;

 

That staff pursue partnership funding opportunities with the Toronto and Region Conservation Authority and the FMC Green Municipal Enabling Fund for the leachate plume assessment and aerobic landfill management plan;

 

And that staff report back in the spring of 2005 on the consultant’s findings and recommendations.

 

PURPOSE:

The purpose of this report is to provide Council with an update on the Settlers Park Landfill Site Management program and to obtain authorization to retain a consultant to carry out a leachate plume assessment and carryout the detail design of an Aerobic Landfill Management Plan for the Settlers Park Landfill site.

 

BACKGROUND:

Site Location

Settlers Park is approximately 38 ha. Of passive parkland located south of John Street between Don Mills Road and Leslie Street. A majority of the parkland is west of German Mills Creek. The western part of the park is bounded by residential homes on Cottonwood Court, Pine Knoll Gate and Dawn Hill Trail and by the Bayview County Club. A site plan is attached for reference as Attachment 1.

 

Previous Land Use

Previous land uses at the site included aggregate extraction and a private landfill operation. Extraction of sand outcrop began in the valley of German Mills Creek in the 1940’s. By the time the sand deposits were mined-out in the 1960’s, the pit was over 18 m deep, with steep side slopes abutting the residential properties.

 

Landfill operations by James Sabiston Ltd. began in the 60’s and ended in 1975. The western portion of the pit area was filled with a mix of commercial, industrial and residential refuse. The areas between the un-opened Leslie Street road allowance and German Mills Creek were filled with inert, clean materials.

 

Groundwater Conditions

Two aquifers exist beneath Settlers Park. The upper aquifer is located immediately below the landfill and groundwater in this aquifer discharges into German Mills Creek. The lower aquifer is located in a deep bedrock valley beneath the eastern part of the park and was formerly used to supply water by wells for the Town in the 1940’s to 1970’s.

 

Leachate and Methane Gas Generation

Leachate generated in the waste landfill has percolated downward to the upper aquifer and eastward toward German Mills Creek.

The landfill is estimated to produce 1,000 to 2,000 tonnes per year of methane gas, based on preliminary gas emission modelling and Environment Canada landfill surveys. This is equivalent to 20,000 to 40,000 tonnes of carbon dioxide emissions (equivalent of 4150 to 8300 cars) per year.

 

Gas Recovery System and Monitoring

After the landfill was completed in 1975, Sabiston transferred ownership of the property to the Town of Markham in the early 1980’s.  The MOE ordered Sabiston to install gas collection wells along the north and west boundaries of the landfill. The purpose of the wells was to prevent methane gas from migrating onto the abutting residential properties via subsurface sand deposits.  The gas collection system was installed in 1983 and the Town took over operation of the system in 1984.  Since the ownership transfer, the Town has been responsible for any landfill gas emissions.  The methane gases collected were burned off on site.

 

The gas recovery system was rehabilitated in 2001 and Operations and Asset Management continue to operate and monitor the system.

Works and Reports Completed from 1994 to 2004

The following works and reports have been carried out on this landfill site from 1994 to 2004:

                   December 1994 – Inspection of the gas and control system by Dames & Moore.

 

                   September 1996 – Report of Gas Control System Investigation by Dames & Moore: Damaged gas probes were replaced and the report recommended repair or replacement of the control system.

 

                   October 1999 – Gas Collection System Preliminary Performance Testing by Beatty Franz & Associates:  The report recommended a two-stage field investigation be carried out to evaluate the condition of the buried wells, delineate the extent of possible gas migration and repair the system.

 

                   March 2000 – Performance of Gas Wells Study by Beatty & Associates: Results of the gas well performance testing indicated that most of the 18 wells need to be repaired or replaced.  It was also recommended that the possible distribution of methane gas along the western and northern site boundary should be investigated.

 

                   June 2000 –     As a result of the previous studies mentioned above, Lantech Drilling Service was awarded the contract to rehabilitate the gas collection system and construction of new wells.

 

                   August 2002 - Beatty & Associates was retained by the Town to carry out a study program to assess potential environmental impacts at the Settlers Park landfill site. The objective of the study was to carry out a “due diligence” program to determine if the landfill has caused any impacts to the groundwater or to the German Mills Creek.

 

Phase I of the study, completed in the summer of 2002, monitored the water quality of the German Mills Creek both upstream and downstream of the landfill site and assessed potential impacts of the landfill on German Mills Creek.  Comprehensive water quality analyses showed no measurable impacts in the stream that could be directly attributed to the leachate plume discharge.

 

·                    May 2003 - Beatty & Associates was retained by the Town to carry out Phase II of the study program. The Phase II study was to investigate and assess the groundwater flow patterns and monitor any potential leachate plume that may exist at the landfill site. A draft report for Phase II was completed in February 2004. The draft report recommended an on-going monitoring program. It also recommended to carryout a pilot project to manage the landfill using Aerobic Landfill Technology.

 

·                    June 2004 - Beatty & Associates was further instructed to monitor and assess the groundwater flow patterns at the landfill site; analyse groundwater samples and evaluate leachate attenuation; analysis of stream sample in German Mills Creek to assess potential impacts; and to carryout an Aerobic Landfill Pilot Test to provide the data necessary to assess the feasibility of full scale aerobic landfill management technology.

 

Results of this latest study are further discussed below:

 

OPTIONS/DISCUSSION:

Monitoring Results:

The key results of site monitoring program include:

 

·                    Water table was a few centimeters higher in August 2004 than in August 2003 due to greater rainfall in 2004;

·                    Observation well analyses confirmed the leachate plume that was identified in 2003;

·                    Comprehensive water quality analyses between upstream and downstream of German Mills Creek indicated no measurable impacts that could be directly attributed to the leachate plume discharge.

·                    Water quality meet MOE Surface Water requirements;

·                    Comparison of the August 2004 leachate plume quality with the September 2003 results indicates that some parameters increased in concentration over the past year;

 

The 2004 monitoring program has confirmed the development of a relatively high-strength leachate plume beneath the waste landfill. The plume discharges into the sandy sediments in the bottom and west bank of German Mills Creek.

 

The impact of the leachate plume on water quality in German Mills Creek is relatively minor, however the presence of relatively high concentration of ammonia and iron in the leachate plume could impact groundwater seepage on the streambank and groundwater upwelling in the streambed and may be deleterious to the aquatic habitat in the stream.

 

Proposed Work Program:

It is proposed to retain a consultant to carry out the following work to assess the potential leachate plume impacts:

 

·                    Meeting with TRCA to review data collected to date and confirm our work program, as well as to develop a partnership with TRCA to establish options/alternatives etc.

·                    Mapping and laboratory analysis of groundwater seepages along the German Mills Creek bank in the vicinity of the leachate plume

·                    Identification of groundwater upwelling areas in the bottom sediments of German Mills Creek by temperature probes and installation of mini-piezometers

·                    Sampling and analysis of groundwater in areas of upwelling for parameters that may be deleterious to the aquatic habitat

·                    Report back in spring of 2005

The cost for this leachate plume assessment is estimated at $12,500. In the event that the parameters identified exceed the Provincial Water Quality Objectives for surface water, a follow-up stream survey by an aquatic toxicologist will be required.

Gas Recovery Well System

During monitoring of gas probes along the landfill boundary this August, in two occasions, the gas recovery well system was found not fully operating and when the system is not operating, malodorous landfill gas emission were noted along the western boundary and methane levels in the boundary gas probes were in the range of 5 to 15% by volume, well above the MOE compliance level of 2.5 %. A follow-up investigation indicated that a blockage in the system header may have prevented effective operation of the western boundary gas recovery wells. Town staff have inspected the site and is in the process of rectifying the problem. Site inspection during the first two weeks of September did not notice of any gas emission in the landfill area.

 

The MOE regulation for control of landfill gas requires that methane gas concentrations “below the surface of the land at the boundary of the site be less than 2.5 percent by volume”.

Monitoring of the gas recovery wells, after the 2001 rehabilitation works, show that the 2.5 percent compliance level is being met at the site boundary. However, the system is prone to breakdown and failure due to ongoing settlement of the gas well header pipe blocking segments of the system and making the wells inoperable. Also, air leaking into the buried piping reduces the methane concentration below 10% volume. The low methane levels prevent the recovered gases from being burned prior to emission to the atmosphere.

 

Continuous operation and maintenance of the perimeter gas collection well system is required in order to meet the Certificate of Approval (C of A) requirements and to protect the neighbouring residences. This is being carried out by the Operations Department.

 

Proposed Remedial Action:

It is proposed that Operations staff correct the header blockage problem, acquire the necessary equipment and training (approx. $2,000) for measuring and monitoring the gas recovery well system, and continue to carryout regular maintenance and inspection to ensure landfill gas containment and compliance with the C of A requirements.

Aerobic Landfill Pilot Test

Slow decomposition of the waste materials has caused differential settlement of 4 m or more in some areas of the landfill over the last 20 years. This has resulted in an irregular terrain with numerous depressions. This slow and continuous differential settlement will impact on the plans for development of a more active type of parkland at this landfill site.  Also, trees are not able to survive on the site because there is no oxygen in the root zone below the landfill cover due to anaerobic decomposition of the waste.

 

·        Landfill Technology – Anaerobic vs Aerobic

Anaerobic:

At present, the Settlers Landfill can be classified as “Anaerobic” because the existing one metre thick clay and silt landfill cap has effectively prevented moisture and air from penetrating into the waste material and created a dry and oxygen-absent environment. The waste decomposition process under anaerobic condition is very slow and can be expected to continue generating leachate and methane gas for many decades up to 80 or 100 years.

 

Aerobic:

Aerobic Landfill Technology is a proven approach for reducing methane emissions by adding air (oxygen) into the landfill to promote aerobic activity, alter the decomposition process and accelerate waste degradation and stabilization. When oxygen is present, bacteria, fungi and aerobic organisms consume oxygen and convert organic material to carbon dioxide and water. On-site reduction of methane is achieved without the need for gas collection, treatment and burning. Aerobic conditions also allow vigorous vegetation growth and reforestation of the site. It would also reduce the long-term care requirements for monitoring a gas migration and gas collection system maintenance. This system was successfully applied at the Donlands landfill site in the City of Toronto in 1981.

Partnership with other Government Agencies

Applying the aerobic landfill technology to this landfill site will have many positive impacts to the environment such as, accelerated waste decomposition and settlement; eliminate the emission of methane and gases; and allow for vigorous vegetation growth. It may qualify for funding contribution from the Green Municipal Enabling Fund (GMEF) established by the Federation of Canadian Municipalities and other funding opportunities.

The Toronto and Region Conservation Authority may also be willing to partner in the water quality monitoring program and the aerobic landfill management plan.

 

·        Feasibility of an Aerobic Landfill

Data collected in the aerobic pilot test has demonstrated that it is feasible to reduce methane at this site to non-hazardous levels. Implementation of an aerobic landfill would achieve a major reduction in greenhouse gas emission in Markham (estimated to produce 1,000 to 2,000 tonnes of methane gas per year), eliminate the need for gas collection at the site and eliminate the risk of off-site methane migration and malodorous gas emission at the site boundary.

Proposed Work Program:

It is proposed to retain a consultant to perform the following work:

·                    Carry out a detail design of an aerobic landfill management plan;

·                    Prepare cost estimate for construction, operation and monitoring of the aerobic landfill;

·                    Evaluate the benefits of aerobic landfill technology, including annual reduction in greenhouse gas emission and eligibility for Emission Reduction Credits etc;

·                    Report back in spring of 2005

The estimated cost for this Aerobic Landfill design is $25,000.

 

RECOMMENDATIONS:

·                    That Beatty & Associates be authorized to carry out a leachate plume assessment in the vicinity of the Settlers Park Landfill site at an estimated cost of $12,500;

 

·                    That Beatty & Associates be authorized to carry out a detail design of an Aerobic Landfill Management Plan at the Settlers Park Landfill site at an estimated cost of $25,000;

 

·                    That the cost for the detail design of the Aerobic Landfill Management Plan to an upset limit of $25,000 be funded from the corporate-wide contingency capital project and the cost for the leachate plume assessment in the estimated amount of $12,500 be funded from the Operations and Asset Management 2004 Capital Budget, Account No. 58-5399-6236-005.

 

·                    That the tendering process be waived in accordance with Purchasing By-Law 143-2000, Section 14(1C) which states “…When the extension of an existing contract would prove more cost-effective or beneficial; ..”

 

·                    That the Operations and Asset Management Department continue to manage and maintain the Gas Recovery Well System to ensure compliance with the Certificate of Approval.

 

·                    That staff pursue partnership funding opportunities with the Toronto and Region Conservation Authority and the FMC Green Municipal Enabling Fund for the leachate plume assessment and aerobic landfill management plan;

 

·                    And that staff report back in the spring of 2005 on the consultant’s findings and recommendations.

 

FINANCIAL CONSIDERATIONS:

That the cost for the detail design of the Aerobic Landfill Management Plan to an upset limit of $25,000 be funded from the corporate-wide contingency capital project and the cost for the leachate plume assessment in the estimated amount of $12,500 be funded from the Operations and Asset Management 2004 Capital Budget, Account No. 58-5399-6236-005.

 

Approximately $22,000 was included in Account No. 58-5399-6236-005 for Urban Design to develop Park Development scenarios.  These will assist with the public consultation process for the landfill management plan.

 

The costs for monitoring the Gas Recovery Well System header and purchasing of monitoring equipment is funded in the 2004 Operations and Asset Management Department’s Operating Budget.

 

 

ENVIRONMENTAL CONSIDERATIONS:

The concept of aerobic landfill technology has been introduced to various stakeholders including municipal governments, Environment Canada, the Ontario Hydro Generation Company, as well as representatives of pilot greenhouse gas emission reduction trading programs to solicit feedback on the technology and the potential for emission trading. There is interest at all government levels in promoting landfill methane emissions reduction as a viable way to meeting greenhouse gas reduction targets. The use of aerobic landfill technology may assist the Town in its commitment to meet the objectives of the Kyoto Protocol. It will also allow enhanced use of land in a passive or active manner by the public.

 

 

BUSINESS UNITS CONSULTED AND AFFECTED:

The Legal Department has been involved in the discussion, provided input and have reviewed this report.

 

 

ATTACHMENTS:

Attachment 1 – Site Plan

Attachment 2 – Plan: Groundwater Flow (Fig. 2)

Attachment 3 – Plan: Leachate Attenuation Zone (Fig.3)

Attachment 4 – Plan: Landfill Geological Cross-Section A-A (Fig. 4)

Attachment 5 – Plan: Landfill Geological Cross-Section A-A (Fig. 2)

Attachment 6 - Photo: Iron-stained Groundwater Seepage (German Mills Creek, August 2002)

Attachment 7 – Memorandum Re: Council Resolution

 

 

 

 

 

_____________________________________

Stan Bertoia, P. Eng.

General Manager, Construction and Utilities

 

 

 

 

 

 

 

 

 

Peter Loukes, P. Eng.

Director of Operations and Asset Management

 

Jim Sales

Commissioner of Community Services and Fire

 

 

Q:\Commission Share\Operations and Asset Management\Reports\2004\C & U\Capital Works R.O.W\Settlers Park Landfil Site Management 2.doc