|
|
|
|
|
|
|
|
|
|
TO: |
Mayor and Members of Council |
|
|
|
|
FROM: |
Stan Bertoia, P. Eng., General
Manager, Construction and Utilities |
|
|
|
|
PREPARED BY: |
Stan Lau, P.
Eng., Senior Project Manager |
|
|
|
|
DATE OF MEETING: |
|
|
|
|
|
SUBJECT: |
|
|
|
|
RECOMMENDATION:
That the report entitled “18th
Avenue Bridge Replacement – Status Update” be received;
That the Operations and Asset Management
Department be authorized to proceed with construction of the
That
Totten Sims Hubicki Associates be retained for finalizing detail design,
preparation of tender documents and provision of contract administration at an
estimated amount of $41,500 plus GST and the tendering process be waived in accordance with Purchasing By-Law 2004-431,
Section II-7(1c).
And
that this project be funded from the 2002 Capital Budget, Account No.
65-5350-4872-005 and from the 2005 Capital Budget, Account No. 58-6150-6581-005.
PURPOSE:
The
purpose of this report is to provide Council with an up-date on the
BACKGROUND:
Class Environmental Assessment and Public Consultation
This bridge is
located on
As required by
the Class EA, a Public Information Centre (PIC) was held on
As a result of
the PIC, an in depth bridge condition survey was carried out and a Life Cycle
Cost Analysis conducted to compare the cost/benefit of bridge repairs vs bridge
replacement.
Posting of Project File
A Project File
was completed and posted on
OPTIONS/DISCUSSION:
2005 Capital Budget
This
project is included in the pre-approved 2005 Capital Budget. It is recommended
that the work be tendered as soon as possible to take advantage of potential
better prices of early tender.
Retaining of Consultant
Totten
Sims Hubicki Associates (TSH) has been involved from the start of the project
and has completed the final design. They have submitted a proposal for the
provision of engineering services including finalizing detail drawings,
obtaining TRCA approval, preparation of tender document,
provide field inspection and contract administration. Total estimated cost for
these services is $41,500 excluding GST. This is equivalent to approximately 8%
of the estimated construction cost ($535,000) and is considered reasonable for
this nature and size of the project.
It
is recommended that TSH be retained for this project at an estimated cost of
$41,500 plus GST and the tendering process be waived in accordance with
Purchasing By-Law 2004-431, Section II-7(1c), authorize the Treasurer, the
Purchasing Manager and the appropriate Director to negotiate a contract “When
the extension of an existing contract would prove more cost effective or
beneficial”.
FINANCIAL CONSIDERATIONS:
Funding
of this project is from the remaining 2002 Capital Budget for Bridges and Culverts Rehabilitation
Program, Account No. 65-5350-4872-005 and from the 2005 Capital Budget for
Bridges and Culverts Improvement Program, Account No. 58-6150-6581-005.
ATTACHMENT:
Appendix A: Location Map
___________________________________
Stan Bertoia, P. Eng.,
General Manager, Construction & Utilities
|
|
|
Peter Loukes, P. Eng., Director of Operations and Asset Management |
|
Jim Sales Commissioner of Community Services and Fire |
Q:\Commission Share\Operations and Asset Management\Reports\2005\C &
U\ROW\Other Report\18th