|
|
|
|
|
|
|
|
|
|
TO: |
Mayor and Members of Council |
|
|
|
|
FROM: |
Stan Bertoia, P. Eng., General
Manager, Construction and Utilities |
|
|
|
|
PREPARED BY: |
Stan Lau, P. Eng., Senior Project
Engineer |
|
|
|
|
DATE OF MEETING: |
|
|
|
|
|
SUBJECT: |
Response to Council Deputation by
Mr. Kay regarding Reesor Road Bridge Replacement between 16th
Avenue and Major Mackenzie Drive |
|
|
|
RECOMMENDATION:
That the report entitled “Response to Council
Deputation by Mr. Kay regarding Reesor Road Bridge
Replacement between 16th Avenue and Major Mackenzie Drive” be
received;
And that the Town proceed with the
Reesor Road Bridge Replacement Project in the summer of 2005 as previously
approved by Council.
PURPOSE:
The purpose of this report is to address Mr.
Kay’s concerns presented to Council on
BACKGROUND:
Council on
To fulfill the Town’s responsibility to provide municipal
roads and safe traffic services to the public, the need to replace the bridge
structure on
In December of
2000, the Town retained the consulting firm of McCormick Rankin Corporation
(MRC) to carryout an Environmental Assessment for the replacement of this
bridge structure as required under “Schedule B” of the Municipal Class
Environmental Assessment (Class EA). After consultation with the public in
It is the
recommendation of the consultant to replace the existing substandard two–lane bridge
with a standard two-lane bridge and with improvements to both the horizontal
and vertical alignment at the approaches.
Mr. Kay’s issues in 2001 have been received through the EA Process
Schedule B of
the Class EA requires the proponent to solicit comments from the adjacent
property owners as well as various government agencies such as MOE, MNR, MTO,
and TRCA etc. To fulfill this requirement, a Public Information Meeting (PIC)
was held on
Despite several
meetings with Mr. Kay in attempt to resolve these issues, Mr. Kay in May 2002
wrote to MOE and requested that the Town be ordered to prepare an Individual
Environmental Assessment for this project. In accordance with the MOE
guidelines, more discussions between staff and Mr. Kay took place but some of
the issues remain un-resolved.
To address Mr.
Kay’s issues, in October 2002 at the request of the MOE, staff reiterated that
the posted speed limit will remain unchanged at 60 km/h; the Town will monitor
the vehicle speed after the new structure is installed; the Town will review
the driveway issue when doing detail design; and that the Town will erect Deer
Crossing warning signs along this section of road although there is no deer
collision reports on file (Appendix A).
As a result, the Ministry of Environment in March 2003, officially
advised the Town that an Individual Environmental Assessment is not required
and the Town may proceed with the bridge replacement. (Appendix B).
Council on
OPTIONS/DISCUSSION:
Present Issues
Staff was advised
by Council on
Another meeting was held
with Mr. Kay on
Response: This issue was
originally raised by Mr. Kay in 2001 and was reviewed and addressed through the
EA process. At the
Response: Current design has identified 4 existing
trees will be removed and replaced with appropriate landscaping.
Response: This issue was originally
raised by Mr. Kay in 2001 and was reviewed and addressed through the EA
process. Shifting the bridge and roadway further to the west would involve more
farm land losses which is not be acceptable to the
affected property owner. During public consultation in 2001, Mr. Richard
Pearse, the owner of the farm land west of
This was one of the alternative
design solutions considered during the EA phase and it was determined to be the
most expensive and has the biggest impact on the adjacent farm land and
therefore was not recommended.
Response: The consultant has confirmed that the
original stone retaining wall, plus the proposed ditches and the proposed steel
beam guard rail will provide sufficient protection to Mr. Kay’s house.
In an attempt to advise Mr. Kay of our response to his concerns, on
January 12, 2005 we called Mr. Kay and left a voice message in his phone and on
January 18 left a message with his wife. As of January 19, we have not received
any response from Mr. Kay.
FINANCIAL CONSIDERATIONS:
No
financial implications are to be considered in this report.
BUSSINESS UNITS CONSULTED AND AFFECTED:
Development Services Commission
(Engineering Department) staff have been consulted and
have no comments on this report.
ATTACHMENT:
Appendix A: Letter to MOE dated
Appendix B: Letter
from MOE dated
Appendix C: Mr. John
Kay’s concerns
____________________________________
Stan Bertoia, P. Eng.
General Manager, Construction & Utilities
|
|
|
Peter Loukes, P. Eng. Director of Operations and Asset Management |
|
Jim Sales Commissioner of Community Services and Fire |
Q:\Commission Share\Operations and Asset Management\Reports\2005\C &
U\ROW\Other Report\Response to Council deputation by Mr. Kay Regarding Reesor
Road Bridge Replacement.doc