TO: |
Mayor and Members of Council |
|
|
|
|
FROM: |
Alan
Brown, Director of Engineering |
|
|
|
|
PREPARED BY: |
Alan Brown, Director of Engineering Ralph Ehlers, P. Eng Capital Engineer |
|
|
|
|
DATE OF MEETING: |
2005-Feb-28 |
|
|
|
|
SUBJECT: |
Town of Markham 10 Year Capital Infrastructure Program
(2005-2015) |
|
|
|
RECOMMENDATION:
That the staff report entitled “Town of Markham 10 Year Capital Infrastructure
Program, (2005-2015)” be received;
And that the 10 Year Capital Program for roads, bridges, sidewalks and
illumination projects be endorsed;
And that the Director of
And that the Town Solicitor be authorized to retain, on a contract basis,
staff person or consultant to negotiate and finalize property acquisitions
necessary to implement the
And that the cost of the Legal Department contract staff or consultant
be assessed to the various capital projects under the
And that if staff cannot secure consultant services for the design of sidewalk
and illumination projects at a competitive price through the purchasing by-law
process then the Director of
Engineering with the assistance of the Manager of Purchasing be
authorized to negotiate consultant services on a preferred supplier basis;
And
that Mr. Keith Bray, Markham Board of Trade, Ms. A Yip, Scarborough/York
Chinese Business Association, and Mr. K. Schipper, Commissioner of Works,
Region of York, be advised accordingly.
PURPOSE:
To obtain
Council’s approval for the scheduling of the road, sidewalk and illumination
construction program for the next 10 years (2005-2015) so that staff can program
the multi year implementation steps to deliver the projects.
EXECUTIVE SUMMARY:
The
BACKGROUND:
In April 2003 Council approved the 2003 and 10 Year Capital Program for
the roads and bridges and requested staff to update the program on a yearly
basis. Staff submitted a report in June
2004 updating the program as it relates to the schedule for
In August 2004 as part of the Development Charges Background Study the
Town of
The proposed 2005 and 10 year Capital Program while utilizing the cost
estimates and funding sources defined in the August 2004 Development Charges Background Study
provides a more detailed schedule.
The
August 2004 Development Charges Study outlined the following hard services
infrastructure required to accommodate growth approved in OPA #5.
|
Costs |
Roads |
$99 million |
Structures |
$ 85 million |
Sidewalk |
$ 15 million |
Illumination |
$11 million |
Sanitary |
$ 21 million |
Storm/Environmental |
$ 68 million |
Water |
$ 24 million |
Intersection |
$ 12 million |
Total |
$335 million |
As
illustrated in Attachment ‘F’ it currently takes from 2 years to 5 years to
deliver an infrastructure project depending on Environmental Assessment
requirements and appeals, property requirements, expropriations and appeals,
approvals (environmental agencies, Hydro One, CN, GO Transit, 407 ETR, MTO, Region, etc.) and utilities
relocates.
The
approval by Council of the 10 Year Capital Program allows staff to program the
projects through the various steps, determine staffing requirements and enable
the Finance Department to project the timing of future funding requirements
(development charges, tax rate, debentures).
10 Year Capital Program
Engineering
staff have prepared the 10 year program for road/structure, sidewalk and
illumination based on the following criteria;
Staff
will on a yearly basis update the program based on the above criteria and
submit an updated 10 Year Capital Program for Council’s concurrence.
This
program relates only to capital projects listed in the August 2004 Development
Charges Background Study. The Operations
and Asset Management Department will budget and program capital projects related
to capital replacement or repair of existing hard infrastructure (roads,
bridges, etc.) which are funded by the tax rate. In addition sidewalk and illumination in
existing communities funded by the tax rate are also budgeted and programmed
under the Operations and Asset Management Department.
Road/Structures
Attachment
‘A’ denotes the 10 year program for roads and bridge structures required to be
constructed to accommodate OPA #5. Attachment ‘B’ provides a more detailed
overview of the infrastructure in the Markham Centre Area including the timing
of Regional road works.
Over
the next 10 years approximately $87.4 million of investment in municipal
roads/bridges is required as noted in Attachment ‘C’. Some of the projects listed beyond the ten year
program (2015) such as
Sidewalks
Of a
total of $15 million in the August 2004 Development Charges Background Study, approximately
$10.6 million has been assigned over the next 10 years to install sidewalks as
listed in Attachment ‘D’. An annual
allowance of $270,000 has been made for sidewalks not associated with either
Regional or Town road construction projects but rather installation within
existing road cross-sections not defined to date. The ability to deliver the sidewalk program
is often dependent on available property, utility relocates and agency
approval. If these issues cannot be
resolved expeditiously than the project may have to be delayed.
Specific
requests in 2004 from the public and Council to be implemented in 2005/2006 are:
Subsequent
to the
To
advance the first three (3) sidewalk projects in 2005 it will require that $328,440.00
be funded by ASDC ($130,863), Town Wide Hard ($23,337) and the Pre-DCA Engineer
Reserve ($174,240). The fourth project
will be constructed by the developer in 2006/2007 through the Site Plan Control
Agreement and suitable ASDC credits granted at the agreement stage. The YRTP’s request for the 3 sidewalks has
been accommodated in the existing budget by deferring the Major Mackenzie sidewalk
to 2006.
Illumination
Of a
total of 11 million in the August 2004 Development Charges Background Study approximately
$8.2 million of street light installation has been programmed to install street
lights on arterial and collector roads for new developments as listed in
Attachment ‘E’. An allowance of $130,000
per year has also been set aside for projects not associated with Regional or
Town road construction projects.
Consultant Services
The
Property Acquisition
In
Environmental Projects
In
the August 2004 Development Charges Background Study, works related to
mitigating the impact of development on our watercourses were defined and
included in the Town Wide Hard Development Charges By-law as 44.65 million out
of the $68 million total for storm related works. The works total $44.65 million of which $ 17.95
million are funded by development charges, ± $15.75 million from the non-growth
sources (Pre DCA
An
implementation plan is required to prioritize and program these works. Staff request authority to sole source the
consultant engineering assignment to Aquafor Beech Ltd. who prepared the
technical study for the Development Charges Study for the environmental works. As Aquafor Beech Ltd has completed the
detailed evaluation of our watercourses, it would be the most economical and expeditious
means to prepare the implementation plan.
Staff will negotiate the appropriate fee schedule with Aquafor Beech Ltd
to be funded under project #6777.
Project Management
Attachment
‘C’, which denotes the capital funds for just the road/bridges required over
the next 10 years, indicates that the capital program is continuing to increase
and will peak in 2008. Attachment ‘F’
denotes the various steps over a 3 to 5 year time period to implement the
various projects. Some projects required
for construction in 2008 will have to commence this year in respect to design
and approvals. Staff will on a yearly
basis advise through the budget process resources required (i.e. staff
secondment, redeployment, consultant, contract positions) to manage the
projects.
FINANCIAL CONSIDERATIONS:
The
peak construction years as identified in the 10 year Infrastructure Program are
2005-2010. This will result in some strain on the Town’s financial ability to fund
without debenturing. The Corporation
can expect to be in a position to require debentures by 2006 to finance
development related capital projects.
Interest accrued from the need to finance development related projects
is recoverable from development charges from the development charges component
only.
ATTACHMENTS:
Attachment
‘A’ - Map – Town of
Attachment
‘B’ - Map –
Attachment
‘C’ - Town of
Attachment ‘D’ - 10 Year Sidewalk Program (2005-2015)
Attachment
‘E’ - 10 Year Illumination Program (2005 -2015)
Attachment
‘F’ - Road Project Schedule
Attachment
‘G’ – 2005 Property Requirements
|
|
|
Alan
Brown, C.E.T. Director
of Engineering |
|
Jim
Baird, M.C.I.P., R.P.P. Commissioner
of Development Services |
Q:\Development\Engineering\REPORTS\2005\Feb\Report 10 YR Markham Capital
Program.doc