GENERAL COMMITTEE

 

 

 

 

 

TO:

Mayor and Members of Council

 

 

 

 

FROM:

Jim Sales, Commissioner of Community and Fire Services

 

 

 

 

PREPARED BY:

Alan Wolfe, P. Eng., Project Consultant

 

 

 

 

DATE OF MEETING:

March 21, 2005

 

 

 

 

SUBJECT:

Proposed Tendering of the Centennial Community Centre Expansion and Indoor Bocce Courts     

 

 

 


 

 

RECOMMENDATION:

THAT this report entitled “Proposed Tendering of the Centennial Community Centre Expansion and Indoor Bocce Courts” be received;

 

AND THAT Indoor Bocce Courts be included as part of the Centennial Community Centre Expansion project;

 

AND THAT the Mayor and Clerk be authorized to execute an agreement with the Markham Bocce Association that includes a $400,000 capital contribution and a commitment to operate the facility in an agreement satisfactory to the CAO, Commissioner of Community and Fire Services, and the Town Solicitor;

 

AND THAT Council approve tendering the Centennial Community Centre Expansion and Indoor Bocce Courts project;

 

AND FURTHER THAT an extensive green roof on the swimming pool roof be included as a separate item in the tender for the Centennial Community Centre Expansion and that the decision to include the green roof in the project be deferred until the tender award.

 

PURPOSE:

The purpose of this report is to obtain Council authority to include the construction of indoor bocce courts in the Centennial Community Centre Expansion project and to proceed with the tendering of the project.

 

BACKGROUND:

On June 14, 2004, Council approved proceeding with the design of Centennial Community Centre Expansion.  The approximate size of the project is 39,335 square feet (sf) including 23,185 sf of new construction and 16,150 sf of renovation.  The approved cost estimate for this project is $9,881,700.

 

The report also approved, in principle, including an 11,045 sf indoor bocce court with an approved cost estimate of $1,953,600.  The approval is subject to identifying a non – DCA funding source that includes a significant contribution from the Bocce clubs.  Furthermore, the bocce club was required to enter into an agreement with the Town for the operation of the facility.

 

OPTIONS/DISCUSSION:

1)                  CENTENNIAL COMMUNITY CENTRE EXPANSION

 

1.1)            A public meeting was held to review the schematic design with the public and the user groups on July 8, 2004.

 

The public meeting was well attended and the design was well received. There were a number of suggestions made at the meeting.  Attachment “A” summarizes the suggestions and indicates which suggestions were included in the design.  The suggestions that were not included are also indicated, including the reason why they were not acceptable.  The suggestions were reviewed with the Building and Parks Construction Committee (BPCC).

 

A second public information meeting will be scheduled for mid-April to present the final design to interested members of the public and user groups. 

 

1.2)      A meeting was held with the Town’s Accessibility Committee on August 18, 2004.

 

The project consultant and the Architect met with the Town’s accessibility committee. The committee thoroughly reviewed the design. There were a number of suggestions to improve the accessibility of the project that are summarized in Attachment “B”. 

These suggestions have been incorporated into the design where feasible.

In addition, the committee was concerned with the accessibility of the 2nd floor washrooms and boardroom. These concerns were presented to the BPCC. The BPCC supported including these improvements within the project. On this basis, a request for $100,000 was included in the 2005 capital budget for these accessibility improvements.

 

1.3)            Energy improvements have been incorporated into the project.

 

During the design process with the BPCC, the Architect was requested to explore improving the energy efficiency of the building beyond the Town’s current standards. Through this process it was determined that the Town’s current standards resulted in improvements that were 9% higher than building code requirements.  It was further determined that through a further investment of $285,000, the efficiency could be improved to 70% higher than the building code requirements.  These improvements are eligible for a $60,000 Canadian Building Incentive Program (CBIP) grant.  On this basis, the BPCC supported proceeding with the improvements and a report was prepared to Council to approve funding.  Council approved the report on December 14, 2005.

 

It should be noted that the addition of solar power was also investigated. However, the financial analysis indicated that the long payback period did not justify the use of solar power at this time.  If solar technology improves and energy costs increase sufficiently,

consideration should be given to retrofit the facility with solar power capability.

 

1.4)      The architect, recreation staff, and the project manager have worked to finalize the design.

 

Over the past months, the architect has worked closely with the Town staff to finalize the detailed design of the building.  The BPCC has been kept up to date with the design process and has endorsed the current design.

 

1.5)      The design was presented to the Development Services Committee.

 

A site plan approval application was submitted on October 25, 2004.  The various comments from the Town departments have been incorporated into the design.  On January 25, 2005, the Development Services Committee considered a report on the design.  The architect also presented the design to the committee.  The design was approved, in principle, by the committee subject to the finalization of technical issues and with the approval of the final drawings delegated to the Commissioner of Development Services.  The committee also had a number of questions for the architect.  A copy of the architect’s response to these questions is included as Attachment “C”.

 

During the site plan review process, two major issues developed.

 

1.5.1)   During the site plan approval process GO Transit indicated an interest in constructing a parking deck.

 

In response to the circulation of the site plan drawings, GO Transit sent the Town a letter indicating that they would be interested in constructing a parking deck.  As deck parking is consistent with the Town’s parking strategy, the architect was requested to perform a preliminary site fit study to determine if it was feasible to consider a parking deck in this location.

 

The facility fit study indicated that a parking deck could be accommodated in the current GO Transit parking lot.  It would be two-levels above the existing grade (approximately 6.6 metres (22 ft) high).  It would result in a net increase of 200-250 parking spaces on the Centennial site that would be shared with GO Transit.  The parking deck would be located north of the community centre and would incorporate the existing shared GO Transit parking area, the westerly portion of the community centre parking lot and the landscaped berm between the parking lot and the railway.  A plan showing the proposed location is included as Attachment “D”.

On this basis, the Town and GO Transit agreed to further explore the feasibility of constructing a parking deck on the Centennial site by undertaking a utilization study.  The study will determine the utilization of the proposed parking deck, the impact of the parking deck on traffic operations and the road infrastructure and the appropriate sharing of the costs of constructing and operating the facility between the Town and GO Transit. This study should be complete by the end of June 2005.  The results will be presented to Council to determine if further work should be done on constructing a parking structure.

 

The site plan will proceed as currently designed without the parking structure.  If it is decided to proceed with the structure, the site plan will be modified and resubmitted for a new site plan review process.

 

1.5.2)   The Urban Design section requested that the parking lot not be extended into the existing landscape buffers along Bullock Drive and McCowan Road.

 

As part of the review of the site plan design, the Urban Design section requested that the parking lot not be extended into the existing landscape buffers along Bullock Drive and McCowan Road.  In order to accommodate this request, the parking lot will be expanded into the berm area between the parking lot and the railway tracks.  The revised parking lot will provide 550 parking spots of which 350 will be dedicated for community centre use and 200 will be for shared use with GO Transit.

 

These adjustments to the parking lot will result in some additional cost that will be further discussed in costing section of the report.

 

2)         Indoor Bocce Courts

 

2.1)      Staff has negotiated a framework for an agreement with the Markham Bocce Club.

 

On November 22, 2004, the Markham Bocce Club presented a business plan that indicated that the club would contribute $200,000 over a 20-year period to the capital cost of the indoor bocce courts. They also indicated that they were willing to enter into an agreement, which would cover the full operating costs of the facility, with the Town.

 

Commissioner of Community and Fire Services, Recreation Services staff, and Legal staff have negotiated terms of an agreement with the club. This proposal includes an increased capital contribution of $400,000, over a 20-year period, and a commitment to pay for the operating costs of the facility.

 

A copy of the terms for the framework for an agreement proposed by the club is included as Attachment “E” of the report.

 

Recreation Services staff have also canvassed the City of Vaughan and the Town of Richmond Hill regarding their arrangements with bocce clubs operating in their municipalities. They reported that their municipality pay the capital and operating costs of the courts. The bocce clubs use the facility on a user pay basis. Given the Markham Bocce Club’s offer to make a significant capital contribution and pays the full operating costs of the courts, the proposed arrangement compares very favourably to the arrangements with Vaughan and Richmond Hill.

 

On this basis, it is recommended that Council approve proceeding with the indoor bocce courts and accept the Markham Bocce Club’s offer to contribute $400,000, over a period of 20 year period, to the capital cost of the facility and to pay for the operating cost of the courts and that the Mayor and Clerk be authorized to sign an agreement with the club satisfactory to the Commissioner of Community and Fire Services and the Town Solicitor.

 

2.2)      The architect and the Town staff have worked with the Bocce Clubs to design a facility that meets the Club’s and the Town’s requirements for the courts.

 

            There were a number of meetings involving the officials of the Markham Bocce Club, Town staff, and the architect.  The result is a design that meets the Club’s playing and social requirements while also meeting the Town’s requirements for the operation of the facility.

 

      The design was reviewed and endorsed by the BPCC.

 

3)         PRETENDER COST ESTIMATE

 

3.1)            The construction cost estimate has been modified to reflect the inclusion of the indoor bocce courts, accessibility improvements and the energy saving enhancements.

 

In summary, the project currently under consideration consists of a two-floor addition, with a new fitness centre and fitness studio, a multi-purpose room, an exterior translucent ramp, renovations of existing area to accommodate new change rooms, and renovations to the lobby.  The size of this addition includes 23,185 square feet of new construction and 16,150 square feet of renovated area.  In addition, it is recommended to also include indoor bocce courts. The total size of these courts will be 11,045 square feet.  An additional 100 square feet has also been added to the renovation to improve the accessibility on the second floor. The total area of construction is now 50,480 square feet.

 
Lastly, capital improvements to provide a higher level of energy savings have been included in the project.  On this basis, the construction cost estimate approved by Council is as follows:

 

 

 

 

 

 

 

 

TABLE 1

 

Summary of the Construction Costs for the Centennial Community Centre Expansion

 

 

 

Total Cost

New Construction

Bocce Courts

Renovation

Energy

Saving Enhancements

Accessibility Improvements

Construction

$9,040,000

 

$4,910,000

$1,501,000

$2,267,000

$262,000

$100,000

Site

$1,052,000

 

 $712,000

$150,000

$190,000

 

 

Total Approved Construction Cost Estimate

$10,092,000

$5,622,000

$1,651,000

$2,457,000

$262,000

$100,000

  Note : The above costs are for construction only and do not include construction contingency, FF&E, or internal costs.

 

3.2)            The parking lot north of the community centre will not be included as part of the base tender, pending a decision on the GO Transit parking deck.

 

The construction of a GO Transit parking deck will necessitate the complete reconstruction of the parking lot north of the community centre.  For this reason, the reconstruction of the north parking lot should not proceed until Council decides if the deck will be constructed.  As the tender for the community centre expansion is scheduled to be released in April, there will not be a decision on the deck prior to the proposed tender release.

 

In order not to delay the expansion of the community centre, it is proposed to exclude the section of the parking lot north of the community centre from the base tender.

 

There are three decision-making scenarios that may occur during the construction of this project.

 

1)                  Decision to proceed with the installation of the parking deck. 

 

Only the work necessary to modify the existing parking lot to suit the new building location will be done as part of this tender.  The parking deck will be financed, designed and constructed as separate project.

 

2)                  Decision not to proceed with the installation of the parking deck.

 

The parking lot will be constructed in accordance with the approved site plan.  It should be noted that additional funding would be required to complete the project under this scenario.

 

3)                  No Decision on how to proceed

 

Only the work necessary to modify the existing parking lot to suit the new building location will be done as part of this tender.  Once the decision is made, either the parking structure or the parking lot will be completed as a separate project.

 

The current construction schedule indicates that this section of the parking lot would be constructed at the end of the project during the summer of 2006, see Attachment “F”.  An alternative item for all the work in the parking area north of the community centre will be included in the tender with an option to add this work to the contract until the spring of 2006.

 

3.3)            The architect has completed a pretender cost estimate for the project, as described in section 3.1 and 3.2, that is within the approved cost estimate for the project

 

The architect, through his cost consultant, has completed the pretender cost estimate.  The estimate indicates that the design, including the site work described under scenario 1, is approximately 1% higher than the approved cost estimate. The final cost of the project will be determined through the competitive tendering process. Given the margin of error of a cost estimate, the current cost estimate indicates the project is ready to proceed to tendering.

 

Alternative price items will be included in the tender. This will allow for post-tender adjustments to the project cost if the tender price exceeds the approved construction cost estimate.

 

3.4)      If the GO Transit parking structure does not proceed it will be necessary to provide additional funding to complete the site works to meet current Town standards

 

If it becomes necessary to construct the parking lot as described under scenario 2 additional funding will be required.  The amount of the additional funding is currently estimated at approximately $664,000.  The reasons for the additional funding requirement are summarized in Attachment “G”

 

If the parking deck does not proceed, it will be necessary to provide additional funding to complete the north portion of the parking lot in accordance with the approved site plan.  If the parking deck proceeds, the cost of constructing the parking lot will be incorporated into the cost of the structure.

 

4)                  Installation of a Green Roof on Centennial Community Centre

 

During the design of the building, the architect was requested to investigate the feasibility of installing a green roof on a portion of Centennial Community Centre roof as part of this project.  This installation has been discussed with the Manager of Environmental Leadership and she supports seriously considering this option.  The Development Services Committee has also requested an investigation of the feasibility of including a green roof as part of this project.

 

To date, the architect has reviewed the various options available for a green roof and has examined the locations that would be suitable for its installation on the community centre.

 

A green roof is a space created by adding layers of growing medium and plants on the top of a traditional roofing system.  The two types of green roofs are referred to as intensive and extensive.  They are briefly discussed below.

 

Intensive Green Roofs

Intensive green roofs are characterized by their weight, intensive planting and higher maintenance requirements compared to extensive green roofs.  They are typically accessible to the public to allow views of the “garden-like” treatment.

 

This type of roof garden requires significant amounts of soil to be placed on the roof; significant structural and roof membrane improvements are required.  Furthermore, improvements are also required if the roof is to be made accessible.  These considerations result in higher capital costs. The nature of the “garden” plantings also has high maintenance costs.

 

This type of green roof costs in the range of $30.00–$60.00/sf excluding structural, membrane modifications, and accessibility improvements.  Therefore, it would be prohibitively expensive for this application.

 

Extensive Green Roofs

Extensive green roofs are characterized by their low weight, low capital cost and lower maintenance requirements.  These roofs generally consist of hardy drought-resistant low growing plants (sedums) pre-planted in a 75 mm (3 inch) thick growing medium.  They are typically not made accessible as the plantings, although attractive from a distance, are not “garden-like” quality.

 

The plants and growing medium are provided in 1.2 m (4 foot) wide bats that are rolled out onto the new or existing roof.  Due to its lightweight and soil-less nature, this method of providing a green roof does not require any structural or roof membrane improvements.

 

The cost for providing this type of green roof system would be in the range of $15.00–$20.00/sf; therefore, an extensive green roof would be economically feasible for use on the Centennial Community Centre.

 

Selection of Roof Surface

The criteria for selecting a roof surface on the community centre for the green roof include an uninterrupted surface that is visible from the ground level.  It was determined that the most suitable location on the Centennial Community Centre would be the swimming pool roof which is partially visible from the Bullock and McCowan intersection, see Attachment “H”.  The roof surface was replaced approximately 10 years ago and is in good condition. It is anticipated that the remaining life span of the roof is at least 10 years.  The installation of a green roof should extend this life span to 20 years. The location on the building was endorsed by the BPCC.

 

The architect was also asked to quantify the benefits of this installation.  Unfortunately, due to the limited experience with the installation of green roofs in our climate, there is not sufficient data available to provide definitive cost saving achieved through the installation of green roofs. However, the proponents of green roof installations claim that they reduce cooling costs in the summer and heating costs in the winter, improve storm water management by reducing rain water run off, and increase the lifespan of the roof by 2-3 times.  Furthermore, from an over all environmental perspective, the green roofs help incrementally reduce the urban heat island effect and clean dust and pollutants from the air.

 

The estimated cost for the installation on the roof of the swimming pool, including an irrigation system, is approximately $175,000.

 

The Manager of Environmental Leadership has indicated funding may be available for this project from the Markham Environmental Sustainability Fund.  Environmental Issues Committee manages this fund.  Therefore, this proposal should be reviewed by the committee prior to proceeding.

 

So that the tendering process for this project can continue, it is recommended that an extensive green roof on the swimming pool roof be included as a separate item in the tender for the Centennial Community Centre Expansion and that the decision to include the green roof in the tender be deferred until the tender award.

 

FINANCIAL CONSIDERATIONS:

Cost estimates for the construction portion of the Centennial Community Centre project approved in June, 2004 and in the 2005 Capital budget are as follows (excluding construction contingency):

[*Note:  Funding for Bocce Courts was approved in principle subject to a significant contribution from the bocce clubs and/or other sources of funding]

Final funding required for the construction portion of the project (above) is dependant upon the tender bids and will be discussed, in detail, at the tender award stage.

 

BUSINESS UNITS CONSULTED AND AFFECTED:

The Recreation and Culture Services Department, Strategic Services Department, Finance Department, Legal Department, and the Urban Design Section of the Planning Department have been consulted in the preparation of this report.

 

ATTACHMENTS:

Attachment “A” – Meeting Summary from Public Meeting

Attachment “B” - Meeting Summary from Accessibility Committee Meeting

Attachment “C” – Response to Committee from the January 25, 2005 DSC Meeting

Attachment “D” - Proposed Parking Deck Location Drawings

Attachment “E” - Markham Bocce Club Proposal

Attachment “F” – Proposed Limits of Separate Price Item for the North Parking Lot

Attachment “G” – Table of Cost Increases for Site Work 

Attachment “H”-  Proposed Green Roof Location Drawing

 

 

 

 

 

 

 

Barb Roth

Director of Recreation and Culture Services

 

Peter Loukes, P. Eng.

Director of Operations and Asset Management

 

 

 

 

 

Jim Sales

Commissioner of Community and Fire Services

 

 

 

Q:\Commission Share\Operations and Asset Management\Reports\2005\C & U\Facilities\ReporttoGeneralCommityreCentennialCommunityCentreExpansionTender22(Mar.7).doc