General Committee

 

 

 

 

 

TO:

Mayor and Members of Council

 

 

 

 

FROM:

Jim Baird, Commissioner, Development Services

Valerie Shuttleworth, Director, Planning and Urban Design

 

 

 

 

PREPARED BY:

Linda Irvine, Manager, Parks and Open Space Development

Steven Sydij, Senior Construction Buyer

 

 

 

 

DATE OF MEETING:

April 18, 2005

 

 

 

 

SUBJECT:

Tender Award # 022-T-05 Construction of Woodbine North Community Park

 

 

 


 

 

RECOMMENDATION:

THAT the report entitled “Tender Award # 022-T-05 Construction of Woodbine North Community Park” dated April 18, 2005, be received;

 

AND THAT the contract for Tender # 022-T-05 Construction of Woodbine North Community Park, be awarded to the lowest priced bidder, DDR Landscape Contractors Ltd. in their base bid tender amount of $870,165.50 including testing allowance ($8,000) and excluding GST;

 

AND THAT DDR Landscape Contractors, being the lowest bidder for the construction of Woodbine North Community Park, be awarded the following provisional items in Tender #022-T-05 in the total amount of $18,800: a back flow preventer in the amount of $1,500, water meter in the amount of $3,200, internal chamber plumbing in the amount of $3,000, bollard installation in the amount of $1,200, and a low stone wall in the amount of $9,900;

 

AND THAT $85,000 be approved and set aside in the budget for construction contingency purposes for the Woodbine North Community Park and that the Manager of Parks and Open Space Development and the Treasurer be authorized to approve any required contingency items up to the construction contingency amount, and that any contingency funds remaining at the completion of the project will be returned to the “Additional Park Elements Account”;

 

AND THAT Council approve the total cost for this project, as follows:

            Base Bid Price to DDR Landscape Contractors                                      $870,165.50

            Provisional items to DDR Landscape Contractors                                      $18,800.00

            Construction Contingency                                                                         $85,000.00

                                                                                                                          $973,965.50

AND THAT funding for this project, including the base bid, provisional items and construction contingency in the amount of $973,965.50 be provided from:

 

§         Woodbine North Community Park” (account #81-5350-5190-005) in the amount of $527,856.00 and from;

§         “Additional Park Elements”(account #81-5350-6643-005) in the amount of $446,109.50        

 

PURPOSE:

To award contract for Tender #022-T-05 Construction of Woodbine North Community Park.

 

BACKGROUND:

In 2003, Capital budget approval was given to proceed with the design and construction of Woodbine North Community Park (account #81-5350-5190-005) in the amount of $600,000. In 2005, a capital project entitled “Additional Park Elements” (account #81-5350-6643-005) was approved to provide additional funding to selected community park projects and staff have allocated $461,303.33 from this account to Woodbine Community Park. The total project budget is $1,061,303.33 to cover all costs associated with the design, construction, contingency, and internal fees for this project. Of this total budget, the construction cost (which includes the base bid, provisional items and construction contingency) is $973,965.50.

 

 

BID INFORMATION

Advertised, place and date

Electronic Tendering Network, February 25, 2005

Bids closed on

March 18, 2005

Number picking up bid documents

 9

Number responding to bid

 5

 

 

DETAILED PRICING INFORMATION as submitted and corrected:

Contractor

Base Price (excl. GST, including testing allowance)

Provisional Price (all items excl. GST)

DDR Landscape Contractors

$870,165.50

$18,800.00

Gateman Milloy

$883,961.81

$15,605.00

Melfer Construction

$889,486.10

$23,100.00

Rutherford Construction

$909,402.41

$31,132.60

Pine Valley

$912,681.12

$21,400.00

 

The tender was evaluated based on the selection of the lowest qualified bid for the base bid and the combined base bid and provisional bid items.  The bids have been verified for accuracy and compliance with the tender terms and conditions. Mathematical errors in the bids were corrected and are included in this report.

 


FINANCIAL CONSIDERATIONS:

Summary of costs for this project:

            Base Bid Price to DDR Landscape Contractors                                      $870,165.50

            Provisional items to DDR Landscape Contractors                                      $18,800.00

            Construction Contingency                                                                         $85,000.00

                                                                                                                          $973,965.50

 

Staff recommend that funding for this project in the amount of $973,965.50 be approved from the following:

§         Woodbine North Community Park” (account #81-5350-5190-005) in the amount of $527,856.00 and from;

§         “Additional Park Elements”(account #81-5350-6643-005) in the amount of $446,109.50        

 

 

BUSINESS UNITS CONSULTED AND AFFECTED:

The Finance and Purchasing Departments have reviewed this report and support the recommendations.

 

 

 

 

 

 

 

 

Valerie Shuttleworth,  M.C.I.P., R.P.P.

Director, Planning and Urban Design

 

Jim Baird, M.C.I.P., R.P.P.

Commissioner of Development Services

 

Q:\Development\Design\linda\Parks\F&ATenderWoodbine North.doc