General Committee (Finance and Administrative)

 

 

 

 

 

TO:

Mayor and Members of Council

 

 

 

 

FROM:

Jerry Klaus, General Manager of Waterworks

 

 

 

 

PREPARED BY:

Ernie Ting, Manager of Infrastructure

Ivy Ho, Purchasing Supervisor

 

 

 

 

DATE OF MEETING:

May 2, 2005

 

 

 

 

SUBJECT:

Tender Award - 030-T-05, 2005 Relining of Cast Iron & Ductile Iron Watermains

 

 

 

 

RECOMMENDATION:

THAT the report for 2005 Relining of Cast iron & Ductile Iron Watermains, Tender 030-T-05 be received;

 

AND THAT tender 030-T-05 for “2005 Relining of Cast Iron & Ductile Iron Watermains” be awarded to the lowest priced bidder, Fer-Pal Construction Ltd. in the total amount of $902,042.15 exclusive of GST;

 

AND THAT a separate blanket purchase order be issued for contingency in the amount of $90,000 exclusive of GST, the use of which will be governed by the Expenditure Control Policy;

 

AND THAT the award be funded from Waterworks 2005 Capital Account 53-6150-6665-005 (Cement Relining of Iron Watermains) in the amount of $1,282,500.

 

AND FURTHER THAT upon completion of the project the remaining funds be returned to the original funding source.

 

PURPOSE:

The purpose of this report is to obtain Council approval to award Tender 030-T-05 and proceed with the Capital Project.

 

BACKGROUND:

The tender was called for the 2005 Relining of Cast Iron and Ductile Iron Watermains.  The work involves cement lining of watermains in various streets of the Town that are experiencing water quality problems.

 


 

The tender was issued in accordance with the Purchasing By-Law 2004-341.  The tender closed March 29, 2005.  Seven companies obtained the bid document and three companies submitted qualified bids as follows:

 

Contractor

Total Contract Cost (exclusive of GST)

Fer-Pal Construction Ltd.

$   902,042.15

Trisan Construction

$   993,015.00

Spinello Companies

$1,297,112.00

 

The bid documents have been verified for accuracy and compliance with the tender specifications and staff are satisfied that all terms, conditions and bid prices comply with the Town’s requirements.  Fer-Pal Construction was awarded the same tender in 2003-2004 and staff are confident that they will continue to provide satisfactory service.

 

Internal corrosion of watermain pipes is the main cause of poor (rusty) water quality. Internal corrosion mainly occurs in unlined metallic pipes that were installed in the Town’s water distribution system prior the introduction of lined pipes around 1972. Internal corrosion problem has been eliminated with the advent of plastic (PVC) pipes.

 

There is an estimated 160 km of unlined metallic watermain pipes in the Town’s water distribution system. The majority of these watermains are in good structural condition but has poor water quality due to internal corrosion. A 20-year watermain relining program was approved and adopted by Council in 1997. Currently 51,545 metres of watermain have been relined. This year’s rehabilitation is in the Simonston Boulevard area west of Don Mills. This project will complete the entire area east and west of Don Mills south of John Street.

 

The streets under this project were completed in the Roads department accelerated resurfacing program in 2003. At the time, due to set priorities the cement relining program was not able to be re-prioritized in coordination with the resurfacing program. All efforts are being done under this project to minimize road surface cuts or excavation. A ramp will be installed where temporary pipe crossings are required instead of cutting the road. Although unavoidable in this project, only required pit excavation will be allowed. All excavation and road restoration will be completed under the strict restoration standards by the Roads department. Waterworks and Roads department will continue to closely coordinate all projects to avoid the same circumstances. 

 

The 2005 program will complete an additional 5230 metres of cement relining. At the current replacement rate of about 5 km. per year, it is estimated that the program will be completed by 2010.

 

This rehabilitation project extends the life expectancy of the watermain pipe and results in:

  • Restoring water quality to meet the Provincial Drinking Water Regulations standards
  • Least cost of rehabilitation/construction
  • Minimum disturbance and inconvenience to customers
  • Watermain estimated life extension of +50 years
  • Restoration of pipe flow capacity for domestic and fire demand

 

The watermain cement relining program is run in parallel with the watermain replacement program to replace aging watermains. Upon completion of the cement relining program, the budget for this program will then be directed to the watermain replacement program.

 

FINANCIAL CONSIDERATIONS:

The funds for this project are included in the approved 2005 Waterworks Capital Budget for water cement relining of iron watermains account #53-6150-6665-005 with a total budget of $1,282,500.

 

A separate blanket purchase order will be issued for contingency in the amount of $90,000 exclusive of GST, the use of which will be governed by the Expenditure Control Policy.

 

 

Upon completion of the project the remaining funds in this account will be returned to the original funding source.

 

ENVIRONMENTAL CONSIDERATIONS:

None

ACCESSIBILITY CONSIDERATIONS:

None

ENGAGE 21ST CONSIDERATIONS:

This report is consistent with the following:

Infrastructure Management

To build, renew and strategically manage the Town’s infrastructure to meet the demands and expectations of the growing community.

Fiscal Stewardship

To ensure that resources are managed responsibly and taxpayers receive the best value for their money.

BUSINESS UNIT CONSULTED AND AFFECTED:

Customer Services – residents to be informed of the schedule and work to be done on each street.

Fire Department – to be informed of limited fire flow during construction.

ATTACHMENTS:

·        2005 Watermain Cement Relining Project Locations

 

 

 

 

______________________________                        ____________________________

Jim Sales, Commissioner of Community,                       Peter Loukes, P. Eng. Director of        

And  Fire Services                                                        Operations & Asset Management                                            

Q:\Finance and Administration\Finance\Purchasing\2005 File Management\Contract Management\030-T-05 2005 Relining of Cast Iron and Ductile Watermains\030-T-05 Award Report F & A.doc