*2006* |
*2007* |
*2008* |
*2009* |
*2010* |
*2011* |
Phase
1 |
EXPENDITURES |
|
Museum Ward Building |
|
|
|
|
|
|
|
Fees - Architectural Services |
170,000 |
- |
- |
- |
- |
- |
170,000 |
Construction |
|
1,650,000 |
- |
- |
- |
- |
1,650,000 |
Landscaping |
|
- |
50,000 |
- |
- |
- |
50,000 |
Exhibition (Visible Storage) |
|
- |
598,000 |
- |
- |
- |
598,000 |
Contingency (5% of Constr &
Landscapt) |
|
85,000 |
- |
- |
- |
- |
85,000 |
FF&E (incl Disbursements) |
|
|
230,000 |
- |
- |
- |
230,000 |
Total Ward Budilding |
170,000 |
1,735,000 |
878,000 |
- |
- |
|
2,783,000 |
|
Heritage Carnival Grounds |
|
|
|
|
|
|
|
Renovate Wilson Store |
- |
- |
- |
148,919 |
48,351 |
- |
197,270 |
Remove Housser House (2) |
|
- |
- |
- |
- |
36,081 |
36,081 |
Experience Elements - Wilson |
|
|
- |
60,000 |
- |
|
60,000 |
Ride Purchase/Restore |
- |
- |
- |
100,000 |
50,000 |
150,000 |
300,000 |
Ride Install |
|
|
- |
208,230 |
|
127,520 |
335,750 |
Total
Heritage Carnival |
- |
- |
- |
517,149 |
98,351 |
313,601 |
929,101 |
|
Celebration Area |
|
|
|
|
|
|
|
Fees - Architectural Services/Soft
Costs |
- |
- |
- |
- |
90,000 |
|
90,000 |
Remove Strickler House (2) |
|
- |
- |
- |
12,398 |
- |
12,398 |
Remove Rail Complex |
- |
- |
- |
- |
44,443 |
|
44,443 |
Construction |
- |
- |
- |
- |
- |
223,200 |
223,200 |
Total Celebration Area |
- |
- |
- |
- |
146,841 |
223,200 |
370,041 |
|
Other Experience Elements |
|
|
|
|
|
|
|
Fees - Design |
5,000 |
5,000 |
- |
- |
- |
- |
10,000 |
Signage and Exhibits - Village |
20,000 |
20,000 |
45,000 |
- |
- |
- |
85,000 |
Total Other |
25,000 |
25,000 |
45,000 |
- |
- |
- |
95,000 |
|
Phase 1 Capital Costs |
195,000 |
1,760,000 |
923,000 |
517,149 |
245,192 |
536,801 |
4,177,142 |
|
|
|
Ongoing Lifecycle Projects |
|
|
|
|
|
|
|
Building & Site Restoration |
25,000 |
25,000 |
25,000 |
25,000 |
25,000 |
25,000 |
150,000 |
Artifact Restoration |
15,000 |
15,000 |
15,000 |
15,000 |
15,000 |
15,000 |
90,000 |
Site
Drainage Improvement |
- |
- |
20,000 |
- |
- |
- |
20,000 |
Fire & Security Upgrade |
30,000 |
- |
- |
- |
- |
- |
30,000 |
Site Lighting |
|
|
|
|
25,000 |
50,000 |
75,000 |
Parking Improvement - North Lot |
45,000 |
25,000 |
25,000 |
- |
- |
- |
95,000 |
Total
Ongoing Lifecycle |
115,000 |
65,000 |
85,000 |
40,000 |
65,000 |
90,000 |
460,000 |
|
|
TOTAL EXPENDITURES |
310,000 |
1,825,000 |
1,008,000 |
557,149 |
310,192 |
626,801 |
4,637,142 |
|
|
|
|
|
|
SOURCES OF FUNDING |
|
|
|
|
|
|
|
|
|
   
|
500,000 |
500,000 |
500,000 |
500,000 |
500,000 |
500,000 |
3,000,000 |
Ward
Family Contribution |
- |
25,000 |
25,000 |
25,000 |
25,000 |
- |
100,000 |
Corporate Contribution |
- |
25,000 |
- |
- |
- |
- |
25,000 |
Service Club |
5,000 |
5,000 |
5,000 |
5,000 |
- |
- |
20,000 |
Canada/Ont. Infrastructure |
- |
- |
- |
- |
- |
- |
- |
Federal - MAP Grant/ |
- |
50,000 |
- |
- |
- |
- |
50,000 |
Federal - Cultural Spaces |
|
462,000 |
- |
- |
- |
- |
462,000 |
Total Funding |
505,000 |
1,067,000 |
530,000 |
530,000 |
525,000 |
500,000 |
3,657,000 |
|
|
FUNDING SHORTFALL |
195,000 |
(758,000) |
(478,000) |
(27,149) |
214,808 |
(126,801) |
(980,142) |
|
|
CUMULATIVE SHORTFALL |
195,000 |
(563,000) |
(1,041,000) |
(1,068,149) |
(853,341) |
(980,142) |
|
|
|
|
|
Notes: |
|
(1) Budget number are in 2004
dollars |
|
(2) Elements are moved up from Phase II |
|
|
|
|
|
|
|
|
|