REPORT
TO GENERAL COMMITTEE |
|
|
|
|
|
|
|
|
TO: |
Mayor and Members of Council |
|
|
|
|
FROM: |
Alan Brown,
Director of Engineering |
|
|
|
|
PREPARED BY: |
Nehal Azmy, Project Engineer Allan Arbuckle, Manager of
Infrastructure & Capital Works |
|
|
|
|
DATE OF MEETING: |
|
|
|
|
|
SUBJECT: |
Tender Award #098-T-05 Upper Milne Creek
Rehabilitation |
|
|
|
RECOMMENDATION:
THAT the report entitled “Tender Award
#098-T-05 Upper Milne Creek Rehabilitation” be received;
AND THAT the contract for tender #098-T-05 Upper
Milne Creek Rehabilitation be awarded to the lowest priced bidder, Dynex Construction Ltd. in
the amount of $418,375.94 inclusive of 7% GST ( $391,005.55 exclusive of GST);
AND
THAT the tendering process for the retention of the consulting firm be waived
in accordance with Purchasing By-law 2004-341, Part II, Section 7 (1) which
states “When any of the following conditions apply, the Treasurer and the
Manager of Purchasing may, in consultation with the appropriate Director,
negotiate a contract for the supply of goods and services without a competitive
process, which shall be submitted to the Chief Administrative Officer for
approval…(c) when the extension of an existing contract would prove more
cost-effective or beneficial;
AND
THAT staff be authorized to retain the consulting firm of Harrington and Holye
Ltd to provide construction inspection and contract administration services
during construction of the project to an upset limit of $52,328.35 inclusive of
7% GST ($48,905 exclusive of GST).
AND
THAT funds are provided for in the Engineering Department’s 2005 Capital Budget
Account # 83 5350 6777 005 Downstream River Improvement Work Program in the amount of $500,000.00;
AND THAT
a contingency amount of $42,800.00 inclusive of 7% GST ($40,000.00 exclusive of
GST) be established to cover any additional construction costs and that the
Director of
AND
THAT upon payment of all invoices, any remaining funds will be returned to the
original funding source.
PURPOSE:
The purpose of this report is to award the contract for the
construction of the Upper Milne Creek Rehabilitation and
to retain a consultant to provide construction inspection and contract administration
services during construction of the project.
BACKGROUND:
In 2000, the Town completed an Environmental Assessment Report for the
rehabilitation of Milne Creek, a tributary of the
The first phase of the project, the rehabilitation of the lower section
of the Milne Creek was completed in 2003. The current project involves the restoration
of the upper portion of Milne Creek from
PROJECT APPROVALS
All required approvals for the project
have been secured including
Advertised,
place and date |
Electronic
Tendering Network |
Bids
closed on |
|
Number
of contractors picking up bid documents |
13 |
Number
of contractors responding to bid |
3 |
Detailed pricing information as submitted is as follows;
|
Contractors |
Prices Exclusive of GST |
1 |
Dynex
Construction Ltd. |
$391,005.55 |
2 |
560789 Ontario Ltd. O/O R & M
Construction. |
$481,242.39 |
3 |
|
$584,844.00 |
CONSULTANT SERVICES
Harrington Hoyle
Ltd. having undertaken the design and preparation of the tender for the Milne
Creek rehabilitation are best suited to undertake the contract administration
of this project. Staff have negotiated a
fee to provide full time supervision of this construction project.
PROJECT SCHEDULE
No work is
permitted within the watercourse during the period from April 1st to
June 30th. Subject to Council’s award of this tender, construction
of the project is scheduled to commence in early July and to be complete by the
end of October 2005.
FINANCIAL CONSIDERATIONS
Staff recommends
that the tender for contract #098-T-05 Upper Milne Creek Rehabilitation be awarded to the lowest
priced bidder, Dynex Construction Ltd. in the amount of $391,005.55 exclusive
of GST and that the consulting firm of Harrington and Hoyle Ltd be retained to
provide construction supervision and contract administration services for the
project in the amount of $48,905 exclusive of GST.
The total cost of constructing this
project is as follows,
Item |
Cost incl. 7% GST |
Cost excl. GST |
Construction Cost |
$418,375.94 |
$391,005.55 |
Construction Inspection
& Contract Administration fee |
$52,328.35 |
$48,905.00 |
Contingency allowance |
$42,800.00 |
$40,000.00 |
Engineering Department
Project Management Fee @ 4% |
$20,544.00 |
$19,200.00 |
Total Project Cost |
$534,048.29 |
$499,110.55 |
Funding
for the project will be provided from the Engineering Department’s 2005 Capital
Budget Account # 83 5350 6777 005 in the amount of $500,000.
ATTACHMENTS
Attachment “A” – Site Location
Attachment “B” – Consultant’s tender
recommendation letter
|
|
|
Alan Brown, C.E.T. Director of Engineering |
|
Jim Baird, M.C.I.P., R.P.P. Commissioner of Development Services |