GENERAL COMMITTEE (FINANCE AND ADMINISTRATIVE)

 

 

 

 

 

TO:

Mayor and Members of Council

 

 

 

 

FROM:

Jim Sales, Commissioner of Community and Fire Services

 

 

 

 

PREPARED BY:

Eardley Adams, Project Manager

 

 

Deborah Walker, Manager, Library Strategy

 

 

DATE OF MEETING:

August 29, 2005

 

 

 

 

SUBJECT:

Proposed Tendering of the Markham Village Library Expansion and Renovation

 

 

 


 

RECOMMENDATION:

THAT this report entitled “Proposed Tendering of the Markham Village Library Expansion and Renovation” be received;

 

AND THAT the revised cost estimate of $10,502,055 outlined in Table 1 on Page 3 of this report be approved;

 

AND THAT the revised square footage of 38,360 square feet (12,500 sf for the expansion, 6,300 sf for the Library Administration replacement and 19,560 sf for the renovation) be approved;

 

AND THAT the current funding shortfall in construction, contingency & internal costs, in the amount of $2,364,408, and the proposals to mitigate the shortfall outlined in Table 3 on Page 5 of this report be reviewed in further detail by Finance and reported to Council in the construction award report for the Markham Village Library;

 

AND THAT the Furniture, Fixture & Equipment portion of the project, in the amount of $741,405, and the Collections costs, in the amount of $1,144,600, be funded from the Development Charges Reserve;

 

AND FURTHER THAT Council approve tendering the Markham Village Library Expansion and Renovation as a single-phase project.

 

PURPOSE:

The purpose of this report is to obtain Council authorization to tender the construction of the Markham Village Library expansion and renovation project as a single-phase contract.

 


BACKGROUND:

The Markham Village Library is located at the southeast corner of Markham Main Street and Highway #7, in Ward 5, and within the Markham Village Heritage Conservation District.  The present building is not large enough to serve the existing community.  The expansion of the Markham Village Library is a reflection of the continuing need of a growing community and will improve public seating capacity, reduce overcrowding in the collections area, improve collections and allow for collection expansion, improve access to the collections, increase the space to facilitate movement of people, create dedicated space for computers and access to e-based information, improve the entrance lobby and provide space for standard features found in modern libraries that include material security, Self-Check units, dedicated quiet study areas, computer training labs, children and youth areas, and areas reserved for activities such as food vending and book sale space. Included is the relocation of the Library’s Administration and Technical Services functions to the lower level of the expanded Markham Village Library, which will improve public access to the Library’s Administration.

 

On June 22, 2004, Council approved Option 4 of the Schematic Design of the Markham Village Library Expansion.  The approximate size of the project is 35,310 square feet (sf) including 15,750 sf of new construction and 19,560 sf of renovation.  Council approved the Schematic Design Construction cost estimate for the New Construction, Replacement and Renovation which is summarized below which included an additional 1050 sf of administration floor area:

 

 

New Construction

Replacement

Renovation

Total

Construction

$3,095,850

$1,294,309

$2,101,925

$6,492,084

Note: The above cost for construction includes contingency but does not include FF&E, Collections and Internal Costs.

 


PRE-TENDER COST ESTIMATE

 

TABLE 1

 

(A) - Detailed explanation for construction cost increases is included in Attachment “B”

(B) - Construction contingency was increased by $116,853 due to higher construction costs and to account for a project that is a mix of new construction and renovation.  Normally the percentage of renovation construction contingency is higher than for new construction.  In this case the blended construction contingency in the revised cost estimate has been established at 6% of construction.

(C) - Detailed breakdown of Internal Costs in included in Attachment “F”

 

Not included in the project is a large portion of landscaping, it is anticipated that any shortfall in landscaping at this stage will be provided during the Landscaping Master Plan implementation (See Attachment C for more details).  Also the existing condenser unit required for ice making refrigeration in the Markham Community Centre arena will remain without modification. Both these resulted from cost reduction measures.

 

However, it should be noted, the final cost for this project will be determined with the construction tender.

 

 


FINANCIAL CONSIDERATIONS:

As outlined in Table 1 (on the previous page), the original cost estimate for this project of $9,245,204 has increased by $1,256,851 to $10,502,055.  The $1,256,851 increase is in the areas of construction, construction contingency and internal costs (e.g. increase from $7,359,199 to $8,616,050).  Funding for the original cost estimate, $7,359,199, for construction, contingency, and internal costs is outlined below:

 

TABLE 2

 

The $1,107,557 labelled as “Non-Development Charge Sources”, in Table 2, represented the amount in excess of Development Charges in June 2004 and still requires a funding source to be identified (e.g. funding shortfall).  With the cost increase of $1,256,851 in the revised cost estimates, the funding shortfall is expected to increase.  However, the following funding sources were proposed to mitigate the increases in the revised cost estimate:

 


TABLE 3

 

 

(A)     As outlined in Attachment B (page 10), the new construction portion of the project has increased by 2,000 sf due to the energy improvements.  Accordingly, the Development Charges amount has increased by a total of $469,380 ($422,442 DC Reserve Fund (90%) + $46,938 from the 10% Non-DC Reserve) based on a cost per square foot of $234.69 in the DC Background Study.

 

(B)     As outlined in Attachment B (page 10), the estimated energy savings from the energy improvements is $24,000 per year.  The Library has proposed the removal of $24,000 from the future base operating budget for utilities in the expanded building in order to fund $250,000 of the funding shortfall.  In addition, the energy improvements qualify for a Canadian Building Incentive Program Grant which is estimated, by the architect, to be $48,000.  These sources of funding would require up-fronting by the Town until the savings are achieved/grant is received.

 

(C)     The Library Board also proposes to fund $207,000 of the shortfall from 2006 Operating Savings projections due to the closure of the Markham Village Library during construction.  The proposed savings will be further reviewed by Finance.

 

The current funding shortfall, in the amount of $2,364,408, is based upon the revised cost estimate and may increase/decrease based upon construction pricing resulting from the construction tender close.  Therefore, the current funding shortfall and the proposals to mitigate the shortfall (as shown in Table 3) will be reviewed in further detail by Finance and will be reported to Council in the construction award report for the Markham Village Library. 

 

The Furniture, Fixture & Equipment portion of the project, in the amount of $741,405, and the Collections costs, in the amount of $1,144,600 (see Table 1) agree to the 2004 Development Charges Background Study and it is recommended that they be funded from the Development Charges Reserve.

 

ATTACHMENTS:

Attachment “A”- Discussions with the Public, Accessibility Committee and Heritage Markham

Attachment “B” – Explanation for cost increases subsequent to June 2004 Council Report

Attachment “C” – Landscape Master Plan

Attachment “D” – Cost Savings Identified

Attachment “E” – Resolutions of the Markham Public Library Board

Attachment “F” – Increase in Internal Costs

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Catherine Biss, CEO,

Markham Public Libraries

 

Peter Loukes, P.Eng.

Director of Operations and Asset Management

 

 

 

 

 

 

__________________________________________

Jim Sales

Commissioner of Community and Fire Services

 

 

 

 

 

 

 Q:\Commission Share\Operations and Asset Management\Reports\2005\C & U\Facilities\Markham Village Library Tender Approval Gen Comm - Aug29, 2005.doc


                                                                                                           

ATTACHMENT “A”

 

DISCUSSIONS AND REVIEW OF DESIGN DEVELOPMENT OF THE MARKHAM VILLAGE LIBRARY EXPANSION BY THE PUBLIC, ACCESSIBILITY COMMITTEE AND HERITAGE MARKHAM

 

A.1 public meeting was held to review the schematic design on June 9, 2004

 

At the June 9, 2004 public meeting, which was well attended, the Library design was well received.  There were a number of suggestions related to site issues which will be incorporated into the Landscape Master Plan under the direction of the Urban Design section.   The suggestions were reviewed with the Building and Parks Construction Committee (BPCC) as the design progressed.  A second public meeting will be scheduled to present the final site plan, elevations and floor plan design to interested members of the public and user groups.

 

A.2 The Town’s accessibility committee suggested improvements to the project

 

The project consultant and Architect met with the Town’s Accessibility Committee on October 20, 2004.  The Committee thoroughly reviewed the design. There were a number of suggestions noted to improve accessibility to the project that have been incorporated into the final design with minimal cost impact.  These costs were included in the May 2005 cost estimate.  The two major improvements were the provision of a larger elevator and larger washrooms.  The increase in size of these components will accommodate wheel chairs, motor scooters, and quadriplegic change tables.

 

A.3 Heritage Markham preferred an alternative to roof mounted mechanical equipment and requested soft natural earth tones for exterior masonry

 

On October 13, 2004 and April 25, 2005, the Architect presented an overview of the elevations to the Heritage Markham Committee.

 

Heritage Markham preferred to not have the mechanical equipment located on the roof of the building, and requested the Architect review other alternatives.

 

Heritage Markham had no objections to the elevations for the proposed addition, subject to staff reviewing the colour and material boards for shingles, brick colour, and size and other material.  Also Heritage Markham prefers a soft, natural earth tone brick colour, which will be incorporated into the final design.


                                                                                                            ATTACHMENT “B”

 

DETAIL EXPLANATION FOR COST INCREASES FOLLOWING THE JUNE 2004 REPORT

 

Col #.

Description of increased cost

Cost

May 2005 Cost Estimate

B.1

Cost escalation – Two components led to this factor:

  1. Steel cost escalation $313,147
  2. Construction postponement from May to September $73,000

$   386,147

Included 

B.2

Underground Storm Water storage – This is required as a result of expanding the parking lot.

Waste Management Room – Estimated cost to renovate an existing storage room located at the south end of the arena.

$   101,680

 

$     10,520

Included

 

Included *

B.3

Window Replacement Lower Level – This improvement to the south elevation of the basement would increase the amount of natural light and help to improve the working environment.

$     18,651

Included

B.4

Energy Conservation measures

$   250,000

Included

B.5

Road Entrance improvements – Resulting from the traffic consultant’s recommended modification to the intersection and resurfacing of the entrance road access to the parking lot. 

$     85,000

Included *

B.6

Asbestos removal allowance – Asbestos has been confirmed to exist in the exterior stucco cladding; removal of all asbestos stucco will be necessary.

$     40,000

Included **

B.7

Upgraded hydro service

$     35,000

Included

 

Total

$   926,998

 

* Items added resulting from Site Plan Approval* requirements and Asbestos abatement**.

 

B.1   Cost Escalation

There are three components that have significantly increased cost on this project they are:

 

a)             Steel Cost – this component is the single largest contributor to increased cost and its impact has been felt throughout the construction industry and in every component containing steel. The steel escalation cost is estimated at $313,147.

 

b)             Project Postponement – A host of elements has combined to significantly delay the construction of this project.  This postponement has escalated the project cost by an estimated $73,000

 

 

B.2    The Site Plan was approved by the Development Services Committee on May 17, 2005

 

A site plan approval application was submitted on March 21, 2005. The various comments from the Town departments have been incorporated into the design.  On May 17, 2005, the Development Services Committee considered a report on the design.  The Architect presented the design to the committee.  The design was approved, in principal, by the committee subject to the finalization of technical issues and with the approval of final drawings delegated to the Commissioner of Development Services.

 

Underground Storm Water Storage

The project includes the expansion of the parking lot.  Town policy requires that, where new parking lots are constructed or existing parking lots are expanded, storm water discharge shall be retained on site for a period of time to lessen the impact on the river system.  In the case of this project, the method used to retain storm water on site is by the installation of large diameter underground concrete pipes at a cost of $101,680.  This method of retaining water on site will also assist in preventing possible basement flooding.

 

Waste Management Facility

During the review, it was noted a waste management room would be a desirable addition to the facility.  This can be accommodated by making some modification to a storage room on the south side of the existing arena building, at an estimated cost of $10,520.

 

 

B.3    Basement windows will be replaced and made larger to improve the environment for library administration offices

 

The existing basement windows on the south elevation of the building serves to provide natural light to the existing multi-purpose / meeting rooms and are used intermittently for short periods of time.  Upon reviewing the basement use as a Library administrative centre where employees will be spending eight hours per day five days a week, it was considered more appropriate to increase the amount of natural light to improve the proposed office environment.  The decision to increase the window area was approved by the Library Board and the BPCC.  The cost of this improvement is estimated at $18,651.  Windows in the remainder of the building will be replaced the cost of which is included in the cost estimate.

 

B.4     A decision was made to relocate the mechanical equipment from the roof to the basement within the building

 

Following the meeting with Heritage Markham on October 13, 2004, the Architect met with Town staff to discuss options to locating the mechanical equipment on the roof.  Furthermore, the mechanical engineer also indicated that indoor equipment would have a life cycle double that of equipment installed on the exterior.

 

This matter was presented to the BPCC. Given the constraints of heritage planning, design, and cost the decision was made to place the mechanical equipment in the basement. This added an additional 2,000 square feet of basement space at an estimated additional cost of $200,000 or $100 per sq. ft.

 

Energy Improvements incorporated into the project and funded by operational savings

 

During the design process, the BPCC requested the Architect to explore improving the energy efficiency of the building beyond the Town’s current standards.  Through the evaluation process it was determined that an investment of $250,000 would result in an annual operational cost saving of 24.4% (or $24,000 per year) compared with the Town’s current standard.  The energy savings would result in a cost recovered of the investment in 10.4 years.  These improvements are also eligible for a $48,000 Canadian Building Incentive Program (CBIP) grant.  The placement of the HVAC equipment in the basement is the most cost effective and cheapest floor space available.  The additional 2000 sq. ft. of basement floor space is necessary to accommodate the mechanical equipment and the capital cost of the additional floor space plus the more environmentally friendly and energy efficient equipment is included in the $250,000.

 

Additional Design Fees ($23,000) and fee for preparation of the CBIP grant application ($10,000) is included in the Increases in Internal Fees (Attachment F).

 

The Library Board has proposed the use of expected operating savings of $24,000 per year and $48,000 CBIP grant to fund the Markham Village Library project.  On this basis, the BPCC supported proceeding with the design of the improvements.

 

B.5    The existing entrance to the Library Parking Lot at Reeve Drive has been reviewed and is acceptable to the Traffic Engineer and the community

 

A public meeting with Reeve Drive residents was held on February 23, 2005.  The project’s traffic consultant, Poulos & Chung presented its study and analysis of traffic conditions on Cosburn Road and Reeve Drive and pointed out the pre-existing deficiencies of design of Reeve Drive at the Library entrance.  He went on to present 2 options:

 

Option 1

The construction of a new 4 way stop junction located at the intersection of Reeve Drive and Reeve Drive, south of the existing entrance with a pedestrian crossing to access the Library property.

 

 

 

 

Option 2

Will utilizing the existing entrance with modification to the entrance design.  The consultant pointed out that both entrances would work equally as well, though option 1 had the advantage of improved traffic and pedestrian control.

Following the presentation, residents indicated by a large majority their preference for option 2 (modifications to the existing entrance rather than a new access road with 4 way stop signs located south of the existing access).   A further public meeting with Reeve Drive residents and the local ward Councilor was held to review details of the modifications presented at Development Services Committee on May 17, 2005.

 

It is recommended that option 2 be implemented.  This option has been incorporated into the design.  The cost of this work estimated at $85,000 was not included in the original estimate and will increase the project cost.

 

B.6    The presence of Asbestos has been identified in the exterior stucco and some of the stucco material will need to be removed

 

An environmental audit of the building was conducted by an environmental engineering firm who identified the exterior stucco to contain asbestos.  This type of asbestos is harmless in its present form or if left undisturbed.  However, this project requires the expansion of the existing building to the east which requires the entire existing east elevation to be cleared of stucco. Also the steel frames on the south elevation which are built into the building presently support lattice.  These steel frames will need to be removed, and the removal operation will cause some damage to the existing stucco around the steel frames.

 

The asbestos removal will be strictly controlled, and no other work will be allowed to continue within that area while the asbestos removal operations are in progress.  As it is unclear precisely how this will affect the project, an allowance of $40,000 has been set aside for the removal of all the exterior stucco containing asbestos.

 

B.7   An upgraded Hydro service will be required

 

An examination of the existing electrical supply resulted in the need for an upgraded hydro service to supply the existing and the new expanded Library.  The cost of this upgrade is estimated at $35,000.

 

Over the past months, the Architect has worked closely with Town staff to finalize the building design.  BPCC has been kept up-to-date with the design process and has endorsed the current design. 


                                                                                                            ATTACHMENT “C”

LANDSCAPE MASTER PLAN

 

The Landscaping Master Plan for the entire property is contingent on several related issues

 

The Architect’s sub-consultant Scott Wentworth, Landscape Architect, is presently working with Urban Design staff and the Technical Advisory Committee to produce a Landscaping Master Plan for the park property in which the Library is situated.  The Master Plan is an important element of the overall park design and ties-in the community and its surroundings to form a key component to the development.  The Master Plan is an important feature that is distinct and separate to the site plan approvals process.  The Master Plan will be taken to the community for public review once the work of developing appropriate options has been completed.   The implementation of the Master Plan is reliant on several issues: the new “Viva” transit system, the Highway 48 and Highway #7 intersection improvements, reconstruction of Highway 48 south of Highway #7, the construction of approximately 35 new residential homes south of the Library and the completion of the Library expansion.  The Urban Design staff will address the Master Plan final design, its cost, phasing the implementation and tendering under separate report.

The landscaping included in the project is consistent with the options presented in the master plan.

 

 

 

 


ATTACHMENT “D”

COST SAVINGS

 

To balance the design and achieve as close as possible Council’s approved cost estimate, staff, the Architect and the Library Board reviewed the design and construction plan for elements of the design that could possibly be eliminated without having serious operational impacts on the facility.  The second analysis considers the impact these changes would have on Library operations.  The result is a table containing project cost savings that are agreeable to staff and the Library Board.

Col. #

Description

Amount

 

One Phase Construction

Design Savings:

 

 

Landscape

 

1.   

Grass seed + concrete walks only

$30,000

2.   

Do not move condenser

$36,000

 

Building Exterior

 

3.   

Asphalt shingles on addition

$47,000

4.   

(Single phase) Capital construction cost savings

$106,000

 

Sub total

$219,000

 

Other Savings:

 

5.   

Energy conservation over 10 years

$250,000

6.   

During construction Library savings

$207,000

 

Sub total

$457,000

 

D.1&2  Landscape

The Landscaping will be provided during implementation of the Landscaping Master Plan and the arena condenser will be retained

The Landscape budget was reduced significantly by replacing planting materials with grass seed and keeping concrete sidewalks, where necessary.  The intent is to have the Landscaping Master Plan provide further landscaping around the building, at some future time.  No reduction of landscaping is contemplated to the area between the arena and proposed Library.

 

The moving of the arena condenser is seen as not critical to the Library’s functional operations, although some improvements to the acoustic protection of the new Library will be necessary.  (The cost of these acoustic measures is reflected in the savings.)  The condenser unit is required for ice making. The life expectancy of the arena has been stated to be between 6 to 10 years and the condenser will no longer be required once the arena is decommissioned.

 

 

D.3  Building Exterior

The proposed sheet metal roof will be replaced with asphalt shingles

Replacing sheet metal roofing on the addition with asphalt shingles will not affect Library programming and will provide a significant saving.  The asphalt shingle roof will have a 20-year guarantee and will need to be replaced at or about that time; however, the sheet metal roof would not need to be replaced for 40 years or more.  The renovation of the existing building includes replacement of the existing asphalt shingle roof with asphalt shingles.

 

These cost savings have been incorporated into the current cost estimate.

 

D.4  Single Phase Operational Savings

Significant savings are achieved by adopting a one-phase construction approach

The Town of Markham Public Library Board has endorsed a one-phase construction process and directed Library staff “to present options for relocation of library services from the existing location during the one phase construction process to a temporary location in the Markham Village Area.”  The operational savings identified in this One-Phase Construction program are predicated on alternative accommodation being available on a temporary basis at no additional cost during the construction operation.  The temporary location under consideration includes the 1st and 2nd floors of the Markham Village Community Center.  The Commissioner of Community and Fire Services has directed staff to investigate this location fully as it seems to meet all functional requirements, including Telecommunications, Voice and Data and at no rental cost to the Town.

 

A single-phase construction process benefits this project in many ways

 

The Architect recommends that the expansion and renovation of the existing Library be completed as one operation, due to the opportunity for reduced construction costs, the increased assurance of safety-code compliance and reduced public inconvenience.  The analysis is stated below:

 

·                 In a two-phase construction process, there would be no safe or convenient means for the public to access the Library from the parking lot.  Construction traffic will route through the parking lot and around the west end of the existing building.  This means, during phase one, that Library customers would have to access the existing building through a parking lot that would also serve as a construction traffic route.  During phase two, while the existing building underwent renovation, the public, to reach a temporary entrance point into the new structure (probably through a temporary door in a bay window on the west façade), would have a long walk from the parking lot around the west end of the building, with exposure to unsafe conditions from to construction traffic and other construction activity.

 

·                    Building codes require two exit stairs for a public library facility.  Since the exit stairs in the existing building’s northeast corner will have to be blocked/demolished early in the construction process, each of two construction phases would involve the cost of constructing temporary exit stairs on scaffolding to meet code.

 

·                    Operating Library services next to construction would result in construction dust and odours in HVAC systems (old and new).

 

·                    In a two-phase construction process, a shutdown period of at least one month would be required to integrate the old and new structures.

 

·                    In a two-phase construction process, existing collections, IT components, stacks, and other furnishings must be moved at least twice.

 

·                    In a one-phase construction process, 4 months of construction time and $106,000 in capital construction cost will be saved through cost avoidance.

 

·                    A one-phase construction process entails less risk for both the builder and MPL as owner.

 

Therefore, the Architect recommends construction and renovation should proceed as one-phase and Library services from the current location be suspended during construction. 

 

The Town of Markham Public Library Board and the BPCC had reviewed and concur with the Architect’s recommendations on the understanding that a suitable alternative location for a temporary Library would be available.

 

Through the cooperation of the Recreation Department, the ground floor of the Markham Village Arena is available as a temporary Library during the period of construction and renovation of the new facility.  The Technical Advisory Committee (TAC) is working to produce a transition strategy and a project management plan for this change-over to occur.  Any modifications to the Arena ground floor space will be completed and operational before construction on the new facility begins.  On that basis, it is recommended that Council approves proceeding with a single phase construction of the expansion and renovation.

 

D5.      The explanation of energy conservation is explained in attachment ‘B’ sub clause B4.

 

D6.      The explanation of library operational saving during construction is explained in attachment ‘E’.

 


 

ATTACHMENT “E”

 

 

RESOLUTIONS OF THE MARKHAM PUBLIC LIBRARY BOARD

 

Analysis of Savings supported by Town of Markham Public Library Board

The above summary and analysis of potential cost savings was discussed with the Town of Markham Public Library Board (TOMPLB) at a meeting held on February 28, 2005.  The TOMPLB gave careful consideration to all items in detail and concluded with the following motions:

 

“RESOLVED THAT:  The Library Board has considered a number of options to deal with the difference between the design and construction cost estimate approved by Council on June 24, 2004 for $6,492,084 and the January 2005 construction estimate of $7,286,611 prepared by Shoalts and Zaback Architects and recommends the following: 

 

AND THAT: while the Board appreciates the considerable budget pressures that face Council, we do not believe that the increased cost of steel and other building materials should reduce the approved functional program and space for the Markham Village Library expansion.

 

AND THAT: in the spirit of sharing the budget problem so as to reduce the cost to the taxpayers of Markham, that the following options have been considered by the Board and are presented to Council as the Library Board’s proposal to reduce the difference:

 

One Phase Construction savings:

 

  • Capital Construction cost savings                                                          $106,000
  • Operating Budget savings during library closure                         $207,000

 

Modified version of landscaping                                                                        $  30,000

Asphalt shingles on the addition                                                             $  47,000

Not to move the arena condenser                                                                      $  36,000

 

Total Savings                                                                                                 $426,000

 

RESOLVED THAT:  the library staff is directed to respond to the Architect’s report and ask the Architects to consider that response in preparing its report to town staff, specifically, parking, elevator and ramp.

 

AND FURTHER THAT:  the Architects seek a response and recommendations from the accessibility committee as to those aspects of the report.

 

 

 

                                                                                                                                                                                                                                                                                                                                                                ATTACHMENT “F”

 

 

Markham Village Library Expansion and Renovation

 

Internal Costs – Cost Breakdown Table

 

Col. #

Description

Cost Allocation

Original Amount

Increased by

 

Fees for Service

 

 

 

  1.  

Design Fees

$599,650

$ 574,650

$  25,000

  1.  

Disbursements

$  30,000

$   50,000

-$ 20,000

  1.  

Miscellaneous Fees

$  20,000

$   20,000

$

  1.  

Project Management Fees

$  14,000

$

$  14,000

  1.  

Security

$110,000

$  50,000

$  60,000

  1.  

Fee Contingency

$  62,465

$  62,465

$

  1.  

Signage

$  50,000

$  50,000

$

  1.  

Miscellaneous Expenses (Moving)

$  80,000

$  60,000

$  20,000

  1.  

IT Cables (Voice and Data)

$  57,000

$

$  57,000

  1.  

Insurance

$  20,000

$

$  20,000

  1.  

Communications

$    4,000

$

$    4,000

12.

Design Fee ($23,000) for Energy Improvements & Fee for preparation of Canadian Building Incentive Program grant application ($10,000)

$  33,000

$

$  33,000

 

Total

1,080,115

$  867,115

$213,000

 

Q:\Commission Share\Operations and Asset Management\Reports\2005\C & U\Facilities\Markham Village Library Tender Approval Gen Comm - Aug29, 2005.doc