|
|
|
|
|
|
|
|
|
|
TO: |
Mayor and Members of Council |
|
|
|
|
FROM: |
Alan
Brown, Director of Engineering |
|
|
|
|
PREPARED BY: |
Ralph Ehlers,
Capital Engineer |
|
|
|
|
DATE OF MEETING: |
2005-Oct-17 |
|
|
|
|
SUBJECT: |
Region of York Individual Environmental Assessment Markham By-Pass from Hwy 407 to Morningside
Road |
|
|
|
RECOMMENDATION:
That the staff report entitled “Region of York Individual
Environmental Assessment, Markham By-Pass from Hwy 407 to
And that the recommended alignment developed through
the Environmental Assessment (EA) for the proposed four-lane arterial road
between the Markham Bypass / Highway 407 interchange and
And that the
Regional Municipality of York be requested to review
with the Town of
And that Town staff be authorized to hold a Public
Meeting when the Box Grove Developer submits an Official Plan Amendment and/or
Rezoning Application for the location of a Service Station to the east side of
the By-Pass, within the Box Grove Secondary Plan area.
And that Mr. B. Macgregor, Commissioner of Transportation and Works,
Regional Municipality of York be advised accordingly.
PURPOSE:
This report seeks the endorsement of Council regarding the preferred
alignment of the Markham By-Pass from Hwy 407 south to
BACKGROUND:
The Region of York is nearing the completion of
the Environmental Assessment for the Markham By-Pass from Hwy 407 south to
A comprehensive public consultation process
involving input from the public, adjacent landowners, provincial and public agencies
has been followed in developing the preferred design. The Region and their
consultant presented to the Town’s Transportation Committee on
A member of the Boxgrove
Ratepayers Association wrote the Region’s consultant on
The Owner of the Parkview Golf Club expressed
concern over the preferred alignment and the impact on the Golf Club. They
requested the Region to meet with them to discuss options other than the
preferred alignment which would impact less on the Golf Club.
A subsequent site visit and workshop with the
Town, Region and owner of Parkview Golf Club took place on
The Town received a letter from Box Grove Hill
Developments Inc. to the Region on
w The relocation of a proposed
automobile Service Station to the east side of the By-Pass;
w The Service Station be
provided with a full movements signalized intersection at
w The Service Station be
provided with a right-in right-out access at the north end of the site;
w A satisfactory layout for the
service station can be accommodated on the proposed site;
w The proposed Service Station is not referred
to the Ontario Municipal Board.
The owners of the Highcock
property, on the east side of the preferred alignment attended the presentation
on September 1, 2005 and are having further discussions with the Region and the
Box Grove Developer regarding the alignment and the impact on their property.
Subsequent to the Workshop of
OPTIONS/DISCUSSION:
Alternatives Evaluated
The Region’s project team developed and evaluated nine
distinct alternative alignments and presented them to the public in April
2005. As part of the recent consultation
with the public and stakeholders, most of the discussion and interest focused
on four of the nine alternatives.
The preferred alternative and alternative A2 were
reviewed further at a Workshop held on
Public
Consultation
The Region’s project
team undertook the following consultation activities:
w
PCCs on
w
Presentation
to the
w
Presentation
to the
w
Presentation
at a
w
Presentation
at a Markham Council Workshop on
One of the key conclusions reached during the recent
public and stakeholder consultation and reported in the Region’s Committee
report is that there are no easy answers and no one solution will satisfy all
stakeholders. With any significant
undertaking, there will be impacts to the natural environment as well as to
area landowners, residents, businesses and the development community. The project team has focused on mitigating
adverse impacts to the extent possible and to finding a fair balance between
the interests of the various stakeholders.
Deadline For
Filing the EA
The February 1999
Morningside Heights OMB Decision provided for a Morningside Avenue extension in
a 36m right-of-way through part of the Morningside Heights lands in Toronto,
with a condition that an EA study for the northerly extension to Steeles Avenue be submitted for approval by December 31,
2005, or that the Terms of Reference for such a study be submitted for approval
by December 31, 2004. Failing such
submissions, the further extension of
The Terms of
Reference were submitted to the Ministry of the Environment on
The deadline for
submission of the final EA by
Recommended Alignment at Highway 407
The Markham Bypass
has recently been constructed from Highway 407 to Highway 7 and includes a
partial interchange with Highway 407 to and from the north. Once the Markham Bypass is extended to the
south, there will be a need to complete the interchange to allow access to the
highway from the south.
The additional
ramps that will be required were not included in the EA undertaken for the
Highway 407. In order to avoid having to
do a separate EA for completion of this interchange, the missing ramps have
been included in the EA for the Markham Bypass to Morningside Avenue Link. There is currently no funding commitment from
the 407 ETR to construct these ramps and funds are not included in the Region’s
DC Bylaw. A separate report to the
Recommended Alignment South of Highway 407 to the CP
Rail
Immediately south
of Highway 407, the proposed alignment impacts lands owned by Box Grove Hill
Development Inc. and M. Highcock.
The Highcock property includes an old farmhouse occupied by the
landowners along with barn structures near the west limit of their site. Their lands are designated
The alignment
through the Box Grove Hill land falls within the Phase II Box Grove Secondary
Plan development phasing. This area of
the Box Grove Hill land has not been draft plan approved and must accommodate
the final alignment of the Markham Bypass Extension in accordance with the Box
Grove Secondary Plan (Markham OPA 92).
Representatives of
Box Grove Hill Developments have also attended the PCCs
for this project. They have identified
concern with the alignment that was presented to Committee on
Following the
input received by the adjacent landowners, the Region’s project team developed
a refined alignment with the following key features:
·
Provides
acceptable geometry consistent with the design speed of the road and with the
required MTO standards at the Highway 407 interchange.
·
A
revised alignment that impacts the west limit of the Highcock
property but avoids impact to the barn structures.
·
Impacts
the landscape strip at the north-east edge of the planned townhouse development
but should be accommodated without any loss of townhouse lots.
·
Required
relocation of the planned gas bar.
·
Results
in a 1.2 ha remnant block east of the Markham Bypass Extension.
The refined
alignment has been developed in consideration of the comments received by both
affected landowners and Box Grove Hill Development have
endorsed such alignment subject to conditions previously mentioned.
The agreement by
Box Grove Hill Developments is subject to the proposed auto service centre
being relocated to the east of the bypass (utilizing the remnant parcel) and
site access being provided to the bypass.
Regional Staff have agreed, in principle, to access being provided to
the bypass and will work with the Town of Markham and the developer through the
usual re-zoning and Official Plan amendment approval process.
The Town’s
Recommended Alignment at
The proposed
alignment for the Markham Bypass and
The proposed
at-grade intersection includes a minor realignment of the Markham Bypass westerly
to provide for a required 30m setback to the
Currently there
are approximately two trains per day on this CP Rail line which would not
warrant grade separation with
The EA for the
Markham Bypass Extension has developed the future grade separation in
sufficient detail to identify property limits to be protected within the Box
Grove Development.
Recommended Alignment at the South End of Box Grove
At the south end
of the Box Grove development area, a storm water management pond has recently
been constructed as part of the Phase I development. The alignment presented to Committee on April
18th would result in the need to reconfigure this pond to accommodate the
planned road.
In consultation
with the Box Grove landowners, the Region’s project team developed a refined
alignment in this area that minimizes the impact to the existing storm water
management pond.
Recommended Alignment from Box Grove to
At the south limit
of Box Grove, the proposed alignment swings west past the existing 9th
Line alignment and crosses the Rouge River, approximately 150m south of an
existing residential area (Ridgevale Drive and Rouge
River Circle). The noise assessment
undertaken as part of the EA has determined that noise mitigation is not
warranted in accordance with the MTO/MOE Noise Protocol and the Region’s current
Noise Policy. The Region is in the
process of reviewing the current Noise Policy.
At the time of detailed design, the noise impact associated with this
project will be reviewed against the latest Noise Policy and mitigation will be
included in the design if warranted.
Further consultation with residents is required.
Recommended Alignment Through
Villages of Fairtree East Draft Plan
Immediately north
of
ISSUES
Implementation Through the
Box Grove Secondary Plan
Through the Box
Grove Community Memorandum of Understanding (MOU), the Box Grove Landowners
will be constructing the 9th Line Bypass as a four-lane urban cross
section from the existing 9th Line just south of the Highway 407
interchange to fully bypass the Hamlet of Box Grove and reconnect to the
existing 9th Line south of the Hamlet and just north of the CN Line
/ CP Line crossings.
A section of this
9th Line Bypass has been identified in the EA as part of the Markham
Bypass Extension to
The MOU also
commits the Box Grove Landowners to the construction of the road link between
the Markham Bypass / Highway 407 interchange and the 9th Line Bypass
as a two-lane Town of
Rather than build
this road as a two-lane rural cross section as envisioned in the MOU, the
Region and the Town of Markham will investigate the opportunity to have it
constructed as a four-lane urban road as part of the Phase 2 Box Grove
Development (subject to final approval of the EA for the Markham Bypass to
Morningside Avenue link). Construction
of this road would provide a good quality continuous arterial connection from
the Markham Bypass north of Highway 407 to the south limit of the Box Grove
Secondary Plan where it would connect to the existing 9th Line, avoid future
traffic distribution and reduce throw away costs.
Impact to Parkview Golf Club
The proposed
alignment west of 9th Line crosses an existing hydro corridor north
of the CN Rail line before crossing under the rail. In this area, the proposed alignment impacts
the existing
The Owners of
Parkview have identified significant concerns with the proposed road alignment
through the golf course and the resulting impact on their business. The Region’s project team retained a golf
course architect to develop concepts for reconfiguration of the course to
accommodate the proposed road alignment and try to mitigate adverse
effects. Although the concepts are
feasible, there would still be a net effect on the overall course yardage and
significant disruption during construction.
Parkview continues to oppose any alignment through the course noting
concerns with significant effects to their business during the construction
phase with potential to impact the long term viability of the golf course.
The project team
recognizes the potential impact to the Parkview Golf Course as the most
significant adverse socio-economic effect of the Recommended Alignment. It is for this reason that staff recommend
that Council endorse the proposed EA subject to finalization of an
implementation plan including any phasing requirements.
Implementation of
this segment of the overall alignment should be coordinated with the section
south of
The section of the
proposed road through the Parkview Golf Course includes a crossing of the
The preferred alignment crosses the
Financial Implications
There are no financial implications to the Town as a result of the Markham By-Pass South of Hwy 407 to Morningside Avenue Environmental Assessment or the preferred design. The Town of Markham, as per the June 2002 Memorandum of Understanding have included an allowance in the Town wide Development Charges By-Law and draft 2006 Capital Budget to expropriate if necessary property required for the Box Grove Developer Group to construct the two lane rural road from Hwy 407 to the Ninth Line By-Pass.
ATTACHMENTS:
Attachment A, Region of
|
|
|
Alan Brown, C.E.T. Director of Engineering |
|
Jim Baird, M.C.I.P., R.P.P. Commissioner of Development Services |
Q:\Development\Engineering\REPORTS\2005\Oct\Markham
By-Pass South Alignment Endorsement Report.doc