|
|
|
|
|
|
|
|
|
|
TO: |
Mayor and Members of Council |
|
|
|
|
FROM: |
Peter Loukes, Director of
Operations and Asset management |
|
|
|
|
PREPARED BY: |
Stan Lau, Senior Project Manager |
|
|
|
|
DATE OF MEETING: |
|
|
|
|
|
SUBJECT: |
|
|
|
|
RECOMMENDATION:
THAT the report entitled “Settlers Park
Landfill Site Management – Status Update” be received;
AND THAT staff report back when the result of
application to the Canada-Ontario Municipal Rural Infrastructure Fund is known.
PURPOSE:
The purpose of this report is to provide
Council with an update on the Settlers Park Landfill Site Management program.
BACKGROUND:
·
To
carry out a leachate plume assessment in the vicinity of the Settlers Park
Landfill site.
·
To
carry out a detail design for an Aerobic Landfill Management Plan.
Staff was also
requested to report back in 2005 on the consultant’s finding and
recommendations.
The consultant has
completed the study and detail design and the results are outlined below:
·
Groundwater Discharge To German Mills Creek
Inspection of the west bank of German Mills
Creek revealed evidence of groundwater seepage along much of the creek between
the north and south limits of
The temperature profiling study indicates that
the relative small mass of groundwater discharge, compared to flow in the
stream, is too small to have a measurable thermal effect on the stream.
·
Groundwater Quality
The June 2005 water samples from the
stream bank well contained the same type of leachate parameters as previous
2003 and 2004 samples. Although some parameters such as calcium, iron, potassium,
sodium, etc. show increasing concentrations each year, other indicators such
chloride and hardness, show fluctuating concentrations.
Water from the two new piezometers
which sample the groundwater discharge into German Mills Creek contained
elevated leachate parameters, although the concentrations were generally lower
than at the stream bank well.
·
Impact on German Mills Creek
The water quality in German Mills Creek
has been monitored annually since 2002. Water samples were collected upstream
and downstream of the landfill. All samples were collected during the August to
September low flow period when flow was measured in the range of 200 to 300 l/s.
The main leachate indicators which show
minor increases in concentration between the upstream and downstream stations
include chloride, calcium, manganese, zinc and ammonia. The increases in
concentration are generally only a few percent and they vary from year to year.
Comparison of the upstream and
downstream water samples indicates that the landfill leachate plume does not
cause a significant impact to German Mills Creek. This is largely due to the
fact that the low flow in the stream is several hundred times greater than the
groundwater flux beneath the landfill.
Aerobic Landfill Management Plan:
·
Aerobic Landfill Pilot Test
A pilot aerobic air injection test was
carried out in July and August of 2004. Indicators of aerobic landfill
conditions such as decrease in methane gas generation, increase in oxygen
levels in the landfill, and the production of thermal energy (heat) were
monitored in a network of gas probes.
The result of the pilot test indicated
that the landfill temperature increase from 16 degree C to 26 degree C during
the test period and gradual reduce to 21 degree C after about 6 months. Methane
in the landfill around the test well decrease from 34% (by volume) to less than
5% and remain low for 11 days after completion of the air injection test.
The overall results of the pilot test
demonstrated that it is feasible to reduce methane to non hazardous levels by
utilizing Aerobic Landfill Technology.
·
Aerobic Landfill Design
Implementation of the aerobic landfill
technology requires the installation of a network of air injection wells.
Atmosphere air is injected into the waste via the nests of wells by means of
positive displacement air blowers. The air is distributed to the injection well
by means of flexible surface piping.
Temperature and gas monitoring probes are
required throughout the landfill to monitor the system performance. Automated
monitoring using remote temperature loggers are required to ensure optimum
conditions are maintained for aerobic decomposition.
·
Leachate Recirculation System
In order to optimize the aerobic process, it is
necessary to add moisture to the waste material. This is commonly done by
installing an irrigation system on the landfill surface.
In this case, it is proposed to install a row
of shallow well points along the west bank of German Mills Creek to intercept
the leachate plume and then re-circulate onto the landfill by means of a drip
irrigation system or shallow infiltration trenches.
This system will effectively eliminate the
discharge of leachate into the German Mills Creek. As well, it will provide additional
moisture to aid the aerobic process.
·
Implementation Cost
The cost for implementation of the aerobic landfill
and leachate recirculation system is estimated at $700,000.
DISCUSSION:
Implementation of Program:
Implementation
of the aerobic landfill and leachate recirculation system will achieve the
following objectives:
·
Major
reduction of greenhouse gas emission in
·
Elimination
of the risk of underground methane gas migration to the adjacent residences and
the risk of fire and explosion.
·
Elimination
of leachate discharges to the German Mills Creek and contaminate the surface
water.
·
Reduce
the waste decomposition and stabilization period from over 100 years to less
than 20 years.
Potential Partnerships and Funding:
Canada-Ontario
Municipal Rural Infrastructure Fund (COMRIF) – Intake Two:
Council
on
If the
application to COMRIF is successful, the total project cost will be equally
shared by the Federal Government, the Ontario Government and the Town of
FCM
Green Municipal Enabling Fund (GMEF): This project may qualify for funding
contribution from GMEF. Staff will pursue funding opportunities in this regard.
Ministry
of the Environment (MOE): According to our consultant, the MOE has contacted them and has indicated
wishes to monitor our program as they have other candidate site where this
technique may apply.
ATTACHMENTS:
Attachment
“A’ – Groundwater Flow
Attachment
“B” – Air Injection and Leachate Infiltration System
Attachment
“C” – Leachate Recirculation System
Attachment
“D” – Aerobic Landfill and Leachate Recirculation System
|
|
|
Peter Loukes, P. Eng. Director, Operations and Asset Management |
|
Jim Sales Commissioner, Community and Fire Services |
Q:\Commission
Share\Operations and Asset Management\Reports\2005\C & U\ROW\Other
Report\Settlers Park Landfill Site Management Status Update.doc