General Committee (Finance and Administrative) |
|
|
|
|
|
|
|
|
TO: |
Mayor and Members of Council |
|
|
|
|
FROM: |
Jim Baird, Commissioner, Development Services Valerie Shuttleworth, Director,
Planning and Urban Design |
|
|
|
|
PREPARED BY: |
Linda Irvine, Manager, Parks and Open Space Development Bill Inglis, Senior Construction Buyer |
|
|
|
|
DATE OF MEETING: |
|
|
|
|
|
SUBJECT: |
Tender Award # 176-T-05 Construction of |
|
|
|
RECOMMENDATION:
THAT the report entitled “Tender Award # 176-T-05
Construction of Swan Lake Park” dated
AND THAT the contract for Tender #176-T-05 Construction of
Swan Lake Park be awarded to the lowest priced
bidder, Rutherford Contracting Ltd. in the amount of $521,896.46, excluding GST;
AND THAT $40,000.00 be approved and set aside in the budget for design and construction contingency purposes for the Swan Lake Park and that the Manager of Parks and Open Space Development and the Treasurer be authorized to approve any required contingency items up to the construction contingency amount;
AND THAT $13,212.00 be charged to Swan Lake Park Phase 5 (account #81-5350-6258-005) for internal contract fees;
AND THAT Council approve the total cost for this project, as follows:
Base
Bid to
Provisional items – Credit ($ 20,159.20)
Sub-total: $ 521,896.46
Construction Contingency $ 40,000.00
Internal Contract Fees $ 13,212.00
Total $ 575,108.46
General
Committee – Finance and Administrative
Tender
Award # 176-T-05 Construction of
______________________________________________________________________
AND THAT funding for this project be provided from Swan Lake Park Phase 5 (account # 81-5350-6258-005) in the amount of $575,108.46;
AND FURTHER THAT upon payment of all invoices for this project, any remaining funds in account #81-5350-6258-005 shall remain in that account to be used for future park works on Block 31 in Swan Lake Park.
PURPOSE:
To award contract for Tender # 176-T-05
Construction of Swan
Lake Park (Phase 5).
BACKGROUND:
This award is to
construct a water play facility, junior and senior playground and gazebo area
at the corner of
Advertised, place and date |
Electronic Tendering Network , |
Bids closed on |
|
Number picking up bid documents |
9 |
Number responding to bid |
2 |
DETAILED PRICING INFORMATION as submitted:
|
Contractors |
Base Price (excl. GST), including allowances* |
Provisional Price Credit (excl. GST) |
Total (excl. GST) |
1. |
$542,055.66 |
($ 20,159.20) |
$ 521,896.46 |
|
2. Melfer |
$612,916.00 |
($ 3,270.00) |
$ 609,646.00 |
* Pricing includes testing allowance($5,000), water meter allowance($10,000) and power
service allowance($6,000)
General
Committee – Finance and Administrative
Tender
Award # 176-T-05 Construction of
______________________________________________________________________
FINANCIAL
CONSIDERATIONS:
In an attempt to identify certain cost savings, Provisional
Item 2.0, Standard Concrete has been substituted for Part A, Item 1.10, Coloured Concrete which realizes a total savings of
$20,159.20.
Summary of cost for this project;
Base
Bid to
Provisional items – Credit ( $ 20,159.20 )
Sub-total: $ 521,896.46
Construction Contingency $ 40,000.00
Internal Contract Fees $ 13,212.00
Total $ 575,108.46
Staff recommend that funding for this project including the base bid, provisional items, construction contingency and internal contract fees be provided from Swan Lake Park Phase 5 (account # 81-5350-6258-005) in the amount of $575,108.46.
Funding
for this project is available in Capital Budget Account # 81-5350-6258-005.
Currently the balance of approved funding in this account is $616,752.00 as of
BUSINESS UNITS CONSULTED AND AFFECTED:
The
Finance and
APPROVED BY:
Valerie
Shuttleworth,
M.C.I.P., R.P.P. Director,
Planning and Urban Design |
Jim
Baird, M.C.I.P., R.P.P. Commissioner
of Development Services |
|
|
Q:\Development\Design\linda\Parks\Swan Lake Award
Report Final Ver. 2.doc