|
|
|
|
|
|
|
|
|
|
TO: |
Mayor and Members of Council |
|
|
|
|
FROM: |
Steve Andrews, P. Eng., Director of Asset
Management |
|
|
|
|
PREPARED
BY: |
Eardley Adams, Project Manager Steven Sydij,
Senior Construction Buyer |
|
|
|
|
DATE
OF MEETING: |
|
|
|
|
|
SUBJECT: |
Award of Tender # 188-T-05 for the
construction of the Markham Village Library Expansion and Renovation |
|
|
|
RECOMMENDATION:
THAT the report entitled “Award of Tender #188-T-05
for the construction of the Markham Village Library Expansion and Renovation”
be received;
AND THAT the Tender # 188-T-05 for the
construction of the Markham Village Library Expansion and Renovation be awarded to the lowest priced qualified bidder TORCOM Construction Inc., in the total amount of $7,625,000
exclusive of GST;
AND THAT a contingency of $426,000 exclusive of
GST be established and that the Director of Asset
Management or designate, be authorized to approve change orders up to the
contingency amount with the provision that a monthly statement of these
expenditures is forwarded to the Town Treasurer;
AND THAT the Markham Village Library Expansion
and Renovation project budget in the total amount of $10,850,120 outlined on
page 4 be approved;
AND THAT funding be
provided from the following sources:
AND THAT the 2006 Capital Budget
project #7067, Markham Village Library Landscaping, in the amount of $100,000,
and 2006 Capital Budget project #7118, Markham Village Library Expansion &
Renovation Additional Funding in the amount of $2,364,500 be pre-approved;
AND THAT the award for Markham
Village Library Expansion and Renovation project furniture, fixtures and equipment
in the amount of $741,405 be made in accordance with
the
AND THAT the award for Markham
Village Library Expansion and Renovation project collections, in the amount of
$1,144,600 be made in accordance with the
AND THAT the Mayor and Town Clerk be authorized to enter into an agreement with TORCOM Construction Inc. in a form satisfactory to the Town
Solicitor.
PURPOSE:
The purpose of the report is to
obtain Council approval to award Tender #188-T-05 for the construction of the
Markham Village Library Expansion and Renovation project and to obtain approval
for the funding of the project.
BACKGROUND:
On
The Building and Parks Construction Committee (BPCC) reviewed the site layout, building components,
architectural designs, mechanical components, environmental and energy
conservation upgrades, building finishes, exterior design elements, and urban
design requirements to ensure the project meets the library’s needs, satisfies local
neighbourhood concerns and is of a high quality and sustainable design.
Copies of the site plan and building elevations
are included as Appendix ‘1’ of the report.
Based on the results of these reviews, the BPCC endorsed the design of the Markham Village Library
Expansion and Renovation project. The
design has been completed and the Development Services Committee approved the
site plan on
On
DISCUSSION
Tender
Result
The tender was issued to 8 pre-qualified
companies in accordance with the
Advertised |
Invited bids
from 8 pre-qualified companies |
Bids Closed on |
|
Number picking
up bid documents |
8 |
Number
responding to bid |
6 |
Contractor |
Total Contract
Cost (excluding GST) |
||
Base price |
Other item (Landscaping) |
Total |
|
TORCOM Construction
Inc. |
$7,550,000.00 |
$75,000.00 |
$7,625,000.00 |
Aquicon Construction
Co. Limited |
$7,579,000.00 |
$49,800.00 |
$7,628,800.00 |
The Atlas Corporation |
$7,650,000.00 |
$67,800.00 |
$7,717,800.00 |
Jasper Construction Corporation |
$7,650,000.00 |
$80,000.00 |
$7,730,000.00 |
Bondfield Construction
Company Ltd. |
$7,750,000.00 |
$49,000.00 |
$7,799,000.00 |
Pre-Eng Contracting Limited |
$7,868,000.00 |
$65,000.00 |
$7,933,000.00 |
The lowest qualified bid represents an over
expenditure of $348,065 or 4.78 % over the pre-tender cost estimate presented
to Council in September, 2005. The sources of funding for this shortfall is set out under the
Financial Considerations section of this report.
Based on the evaluation results, staff recommends the Tender #188-T-05 for the construction
of the Markham Village Library Expansion and Renovations project be awarded to
the lowest priced qualified bidder, TORCOM
Construction Inc. (Torcom), in the total amount of
$7,625,000 exclusive of GST.
The Town Architect for this project, Shoalts and Zaback Architects
Ltd., conducted a thorough review of each of the pre-qualified bidders and as part
of this process, checked references from building owners and consultants and conclude
that TORCOM have the necessary experience, qualifications
and good track record to complete the construction of the library and
renovations project.
The difference between the lowest bidder and
the second lowest bidder (on the base price) is only $29,000 or 0.38%. The spread between the lowest and the highest
bidder is only $318,000 or 4.2 %. The
Architect has conducted a thorough review of the tendering prices and concluded
that there are no anomalies in the pricing and that the bid price reflects the
current market conditions.
A contingency allowance of $426,000 exclusive
of GST represents 5.58% of the Base price plus
landscaping cost and will be approved under a separate purchase order. The contingency will be used to cover
unanticipated changes to the project.
The use of the contingency funds will be controlled through the use of
Change Orders issued by the Architect and authorized by Town staff. It is recommended that the Director of Asset
Management or designate be authorized to approve the construction change orders
up to this amount with the provision that a monthly statement of these expenditures
be forwarded to the Town Treasurer.
Upon Council approval of the tender on
FINANCIAL CONSIDERATIONS:
Project Cost Breakdown
The
Markham Village Library Expansion and Renovation project pre-construction
tender cost estimates and the final budget (based on construction tender
pricing) are shown below:
The tender for the construction and renovation
of the Markham Village Library totals is $7,625,000 excluding GST. Included in
this amount is a $75,000 additional component for landscaping that was itemized
separately within the tender document. Staff have included this landscaping component to augment
the basic level of landscape treatment built into the base tender which only consists
of sodding and concrete sidewalks. The proposed 2006 Capital Budget includes project
#7067, Markham Village Library Landscaping which is
established at $100,000. Staff are recommending pre-budget approval of this project
to offset the cost of this additional item.
The award for future components of the Markham
Village Library Expansion and Renovation project, such as furniture, fixtures
and equipment for $741,405 be made in accordance with
the
The award for future components of the Markham
Village Library Expansion and Renovation project, such as collections for
$1,144,600 be made in accordance with the
Proposed
Project Funding
Proposed funding for the $10,850,120 Markham
Village Library project is recommended as follows:
Additional
Funding Sources and Pre-Budget Approval
As presented to Council on
As outlined in the table on page 4,
the tender amount is higher than the pre-construction tender cost estimates by
$348,065 of which $100,000 relates to enhanced landscaping and the balance is
due to actual construction bids being higher than the pre-construction tender
cost estimate.
A 2006 capital request is also
being brought forward for the enhanced landscaping. Capital project #7067 – Markham Village
Library Landscaping, as shown in the table above, in the amount of $100,000 is
included in additional funding.
Since funds must be approved by
Council prior to the award of a tender, it is recommended that the 2006 Capital
project #7067 – Markham Village Library Landscaping, in the amount of $100,000
and project #7118 – Markham Village Library Additional Funding, in the amount
of $2,364,500 be pre-approved.
It is recommended that the
remaining shortfall in the amount of $248,065 ($348,065 - $100,000 from the
2006 Landscaping project) be funded from the following sources:
·
$107,000 from
surplus funds remaining in the Library IT account for the 2002 Angus Glen Community
Centre capital project;
·
$126,959 from Development
Charges Reserves; and
·
$14,106 from the
10% Non-DC Reserve.
Funding for the total $10,850,120 project
spans several years and is from several different sources. As shown in the following table, 42.9% (or $4,650,843)
of the project is funded from Development Charges and the remaining 57.1% (or
$6.2M) is from Non-Development Charge sources:
BUSINESS UNITS CONSULTED AND AFFECTED:
The
Markham Public Libraries and the
ATTACHMENTS:
Appendix
1 - Project
Site Plan and Elevations
Steve Andrews, P. Eng., Director of Asset Management |
|
Catherine Biss, CEO, |
Jim Sales, Commissioner of Community and Fire Services |
|
Q:\Commission
Share\Operations and Asset Management\Reports\2005\C & U\Facilities\Award
Report #188-T-05.doc