GENERAL COMMITTEE

 

 

 

 

 

TO:

Mayor and Members of Council

 

 

 

 

FROM:

Alan Brown, Director of Engineering

 

 

 

 

PREPARED BY:

Lloyd Fernandes, Senior Capital Works Engineer

Allan Arbuckle, Manager of Infrastructure & Capital Works

 

 

 

 

DATE OF MEETING:

January 23, 2006

 

 

 

 

SUBJECT:

GO Transit Hagerman Grade Separation Project Update

 

 

 

 

RECOMMENDATION:

THAT the report entitled “GO Transit Hagerman Grade Separation Project Update” dated January 23, 2006 be received;

 

AND THAT staff be authorized to continue negotiating with GO Transit to reach an agreement with respect to the relocation of Town services including cost sharing, project scheduling, conveyance of easements and other items relating to the implementation of the project;

 

AND THAT the preferred design concepts for the relocation of Town services as presented by engineering staff at the January 23rd 2006 Committee meeting be received;

 

AND THAT staff be authorized to finalize the preferred design concepts with GO Transit for inclusion into the design-build contract;

 

AND THAT staff report back to General Committee in the spring of 2006 with an update on the services to be relocated, total project costs, cost sharing, agreements, financing, any additional 2006 Capital Budget requirements, conveyance of easements and schedule in respect to the relocation of Town services.

 

PURPOSE:

The purpose of this report is to update Council on the current status of the Hagerman Grade Separation project being undertaken by GO Transit and to advise of the recommended option and potential costs to relocate existing Town services which will be impacted by the proposed grade separation project.

 

 

 

 

 

 

BACKGROUND

The GO Transit Stouffville Corridor rail line runs in a north-south direction and provides service to Markham at the Milliken, Unionville, Markham and Mount Joy stations. In the area west of Kennedy Road between 14th Avenue and Highway 407, the north-south GO rail line crosses the east-west CN tracks at a level crossing known as the Hagerman Diamond. The location of this crossing is shown on Attachment “A”.

 

In 1991, GO Transit completed a planning study of the Stouffville Corridor from Scarborough to Uxbridge to investigate the feasibility of providing full GO service along this corridor. This study, together with a further planning study entitled Stouffville Corridor Planning Study” prepared in 2002 identified the Hagerman Diamond level crossing as a major constraint to operations along this corridor. The study further recommended that a rail/rail grade separation be constructed at the Hagerman Diamond to separate the GO tracks from the CN tracks and remove the operational constraint. The project will involve the lowering of the existing GO tracks to pass under the CN tracks as shown on Attachment “B”. This lowering of the tracks will extend from Denison Street in the south to approximately the Unionville GO station and will involve the construction of a new rail underpass structure at 14th Avenue. 

 

Municipalities and other operators of utility systems are required to enter into agreements with railway companies to permit the construction of services which cross rail lines. These agreements contain standard clauses which require the owner of the utility to remove or relocate the services at the owner’s sole expense if requested by the railway. The Town has a number of municipal services which cross the GO tracks in the area of the Hagerman Diamond including a 400 mm diameter watermain, a 250 mm diameter sanitary sewer and a 900mm dia, storm sewer on 14th Avenue, a 900mm dia. storm sewer located north of Denison Street and a 1950mm dia. storm sewer located north of Duffield Drive. The Town of Markham has entered into three Pipe Crossing Agreements with Canadian National Railways to permit the installation of these services, one in 1980, one in 1985 and one in 1994. Each of these Agreements contains the standard relocation clause which states “Should it become necessary or expedient for the purpose of repair or improvement on the said Railway that the Works be temporarily removed or relocated, the Applicant shall, upon request of the Railway and at the sole cost and expense of the Applicant, forthwith remove or relocate the Works”. GO Transit, who purchased the Stouffville line from CN, has indicated that these services must be relocated to accommodate the proposed track lowering.

 

The locations of the Town’s services which will be affected by the proposed rail line lowering are shown on Attachment “C”.

 

DISCUSSION

In the summer of 2002, GO Transit commenced the preparation of an Environmental Assessment for the Hagerman Diamond Rail/Rail grade separation project. Since 2002, Engineering staff have been involved in discussions with GO Transit and their consultants and have clearly and consistently advised GO of the significant impact to the Town’s municipal infrastructure of the proposed grade separation project and the need for a thorough review of alternatives. In particular, staff requested that the development and evaluation of a full range of relocation alternatives be carried out to ensure that the selected relocation options will provide the most cost effective solution from a initial capital cost, maintenance and operations perspective.

 

In the spring of 2005, GO elected to proceed with the Hagerman grade separation project as a design/build undertaking and in the late fall of last year began soliciting proposals from design/build teams. Since the start of November, Engineering staff have met with representatives of GO and their project managers, AGM Program Managers, on a number of occasions. Despite

numerous assurances from GO in the past that servicing relocation alternatives would be identified and evaluated by GO and solutions acceptable to the Town would be included in the design/build package, this review and evaluation of alternatives has not been carried out and the design/build package does not identify acceptable relocation solutions for all of the Town’s services.  This creates the situation where the Town may be forced to accept relocation solutions which are not in the Town’s best interests or staff may be forced to negotiate prices for acceptable solutions with the design/build team after the contract has been awarded by GO. Our experience indicates that it is unlikely that favourable prices can be negotiated under these conditions.

 

Given GO Transit’s refusal to undertake a detailed assessment of servicing relocation alternatives, engineering staff has been forced to proceed with this assessment independently. Staff had requested that GO delay the submission of design/build proposals until such time as a detailed assessment can be completed by the Town in approximately 3 to 4 months. GO rejected this request but on December 7th 2005 agreed to consider extending the closing date of the design-build proposal call from December 22, 2005 to the end of January 2006.  Although this timeframe does not permit a full assessment of alternatives, engineering staff agreed to dedicate the time and resources to establish preferred design concepts for the relocation of all services impacted by the project. Subsequent to the December 7th meeting, GO advised that they were unable to extend

 the closing date to the end of January but had extended the closing date to January 12th 2006.

 

GO Transit is proceeding with the design-build process without the Town having identified preferred relocation options, and the design-build proposal will close before these preferred relocation options have been identified.  Notwithstanding GO’s action’s, Engineering staff are continuing to work on identifying the preferred relocation options and preparing conceptual designs for each preferred alternative. This information will be submitted to GO by January 31st  2006 in accordance with our original commitment. Staff has also committed to continue working with GO Transit and their representatives to resolve outstanding issues regarding this project including potential cost sharing of the servicing relocation works, GO request to obtain easements over a portion of the Town’s Milliken Mills park and the need for GO to utilize Town sewers and/or stormwater management facilities as outlets for their track drainage systems.   

 

Consultant Services

Since early December, Engineering staff have been developing and evaluating solutions for the relocation of all of the Town services which cross the rail line or which will otherwise be affected by the proposed track lowering. This work involves:

-       Assembly and retention of a consultant project team

-       Field surveys and inventories of existing systems

-       Development of relocation alternatives for all services (storm sewers, sanitary sewers and watermains)

-       Assessment of the impact of each alternative based on capital cost, maintenance costs, future risk of additional costs to the Town and liability as it relates to operations during major storm events.

-       Review options with the Town’s Operations and Asset Management Departments

-       Provide recommendations to GO Transit for inclusion in the design build process by January 31st, 2006.

 

Due to the short time frame available to complete the work, the consulting firm of McCormick Rankin Corporation has been retained under the emergency purchase provisions of the Purchasing By-law to assist staff in completing this work. It is estimated that the total cost of the

McCormick Rankin work will not exceed $70,000 excluding GST ($74,000 including GST).

 

Project Schedule

GO has advised that the current schedule for the project calls for the award of

the design-build’ contract by February 2006 and to have the design completed within 4 months. Construction of the project is scheduled to commence in the summer of 2006 and to be completed by the end of 2007.

 

GO Transit Meeting

GO Transit has demonstrated a lack of timely regard for Town issues as a part of the Hagerman Grade Separation project and a January 17, 2006 meeting has been arranged between senior staff of GO and the Town to discuss this matter and other issues of mutual concern including the terms and conditions of other existing rail crossing agreements, ongoing issues with the Anti-Whistling initiative in Markham and the Castlemore Rail Crossing Agreement in north east Markham.  Staff will provide a verbal update of the results of the meeting.

 

FINANCIAL CONSIDERATIONS:

As noted in preceding sections of this report, the existing Rail Crossing Agreements require the Town to be responsible for all costs associated with the relocation of all Town services. The approved 2005 Capital Budget includes $25,000 for the preliminary review of relocation alternatives and the draft 2006 Capital Budget includes funding in the amount of $275,000 to complete the review and evaluation of alternatives and the preparation of conceptual designs. The draft 5 year Capital Project Plan includes additional funding in the amounts of $500,000 in both 2007 and 2008 for construction of the servicing relocations. This estimated construction value was based on the preliminary work completed in 2002 which indicated that a 400 mm watermain and the 1950mm dia storm sewer would require relocation. As a part of the current design-build proposal, GO has prepared more detailed design information regarding the proposed track lowering and engineering staff have carried out a detailed inventory of existing services in the area. This work has identified that in addition to the large diameter storm sewer and watermain previously identified, a sanitary sewer and two additional storm sewers will also require relocation. Based on information which has been developed to date as a part of the Town’s detailed assessment of servicing relocation alternatives, the total cost of carrying out all of the required relocations is more likely in the $3 to $6.0 million range, all of which would require tax/water rate funding unless cost sharing arrangements can be negotiated with GO transit.  Detailed estimates will be produced as a part of the alternative evaluation process and will be a component in the selection of a preferred option.

 

The total cost to the Town of the servicing relocations will be determined once the preferred relocation option has been identified, the detailed design of this option completed, detailed costing has been received from the design-build team  and negotiations with GO Transit regarding potential cost sharing have been concluded. Given the construction of the project is not scheduled to commence until the summer of 2006, it is unlikely that the value of any Town works carried out in 2006 will exceed the value of the funding included in the 2005 and 2006 Capital Budgets. Staff will report back to Council in the spring of 2006 with details of the final Town costs and the need to include additional funding in the 2007 Capital budget. GO has indicated that they would consider providing front-end financing for all or a portion of the Town costs if requested.

 

BUSINESS UNITS CONSULTED AND AFFECTED:

The Finance Department has reviewed this report and their comments have been incorporated.

 

ATTACHMENTS

Attachment “A” – Location Plan

Attachment “B” – Track Lowering Details

Attachment “C” – Existing Services

 

 

 

 

 

 

 

 

Alan Brown, C.E.T.

Director of Engineering

 

Jim Baird, M.C.I.P., R.P.P.

Commissioner of Development Services

 

Q:\Development\Engineering\REPORTS\2006\Jan\Hagerman