REPORT TO GENERAL COMMITTEE    

 

 

 

 

 

TO:

Mayor and Members of Council

 

 

FROM:

Jim Baird, Commissioner of Development Services

 

Alan Brown, Director of Engineering

 

PREPARED BY:

Alan Brown, Director of Engineering

 

 

 

DATE OF MEETING:

January 23, 2006

 

 

 

SUBJECT:

Engineering Department

Capital Project Process

 

 

 

RECOMMENDATION:

That the January 23, 2006 report entitled “Engineering Department, Capital Project Process”, be received;

 

And that the process improvements as listed in the report be endorsed;

 

And that engineering staff update Council on at least a quarterly basis on the status of major capital projects as listed in the report;

 

And that the merit of a quarterly update to Council on Park projects and Community Services Commission capital projects be considered by the Building/Parks Construction Committee.

 

PURPOSE:

To recommend improvements in reporting of major Engineering capital projects to Council.

 

EXECUTIVE SUMMARY:

Council, as a result of issues arising from the Enterprise Drive/GO and Rodick Road/Hwy 407 grade separations projects, requested staff to review engineering capital project processes and recommend improvements to such and communications with Council.

 

In addition, during the 2006 Budget Review Process questions arose to the assessment and disposition of contingencies for capital projects in general.

 

Staff have prepared a number of recommendations that will address Council’s concerns including:

§    Not tendering projects unless all property, approvals and agreements are in place

§    At least quarterly update to Council on major projects

§    Council’s assistance in obtaining agencies approvals in a timely fashion

§    Reporting of contingency expenditures.

 

BACKGROUND:

At the September 19, 2005 and June 28, 2005 Committee/Council meetings, staff submitted reports with respect to Enterprise Drive/GO and Rodick Road/Hwy 407 grade separations. 

 

Council requested staff report back on how delay claims can be avoided in the future, more regular updates to Council, financial practices/processes and an update to the Development Charges by-laws to reflect increased capital costs.

 

While this report responds to most of the issues raised by Council, a separate report on the update of the Development Charges By-law will be presented to General Committee in February 2006.  In addition upon completion of Enterprise Blvd/GO Transit and Rodick Road/Hwy 407 grade separation projects, a final report outlining the final project costs will be submitted to Committee.

 

Council Updates

 

In the past, reports were brought forward to Council only at key decision making points (i.e. award of tender, property acquisition, Environmental Assessments, project cost overrun over $100,000, etc.).

 

Council has requested, in future, more frequent updates on critical projects and issues which may delay the project or increase its budget.  Staff recommend at least quarterly updates on critical projects on the following issues:

·        EA status

·        Project management process

·        Design status

·        Property acquisition status

·        Agency approval status

·        Construction schedule

·        Budget Status

·        Utilization of Contingencies

·        Key Issues

 

The Capital projects (both carryover and 2006) to be managed by the Engineering Department, total over 80 and are listed in Attachment ‘A’.  Staff recommend that the following projects which have either large financial budgets or have significant impact be brought forward as updates to Council on at least a quarterly basis:

 

Roads

·        Rodick Road/Hwy 407 grade separation

·        Birchmount Road extension (14th Avenue to Enterprise Blvd)

·        Hwy 404 grade separation at Centurian Blvd

·        Woodbine By-pass around Victoria Square

 

Environmental

·        Pomona Mills Creek Environmental Study

 

Servicing

·        Hagermans Corner rail/rail separation – servicing relocation

·        Hwy 7 Sanitary Sewer and Sheridan Stormwater Management Facility

 

Transportation

·        Bike Path System

·        Travel Demand Management

 

Staff will monitor the overall project status list, and will bring updates to Council on other projects as required or as Council requests.

 

With the above updates Council will be better apprised of the ongoing step by step progress of those capital projects identified by Council as being of key strategic or financial priority.

 

Parks/Building

Currently both Parks and Building projects are vetted through the Parks/Building Sub-committee.  Senior staff will be reviewing with the Committee if further updates on these projects on a quarterly basis are required.

 

Tendering Process

Stemming from the significant delay claims on the Enterprise Drive/GO and Rodick Road/Hwy 407 grade separation projects (primarily as a result of delay in acquiring external agencies agreements, permits, property and in the case of the Enterprise project, capital works to be undertaken by GO Transit), Council on September 13, 2005 instructed engineering staff to delay the tendering of future construction contracts for all engineering capital works until all necessary approvals/agreements from external agencies are received to the satisfaction of the Director of Engineering or unless Council instructs otherwise.

 

The Engineering Department has accordingly adjusted its 10 year Capital Program to reflect the approval process time frames currently encountered.  The Engineering Department 10 Year Capital Program Update for roads, sidewalk and illumination will be submitted along with the Finance Department Cash Flow analysis on February 20, 2006.  If Council wishes to advance certain capital projects without having all the necessary permits/property, staff would recommend a substantial contingency be included in the budget for potential delay claims.

 

Contingencies/Expenditure Control

At the December 5 and 6th 2005 General Committee and Budget Committee, concerns were raised regarding the process for expenditures of contingencies for capital projects in general.

 

At the award of tender for all major capital projects (roads, sewers, watermain, building, parks, etc.) a contingency is included as part of the tender award. The contingency value varies from 2% to 7% depending on the value of the contract, complexity of the project and degree of unforeseen additional work which may be encountered during construction.

 

The expenditure of contingencies must be approved in accordance with the Expenditure Control Policy, which authorises the user Department Director or other senior staff to award expenditures only up to the preset limit.  If the contingencies are expected to be exceeded, then Council approval is required to increase the limit.  Staff as part of the quarterly update will include a summary of contingency expenditures.

 

As per the Expenditure Control Policy the level of authority for Capital expenditures that exceed the awarded project budget is as follows:

 

·        Director            -           $ 10,000 and less than 10% of contract value

·        Commissioner   -           $ 25,000 and less than 10% of contract value

·        Treasurer          -           $ 50,000 and less than 10% of contract value

·        CAO                -           $100,000 and less than 10% of contract value

·        Council -           greater than $100,000.

 

Project Management

To address the magnitude (over 80) and complexity of projects from a coordination, agency approval, property acquisition and management perspective, the following improvements in the engineering project management process have been implemented:

·        Addition of one senior contract position in 2005 to assist in management of projects

·        Bi-weekly meetings between Director, Manager and Engineers to review status, issues and next steps for each project

·        Addition of one senior property acquisition staff in the Legal Department in 2005 to acquire the necessary property/easements for the capital projects

·        Weekly meetings with Legal Department to review property acquisition status

·        Utilization of MS Project Management software.

 

BUSINESS UNITS

This report was reviewed at the February 11 and 18th 2006 CAO/Commissioners meetings and revisions have been incorporated.

 

ATTACHMENTS:

Attachment ‘A’ – Capital Project List – 2006 and Carryover

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Alan Brown, C.E.T.

Director of Engineering

 

Jim Baird, M.C.I.P., R.P.P.

Commissioner of Development Services

 

 

 

 

 

 

 

Q:\Development\Engineering\REPORTS\2006\Jan\Capital Project Process 012406.doc