Report to: General Committee                                                          Report Date: June 6, 2007

 

 

SUBJECT: O                      Options for a Revised Building Strategy for the Museum Ward Building Reconstruction Project

PREPARED BY:               Alan Wolfe, Project Consultant

                                           

 

RECOMMENDATION:

THAT the report entitled “Options for a Revised Building Strategy for the Museum Ward Building Reconstruction Project” be received;

 

AND THAT Council approve allocating $242,750 from the Life Cycle Replacement Reserve to make up the shortfall from the Federal Cultural Spaces Grant;

 

AND THAT Council select an option, in principle, for a Building Strategy for the Museum Ward Building Reconstruction project;

 

AND THAT this option be referred back to the Building and Parks Committee to develop a funding strategy;

 

AND FURTHER THAT a meeting be arranged with Caroline Di Cocco, Minister of Culture, to determine if a provincial contribution for this project is available.

 

EXECUTIVE SUMMARY:

This report is to present Council options for a revised building strategy for the Ward Building Reconstruction. 

 

The Ventin Group Ltd. Architects was hired to complete the schematic design for the project.  A design charette to determine the best location for the new Ward Building was convened.  The charette recommended locating the new Ward Building at the front of the Museum site on the north side of the Reception Centre.

 

The architect also conducted a business case analysis to determine if the existing Ward Building should be maintained.  The business case recommends renovating the Ward Building for non Class “A” storage and other programming uses.

 

The Technical Advisory Committee, Museum Board and Building and Parks Construction Committee endorse a revised building strategy including locating the new Ward Building at the front of the site on the north side of Reception Centre and the renovation of the existing Ward Building.  Unfortunately, the cost of this revised building strategy far exceeds the funds allocate for the construction of this project.

 

Six options for a revised building strategy for the Ward Building Reconstruction project have been developed.  The options are based on either locating the Ward Building on or near its existing location or placing at the front of the Museum site, either demolishing or retaining the existing building, and either maintaining the existing construction cost estimate or exceeding the cost estimate.  The options are analyzed based on cost, as well as program, and site development criteria.

In order for the design process to continue, it is requested that Council provide direction on the building strategy for the Ward Building Reconstruction project.  Once this direction is provided, the architect can continue with the schematic design process.    

 

FINANCIAL CONSIDERATIONS:

A total of $3,325,000 has been allocated to this project.  A copy of the current project cost estimate is included as Attachment “A”.

 

1)                  Federal Cultural Spaces Grant Shortfall

The Town has been awarded an $854,500 grant from the Federal Cultural Spaces Grant for this project.  Although this amount represents a significant accomplishment, it does not match the application amount of $1,097,250.  The shortfall is $1,097,250 - $854,500 = $242,750.  The original report recognized that it was highly unlikely that the Town would receive the full amount of the grant and indicated that any shortfall would have to be provided for in a future capital budget.  This item can be funded from the Life Cycle Reserve.

 

2)         Cost of Building Strategy Options

If Council selects a building strategy option that requires additional funding for the project, the additional funding should be considered as part of the 2008 Capital Budget discussions.  The additional funding requirement will have to be considered in competition with other important Town initiatives such as the tax funding components of the National Research Centre, Canadian Sports Institute, the Royal Conservatory of Music, and the South East Community Centre.  

 

3)         Costs for Parking Lot and Landscaping

This project does not include construction of additional parking and landscaping for the facility.  These amenities will be required to appropriately service the new building.  The site development Master Plan that is currently being undertaken is addressing these issues and will result in recommendation in the amount and extent of the parking lot and landscape requirements.  The funding for the parking lot and landscaping will be identified in the Master Plan.  The Parks Development Charges account will be considered for funding these amenities.

 

PURPOSE:

The purpose of this report is to have Council select an option for a Revised Building strategy for the Ward Building Reconstruction.

 

BACKGROUND:

On June 28, 2005, Council approved the Markham Museum Master Plan – Phase 1 Business Plan.  This report identified the need to reconstruct the Ward Building as a collections storage and exhibition centre.  The new centre will include exhibition space, visible storage, and an archives reading room to allow public access and viewing of the collection.  In addition, closed storage for collection management will also be provided. 

 

On January 17, 2006, Council approved the submission of a grant to the Federal Cultural Spaces for the reconstruction of Phase 1 of the Ward Building in the amount of $1,097,250.  Council also approved $325,000 to hire an architect to design the facility in the 2006 Capital Budget (Project #7004).  In addition, $1,674,750 was pre-approved in the 2007 budget for the construction of the facility conditional on the approval of the Federal Cultural Spaces grant and $228,000 is available from various previously secured funding sources.  Total project funding is $3,325,000.

 

On February 27, 2007, Council approved hiring the Ventin Group Ltd. Architects to complete the schematic design for the project. 

 

OPTIONS/ DISCUSSION:

 

1)                  The design charette recommends locating the new Ward Building at the front of the Museum site on the north side of the Reception Centre

 

Work on the project began shortly after the award of this contract.  The first two steps of the design process were to determine the best location for the new building and to review the existing condition of the Ward Building.  This work was to be done in conjunction with the independent Site Development Master Plan for the Museum site being undertaken by EDA Collaborative Landscape Architects under the supervision of the Urban Design section.

 

To ensure input from all the stakeholders a design charette to determine the options for the location of the new Ward Building and the Master Plan was convened on April 5, 2007.  The charette was jointly facilitated by the Ventin Group and EDA Collaborative.   It was attended by Museum staff, Museum Board members, including Councillors, Urban Design staff and Asset Management staff.  The group developed options for locating the building.  The consensus from the charette was that a location at the front of the Museum site on the north side of the Reception Centre was the preferred site.

 

2)                  The business case analysis recommends renovating the existing Ward Building for non Class “A” storage and other programming uses

 

The Facility Development Plan for the Museum Collection Building (Ward Building) was completed in April 2005.  This report concluded that in order to accommodate the Museum’s full collection, a building of 40,000 sq.ft. of Class “A” storage would eventually be required.  It concluded that it is not financially feasible to construct the total building at this time.  Therefore, it was decided that the building would have to be constructed in two phases.  Phase 1 would include 14,000 square foot reconstruction of the Ward Building.  A description of the various components included in the program is included in Attachment “B”. 

 

The facility plan also indicated that the existing Ward Building could not be economically renovated to meet the Class “A” storage requirements.  Therefore, the existing building was to be demolished and replaced with a new facility.

 

The Museum staff and board have recently reviewed their collection storage and programming needs.  In summary, they concluded that it would be advantageous to maintain the existing building to provide storage space that would not require the Class “A” storage environment, i.e.  sleighs, ploughs, etc., a workshop, and a large room for indoor gathering space for various purposes, including summer camps, wedding receptions, etc.  They also concluded that the phase 1 building program would meet their Class “A” storage requirements for the foreseeable future.  A drawing of the layout of the existing building is included as Attachment “C”.

 

On this basis, the architect completed a business case analysis of renovating the existing building to meet these requirements.  A copy of the business case is included as Attachment “D”.  Their conclusion was that for an investment of approximately $310,000, excluding design fees, the existing Ward Building could be renovated to meet the above programming requirements.  The replacement value of the building is estimated to be at least $1,800,000.  Therefore, the architect recommended to proceed with the renovation.

 

3)                  TAC, Museum Board and BPCC endorse the revised Building Strategy including locating the new Ward Building at the front of the site adjacent to the north side of Reception Centre and the renovation of the existing Ward Building

 

The architect prepared a presentation summarizing the results of the charette and the business case analysis for the renovating of the existing Ward Building.  The presentation also included a preliminary cost estimate of constructing the new building.

 

The presentation was made to the Technical Advisory Committee (TAC) on May 7, 2007, to the entire Museum Board at its May 14 meeting, and to the Building and Parks Construction Committee (BPCC) at its May 18, 2007, meeting.  Each of these committees endorsed revised Building Strategy, including locating the new Ward Building at the front of the site adjacent to the north side of  Reception Centre and the renovation of the existing Ward Building.  The minutes of these meetings are included as Attachment “E” and “F”.  The BPCC also requested that the architect explore the possibility of constructing a two-storey building.

 

4)                  The cost of the proposed building exceeds the budget amount

 

Unfortunately, the cost of the selected option far exceeds the funds allocated for the construction of this building.

 

The current allocation to construct the building is $1,870,000.  This was based on constructing a 14,000 sq.ft. building at the cost of $133.50/sq.ft.  The architect has reviewed the cost estimate.   They advise that the current construction costs for a pre-engineered building is $143.00/sq.ft.   This amount provides a building of similar quality to the existing Ward Building.   It does not provide for the building envelope necessary to achieve the Class “A” storage designation required for the new building.  In order to accomplish this environment, a building envelope is required to be built within the pre-engineered structure.  This would increase the cost to approximately $220.00/sq.ft.  This cost is approximately the same cost as to construct a conventional steel-frame building.   On this basis, the architect recommends proceeding with a conventional steel-frame building.  The architect has also developed a number of costing scenarios to assess the various options available to construct this project.  These pricing options are included in Attachment “G”. 

 

5)         Six Options for a building strategy for the Ward Building Reconstruction project have been developed.

 

Six options for a building strategy for the Ward Building Reconstruction project have been developed.  The options are based on either locating the Ward Building on or near its existing location or placing at the front of the Museum site, either demolishing or retaining the existing building, and either maintaining the existing construction cost estimate or exceeding the cost estimate.  The options are analyzed based on cost, as well as program, and site development criteria.

 

Option 1 - Demolish the Existing Ward Building and Construct a New Building in the same location within the existing cost allocation

 

The cost estimate to demolish the existing building is $100,000.  Therefore, the amount remaining for construction of a new building is $1,870,000 - $100,000 = $1,770,000.  The cost estimate to construct a building with a Class “A” storage area, with basic level quality, and on one level without a basement is $220.00/sq.ft.  Therefore, the size of the new building would have to be reduced from the 14,000 sq.ft. to $1,770,000/220.00/sq.ft. = 8,000sq.ft.

 

Option 2 - Retain the Existing Ward Building and Construct an Addition to the Building within the existing cost allocation

 

The cost estimate to renovate the existing building for non Class “A” uses is $310,000.  Therefore, the amount remaining for construction of an addition is $1,870,000 - $310,000 = $1,560,000.  The cost estimate to construct a building with a Class “A” storage area, with basic level of quality, and on one level without a basement is $220.00/sq.ft.   Therefore, the size of the addition would have to be $1,560,000/220.00/sq.ft.  = 7,000 sq.ft.  Therefore, the total area of building provided is 14,000 sq.ft. + 7000sq.ft. = 21,000sq.ft.

 

Option 3 - Retain the Existing Ward Building and Construct an Addition to the Reception Centre within the existing cost allocation

 

The cost estimate to renovate the existing building for non Class “A” uses is $310,000.  Therefore, the amount remaining for construction of an addition is $1,870,000 - $310,000 = $1,560,000.  As this addition is at the front of the site, it will be necessary to build a building with a medium level of quality on one level without a basement at the rate of $302.50/sq.ft.  Therefore, the size of the addition would have to be $1,560,000/302.50/sq.ft. = 5,100 sq.  ft.  Therefore, the total area of building provided is 14,000 sq.ft. + 5150sq.ft. = 19,150sq.ft.

 

Option 4 - Demolish the Existing Ward Building and Construct a new building to the original size

 

The cost estimate to demolish the existing building is $100,000.  The cost estimate to construct a Class “A” building, with basic level of quality, on one level with a basement is 14,000 sq.ft. X $220.00/sq.ft.  = $3,080,000.  The total cost is $3,080,000 + $100,000 = $3,180,000.  Therefore, the amount of additional funding required is $3,180,000 – $1, 870,000 = $1,310,000.  The total area of building provided is 14,000 sq.ft.

 

Option 5 - Retain the Existing Building and Construct a new building to the Original Size adjacent to the existing building

 

The cost estimate to renovate the existing building is $310,000.  The cost estimate to construct a Class “A” building, with a basic level of quality, on one level with a basement is 14,000 sq.ft. X $220.00/sq.ft.  = $3,080,000.  The total cost is $3,080,000 + $310,000 = $3,390,000.  Therefore, the amount of additional funding required is $3,390,000 – $1,870,000 = $1,520,000.  The total area of building provided is 14,000 sq.ft.  + 14,000 sq.ft. = 28,000 sq.ft.

 

Option 6 - Retain the Existing Building and Construct a new building to the Original Size at the front of the site

 

The cost estimate to renovate the existing building is $310,000.  The cost estimate to construct a Class “A” building, medium level quality, on one level with a basement is 14,000 sq.ft. X $302.50/sq.ft.  = $4,235,000.  The total cost is $4,235,000 + $310,000 = $4,545,000.  Therefore, the amount of additional funding required is $4,545,000 – $1,870,000 = $2,675,000.  The total area of building provided is 14,000 sq.ft. + 14,000 sq.ft. = 28,000sq.ft.

 

 

 

 

 

 

 

 

 

 

 

 

 

ANALYSIS OF OPTIONS

 

Table 1

Cost Comparison of Options

 

 

Description

Cost

Additional Funding Required

Size (sq.ft)

Cost/sq.ft

Option 1

Demolish the existing Ward Building and construct a new building in the same location within the existing cost allocation. 

 

$1,870,000

0

8000 New

$233.75

Option 2

Retain the existing Ward Building and construct an addition to the building within the existing cost allocation

 

$1,870,000

0

  14,000 Reno

  +7,000 New

  21,000

$89.00

Option 3

Retain the existing Ward Building and construct an addition to the Reception Centre within the existing cost allocation.

 

$1,870,000

0

  14,000 Reno

 +5,150  New

  19,150

$97.65

Option 4

Demolish the existing Ward Building and construct a new building to the original size

 

 

 

$3,180,000

$1,310,000

  14,000 New

$227.00

Option 5

Retain the existing Building and construct a new building to the original size adjacent to the existing building

 

$3,390,000

$1,520,00

   14,000 Reno

 +14,000 New

    28000

$121.00

Option 6

Retain the existing Building and construct a new building to the original size at the front of the site

 

$4,545,000

$2,675,000

  14,000 Reno

+14,000 New

   28,000

$162.32

 

From a cost perspective, Options 2 and 3 provide the best value and remain within the current cost allocation, as well as provide more space than original concept.  Options 1 and 4 involve demolishing of the existing facility and have high cost per sq.ft.  Option 1 does not meet the original space requirements.  Options 5 and 6 provide considerably more space than the other options:  However, they are well beyond the existing cost allowance.

 

 

 

 

 

 

 

 

Table 2

Comparison of Program and Site Development Considerations

 

 

Description

Program

Site Development

Option 1

Demolish the Existing Ward Building and Construct a New Building in the same location within the existing cost allocation. 

 

·    Does not provide specified amount of Class “A” storage space

·   Does not provide supplemental non Class “A” storage space

 

·         The location would be remote from the Reception and Administrative areas

·         The location is not consistent with the site development Master Plan and would not serve to increase the Museum’s profile on Hwy 48.

 

Option 2

Retain the Existing Ward Building and Construct an Addition to the Building within the existing cost allocation

 

·   Does not provide specified amount of Class “A” storage space

·   Does provide supplemental non Class “A” storage space

 

·         The location would be remote from the Reception and Administrative areas

·         The location is not consistent with the site development Master Plan and would not serve to increase the Museum’s profile on Hwy 48.

 

Option 3

Retain the Existing Ward Building and Construct an Addition to the Reception Centre within the existing cost allocation.

 

·   Does not provide specified amount of Class “A” storage space

·   Does provide supplemental non Class “A” storage space

 

·         The location would be in close proximity to the Reception and Administrative areas

·         The location is consistent with the site development Master Plan and would serve to increase the Museum’s profile on Hwy 48.

 

Option 4

Demolish the Existing Ward Building and Construct a new building to the Original Size

 

·   Does  provide specified amount of Class “A” storage space

·   Does not provide supplemental non Class “A” storage space

 

·         The location would be remote from the Reception and Administrative areas

·         The location is not consistent with the site development Master Plan and would not serve to increase the Museum’s profile on Hwy 48.

 

Option 5

Retain the Existing Building and Construct a new building to the Original Size adjacent to the existing building

 

·   Does  provide specified amount of Class “A” storage space

·   Does provide supplemental non Class “A” storage space

 

·         The location would be remote from the Reception and Administrative areas

·         The location is not consistent with the site development Master Plan and would not serve to increase the Museum’s profile on Hwy 48.

 

Option 6

Retain the Existing Building and Construct a new building to the Original Size at the front of the site

 

·   Does  provide specified amount of Class “A” storage space

·   Does provide supplemental non Class “A” storage space

 

·         The location would be in close proximity to the Reception and Administrative areas

·         The location is not consistent with the site development Master Plan and would not serve to increase the Museum’s profile on Hwy 48.

 

 

Options 5 and 6 meet all the program requirements.  Options 3 and 6 meet the site development requirements.

 

Other considerations:

 

1)         The Federal Cultural Spaces officials have indicated that a reduction in the size of the new building would result in a review of the grant.  This may result in a reduction in the amount of the grant.

 

2)         The current estimate does not include energy/environmental enhancements to achieve Leadership in Environmental and Energy Design (LEED) certification.   The architect has provided a preliminary analysis of the cost for the various levels of LEED certification.

 

A summary of the analysis is included as Attachment “H”.   The cost to provide LEED certification ranges from $140,000 - $420,000.   A detailed LEED business case will be provided with the schematic design.

 

3)         The above costs are preliminary only to provide order of magnitude pricing to assess the various options.   At the completion of the schematic design a detailed estimate for construction for the selected building strategy option will be provided.

 

4)         The architect has determined that the most economic building configuration to provide a new 14,000 sq.ft. building is to construct an on level building with a basement.  The basement provides an ideal envelop to construct the Class storage and does not require extensive exterior or interior finishing.  Selection of a two storey building without a basement for the building configuration would add significant costs to the facility.  A summary of these costs is included as Attachment “G”.

 

5)         Depending on the option selected, the overall Museum future building program will have to be reviewed.  If the program is reduced from the14,000 sq.ft., the future building program will have to be increased.   If the program is increased from the 14,000 sq.ft., the future building program can be reduced accordingly.

 

6)         Conclusion

In order for the design process to continue, it is requested that Council provide direction on the building strategy for the Ward Building Reconstruction project.   Once this direction is provided, the architect can continue with the schematic design process.  Every effort will be made to control the cost of the new building while ensuring the building meets the Town’s design requirements as the design process proceeds.

 

FINANCIAL TEMPLATE: (external link)

Not Applicable

 

ENVIRONMENTAL CONSIDERATIONS:

None

 

ACCESSIBILITY CONSIDERATIONS:

None

 

ENGAGE 21ST CONSIDERATIONS:

None

 

BUSINESS UNITS CONSULTED AND AFFECTED:

Cultural Services Department

Finance Department

 

 

 

RECOMMENDED

                            BY:    ________________________          ________________________

                                      Steve Andrews, P.Eng.                       Peter Loukes, P. Eng.

                                      Director, Asset Management               Acting Commissioner

                                                                                                Community and Fire Services

 

ATTACHMENTS:

 

ATTACHMENT “A” - Project Cost Estimate

ATTACHMENT “B” - Program Description

ATTACHMENT “C” - Existing Conditions Ward Building

ATTACHMENT “D”- Business Case for Renovating the Existing Ward Building

ATTACHMENT “E” - Minutes Museum Board May 14, 2007

ATTACHMENT “F” - Minutes BPCC May 18, 2007

ATTACHMENT “G” - New Museum Building Costs

ATTACHMENT “H” - LEED Certification Costs

 

Q:\Commission Share\Operations and Asset Management\Reports\2007\Asset Management\Capital Facilities\Report to General Committee June 25 2007 re  Revised Building Strategy for the Ward Building Reconstruction Option Version.doc