Report to: General Committee Report
Date:
SUBJECT: Award of Tender # 065-T-08
Traffic Calming at
PREPARED BY: Parveen Kalia, Engineering Technician, Ext. 6200,
Domenic Smarrelli, Supervisor Traffic Operations, Ext. 4055
Tony Casale, Senior Buyer, Ext. 3190
RECOMMENDATION:
THAT the report entitled “Award of Tender
# 065-T-08 Traffic Calming at Royal Orchard Boulevard,
Carlton Road and Village Parkway” be received;
AND THAT a contingency in the amount of $56,062.00 exclusive of
GST, be established to cover any additional construction costs and that the
Director of Engineering be authorized to approve expenditure of this
contingency amount up to the specified limit;
AND THAT the award be
funded from the 2007 Engineering Capital for Safe Streets Programme, project #
083 5350 7660 005 in the amount of $429,815.00;
AND THAT
EXECUTIVE SUMMARY:
Not applicable
This report seeks
Council approval to award the contract for Traffic Calming at
The Top Twenty Five (25) Streets received one (1) year of enhanced police enforcement. The traffic speed and volume studies were conducted before, during and after enhanced police enforcement period. Based on the speed compliance effectiveness study results and the Traffic Safety Committee’s recommendation, the following six (6) streets were identified for consideration of physical traffic calming measures:
A public information session was held on
The
construction tender # 065-T-08 was issued in accordance with
Project Schedule
Pending Council approval, the construction is expected to commence in July 2008. The traffic claming construction is scheduled for July/August 2008 given that traffic volumes will be lower during this period and that the schools will be on summer break.
Community Notice
Notice letters will be sent to the residents fronting the project streets. Notice letters will advise the community regarding the upcoming traffic calming construction on their respective street and construction schedule.
Contingency
Contingency amount of $56,062.00 exclusive of GST is 15% of the tender cost. Construction contingency has been kept to cover any unforeseen construction costs.
BID
INFORMATION:
Advertised |
ETN |
Bids closed on |
|
Number of contractors
picking up bid documents |
13 |
Number of contractors
responding to bid |
6 |
DETAILED PRICING INFORMATION:
Company |
Total Price, Excl GST |
Mopal Construction Limited |
$373,753.00 |
Concord
Paving Inc. |
$438,140.00 |
Il
Duca Contracting Inc. |
$454,562.00 |
|
$500,231.84 |
|
|
|
|
|
Original Budget and Account # |
|
$690,100 |
|
083 5350 7660
005 Safe Streets Programme |
Current Budget Available (unspent) |
|
$682,563 |
|
|
Less Cost |
|
($373,753) |
|
Awarded
to Mopal Construction Limited |
Less Contingency |
|
($56,062) |
|
|
Budget Remaining |
|
$252,748 |
|
|
Note:
The remaining budget amount of $252,748.00 will be used for alternative
measures of traffic calming on
Not applicable
Not applicable
Not applicable
Not applicable
RECOMMENDED
BY: ________________________ ________________________
Alan Brown, C.E.T. Jim Baird, M.C.I.P., R.P.P.
Director of Engineering Commissioner, Development Services