DEVELOPMENT SERVICES COMMITTEE

 

 

 

 

 

TO:

Mayor and Members of Council

 

 

 

 

FROM:

Valerie Shuttleworth, Acting Director of Planning

Jim Baird, Acting Commissioner of Development Services

 

 

 

 

PREPARED BY:

Dave Miller, Senior Planner, West District Team

 

 

 

 

DATE OF MEETING:

2003-Oct-14

 

 

 

 

SUBJECT:

Langstaff Land Use Study, Terms of Reference, Phase I

(SD.03 - 116189)

 

 

 


 

RECOMMENDATION

THAT the Development Services Commission Report entitled “Langstaff Land Use Study, Terms of Reference, Phase I”, dated October 14, 2003, be received;

 

THAT the study terms of reference attached as Appendix ‘A’ be endorsed;

 

THAT staff be authorized to proceed with consultant selection and commencement of the Study, in accordance with provisions of the Purchasing By-law, with consultant fees not to exceed $37,190.29 inclusive of 7% G.S.T. ($35,800 inclusive of 3% G.S.T.);

 

THAT funds are provided for in Planning Department’s 1993 Capital Budget Account # 79 5399 135 Langstaff Study and 2002 Capital Budget Account # 80 5399 4812 005 Langstaff Land Use Study (Phase 2);

 

AND THAT staff report back on the consultant selection and detailed work program upon completion of the “Request for Proposal” process.

 

PURPOSE

The purpose of this report is to provide information on the terms of reference for a Langstaff Land Use Study.  The terms of reference attached to this report as Appendix ‘A’ provides a guideline for the Purchasing Department to begin negotiations with preferred consultant(s).

 

DISCUSSION

 

Background

The Langstaff area is a mixed use enclave of small-scale industrial, open storage and residential uses.  The area is bounded to the north by Highway 407, to the south by the Holy Cross Cemetery, to the east by Bayview Avenue and to the west by Yonge Street.  Consequently, the area is isolated from the remainder of Thornhill.  A framework for a mixed commercial and residential community was established in the Thornhill Secondary Plan.  The Thornhill Secondary Plan was approved in June of 1997, with modifications.  However, the land assembly and re-development anticipated by that Plan has not occurred.

 

The original version of the Thornhill Secondary Plan as adopted in 1991 contemplated redevelopment of the existing industrial and residential areas in the Langstaff area upon the completion of more detailed studies and a Tertiary Plan addressing land use and market analysis, urban design guidelines, environmental protection and mitigation, and infrastructure requirements respecting transportation, water, sewers and storm water management. In March 1992, Council authorized the undertaking of the Langstaff Development Feasibility and Urban Design Study.

 

The Langstaff Development Feasibility and Urban Design Study completed in February 1995 included, amongst other things, an assessment of opportunities and constraints for the Langstaff Area lands, a community review of three development options, and a recommended land use plan along with guidelines for infrastructure improvements and an implementation strategy.  The Tertiary Plan recommended by the Study was approved in June 1997, as an amendment to the Thornhill Secondary Plan.  The Secondary Plan designates the Langstaff area for Retail Warehouse use between Yonge Street and the C.N.R., and for Urban Residential (Medium Density) from the C.N.R. to Bayview Avenue.

 

The area context has evolved over the last six years

Since the introduction of the Langstaff Redevelopment Area policies into the Thornhill Secondary Plan, a number changes in land use and infrastructure have occurred or are currently under review which may directly influence the feasibility of redevelopment potential for the Langstaff area.

 

These changes include:

 

·        the construction of Highway 407 and the resulting access arrangements and grade conditions;

·        the partial realignment of Langstaff Road East with signalized access to Yonge and Bayview;

·        a proposal by MTO for a Hwy 407 Transitway with stations within the vicinity of the Langstaff area;

·        a proposal to relocate the GO Station north to a new Richmond Hill Intermodal Station and a new underpass access from Langstaff Road East to the new GO station;

·        proposals by the York Rapid Transit Plan Consortium for a Yonge Street Transitway and a Hwy 7 Transitway, including a potential maintenance facility west of the CNR line in the Langstaff Area;

·        redevelopment of the Jail Farm lands in Richmond Hill as a retail warehouse centre; and

·        the further development of the adjoining Cemetery lands by the Catholic Archdiocese.

 

In addition, a number of changes to planning policy and legislation have occurred or are under review which may also directly influence the feasibility of redevelopment potential for the Langstaff area.  The changes include:

 

·        approval of the Town’s Strategic Plan and Corporate Goals;

·        the Langstaff Sewer and Watermain Design Study now underway (by the Town);

·        adoption of the Markham Transportation Planning Study;

·        an endorsement of rapid transit corridor planning principles for the Hwy 7 corridor and authorization to complete a study of public transit and transit supportive development opportunities along Highway ,7 by the Town;

·        confirmation of the Town’s role respecting the provision of rental and affordable housing and opportunities for Community Rental Housing Program funding;

·        a proposal by York Region for policy changes to implement a Centres and Corridors Strategy - identifying a new Richmond Hill/Langstaff Regional Centre and identifying Highway 7 as a Regional Corridor;

·        new Provincial legislation respecting Brownfields redevelopment;

·        Revision to the Town’s Community Improvement policies; and

·        a review of lands under Provincial ownership by the Ontario Realty Corporation.

 

Anticipated re-development has not occurred

The land assembly and redevelopment anticipated in the Thornhill Secondary Plan has not occurred.  A detailed review of the Langstaff Redevelopment Area policies is required to determine whether the mix of land uses, densities, design and development standards, and infrastructure and transportation arrangements currently contemplated continue to be appropriate.  This review should include, but not be limited to, an up to date analysis of the opportunities and constraints for redevelopment and a review of previous development options including land use and servicing configurations to determine if the changes outlined above or changes in market trends have influenced the feasibility of redevelopment potential for the Langstaff area.

 

Staff anticipate that the full study will be conducted in two phases.  In Phase I the consultant team would review and evaluate the opportunities and constraints facing the Langstaff area.  If the Phase I report recommends substantial changes to the policies of the Thornhill Secondary Plan the Phase II consultant would be expected to recommend specific policies to be incorporated into the Thornhill Secondary Plan, provide an Urban Design Plan and a Development Guidelines Report, and prepare any required implementation documents such as Zoning and Property Standard By-laws.

 

Additional funding for the study was approved in the 2002 Capital Budget

Council allocated approximately $20,600 for this study in the 2002 Capital Budget and approximately $15,200 remains in the 1993 budget, from the earlier study.  Town staff have prepared a detailed terms of reference for this study.  The proposed terms of reference are attached as Appendix A.

 

 

CONCLUSION

The attached Terms of Reference for the Langstaff Land Use Study have been forwarded to the Purchasing Department as a guideline for initiating the “Request for Proposal” process, and negotiating the contract with the selected consultant, subject to the Chief Administrative Officer’s approval.

 

Planning Department staff will report back to the Development Services Committee on the consultant selection and detailed work program, upon completion of the “Request for Proposal” process.

 

FINANCIAL CONSIDERATIONS

Sufficient funds to retain a consultant to carry out the Langstaff Land Use Study, Phase I have been approved in the 1993 and 2002 Development Services Commission Capital Budget Account # 79 5399 135 Langstaff Study and Account # 80 5399 4812 005 Langstaff land Use Study (Phase 2) respectively.

 

BUSINESS UNITS CONSULTED AND AFFECTED

Internal departments and external agencies will be involved as required during the study. 

 

ATTACHMENTS

 

Figure 1                     Langstaff Study Area

Figure 2                     Area Context and Zoning

Figure 3                     Air Photo

 

Appendix ‘A’            Langstaff Land Use Study Terms of Reference

 

 

 

 

 

 

Valerie Shuttleworth, MCIP, RPP

Director of Planning and Urban Design

 

Jim Baird, MCIP, RPP

Commissioner of Development Services

 

Q:\Development\Planning\Teams\WEST\Langstaff Area\SD 03 - 116189\DSC - October 14, 2003 report.doc