|
|
|
|
|
|
|
|
|
|
TO: |
Mayor and Members of Council |
|
|
|
|
FROM: |
Jim Baird, Commissioner of Development
Services Valerie Shuttleworth, Director of Planning & Urban Design |
|
|
|
|
PREPARED BY: |
Scott Heaslip,
Project Co-ordinator, East Development District |
|
|
|
|
DATE OF MEETING: |
2003-Dec-09 |
|
|
|
|
SUBJECT: |
Cornell
Community, Development Phasing Plan Update |
|
|
|
RECOMMENDATION:
That the Planning
and Urban Design Department report dated December 9, 2003 entitled “Cornell
Community, Development Phasing Plan Update” be received;
And that the
“Cornell Community, Development Phasing Plan Update” be approved;
And that the
Commissioner of Development Services be authorized to approve minor
modifications to the updated development phasing plan, provided they are in
keeping with the intent of the Plan;
And that Council
be kept appraised of any modifications to the development phasing plan that
would have a significant effect on the overall delivery or allocation of
services, roads or facilities, or the timing of approval of development;
And further that the Mayor and Clerk be authorized to execute a phasing
agreement with the Cornell Landowners Group outlining the phasing requirements
and associated implementation measures.
PURPOSE
The purpose of
this report is to recommend approval of an updated development phasing plan for
the Cornell Community and to seek authorization for the Mayor and Clerk to
execute a phasing agreement with the Cornell Developers Group, to secure the
key phasing requirements.
BACKGROUND
The
Cornell Community Development Phasing Plan was approved in 1997
In 1997 the
majority of the land in the Cornell Community was under the control of one major
landowner (The Law Development Group) and was planned to be developed in 6
sequential phases as shown on Figure 2, attached. Phase 1 has been constructed by the Law
Development Group in accordance with the approved development phasing plan.
Subsequent
changes in land ownership have resulted in revisions to the sequencing of
development
Since construction
of Phase 1, the remaining lands, which were originally under the control of the
Law Development Group, have been conveyed to four landowners – Mattamy Homes
(Phase 2/3), H and R Developments (Phase
4), Madison Homes (Phase 5), and Metrus Properties (Phase 6). These landowners propose to develop their
holdings concurrently, whereas the 1997 development phasing plan assumed that
the phases would be developed sequentially.
The phasing plan therefore needs to be updated to reflect the revised
timing of development.
The
development of Cornell has also been impacted by additional infrastructure and
other new developments in the vicinity
The impact of
additional infrastructure, constructed subsequent to the preparation of the
original development phasing plan needs to be addressed in the development
phasing plan. This new infrastructure
includes Highway 407, the 9th Line sanitary sewer and the Markham
By-pass. As well, the development of the
Greensborough Community and the anticipated development in the Box Grove area
needs to be included in the phasing plan.
Council
has draft approved plans of subdivision for the four major Cornell
landowners, subject to a development
phasing plan update and phasing agreement
The Metrus and H
and R plans were draft approved in June 2002; the Mattamy and Madison plans in
July 2003. The conditions of draft approval for each of these draft plans
includes the following clause, requiring the development phasing plan to be
updated and the developers group to enter into a phasing agreement with the
Town, prior to final approval (registration):
“The Owner
covenants and agrees to prepare, in consultation with the Owners of the other
urban lands within the Cornell Planning District, an update to the Development
Phasing Plan for the Cornell Community.
The Cornell
Developers Group shall enter into a legal agreement with the Town with respect
to the implementation of the Updated Development Phasing Plan referred to in
Condition 9.1. Such agreement shall
document the Group’s commitment regarding the following items:
·
Completion of Bur Oak from Highway 7 to 9th
Line.
·
Provision of an east-west road connection between Bur
Oak Avenue and (existing) Markham By-pass.
·
Assistance to the Region of York, if required, for
provision of external road infrastructure in accordance with the time frames
outlined in the Region’s 10 year capital works program.
The updated Development Phasing Plan shall be approved by Council and the
Development Phasing Agreement shall have been executed by the Owner and the
Town prior to final approval of the draft plan of subdivision.”
Council
granted additional water allocation to Cornell subject to the completion of Bur
Oak Avenue
On October 21,
2003, Council granted an additional 480 units of water allocation to the
Cornell community, subject to a commitment from the Cornell Developers Group to
extend Bur Oak Avenue from its current terminus at Riverlands Avenue (one block
north of Church Street) to Highway 7, by no later than December 2005. This
commitment along with the completion of Bur Oak Avenue through the approved
draft plans will complete Bur Oak Avenue through the Cornell area and make it
continuous from Highway 7 to Kennedy Road. This commitment needs to be
reflected in the development phasing plan and secured in a phasing
agreement. .
The
Cornell Developers Group has submitted a development phasing plan update which
proposes three stages of development.
The development phasing plan update (Appendix
‘A’) outlines how development will progress over time, and identifies the
servicing infrastructure and road network to be provided with each stage of
development. The three stages (Figure 3) are comprised of the following:
Stage 1 -
consists of the four draft approved plans
- 1914 residential units
- utilizes a large portion of the existing
water allocation
- preliminary
servicing has commenced, substantial build out anticipated
in 2005
- community commercial block on south side of Highway
7 at Bur Oak
Avenue
- 27.6 hectares of employment lands located south of
Highway 7 and west
of the future
Markham By-pass.
- assuming confirmation from Region of additional
water allocation to
allow
servicing in 2005, first occupancies in
2006.
Stage 3 - 2312 residential units
- first occupancies 2007/08.
Total Community
7705 residential units
41.2 hectares of commercial and employment land.
The development phasing plan update includes the
following key components:
·
A commitment to construct, and convey to the Town, Bur
Oak Avenue from Riverlands Avenue to Highway 7 by December of 2005. The
construction of this last remaining section of Bur Oak Avenue will
complete this important collector road which commences at Highway 7 and runs
north across 16th Avenue, turning to the west through the
Greensborough, Wismer and Berczy Village communities to Kennedy Road.
·
A commitment to size the sanitary sewer and water
systems to accommodate a potential increase in density along the Highway 7
corridor to bring the total number of residential units up to 10,000, provided
for by the Cornell Secondary Plan. This will ensure that sufficient servicing
capacity is available to accommodate transit supportive development along the
Highway 7 corridor in support of the Highway 7 Corridor Study and the York
Rapid Transit Plan.
The delivery of
parks, schools and place of worship sites is not specifically addressed in the
development phasing plan update because the location of these uses is not yet
finalized. These items will be addressed
through an updated Secondary Plan for Cornell.
The Secondary Plan update is currently being prepared for consideration by
Council in the first quarter of 2004.
An additional update to the phasing plan may be required, following
completion of the Cornell Secondary Plan update.
Development
Phasing Plan Update recommended for approval
The Cornell
Development Phasing Plan Update provides the framework for the logical,
sequential buildout of the Cornell Community and outlines the required
infrastructure and public facilities to support each of three stages of
development. The proposed sequencing of
development will provide adequate community connectivity at each stage of
development while minimizing the exposure of occupied homes to construction
activity and traffic. The Development Services Commission will monitor the
development phasing plan and implementation mechanisms to ensure development
proceeds in an orderly manner.
It has been the Town’s practice to require developers groups to enter into a development phasing agreement with the Town, to secure the recommendations of the approved development phasing plan. To date, the Town has secured such agreements for the Wismer Commons, Greensborough and Berzcy communities. The phasing agreement for Cornell would include, among other items, the following:
·
Requirement to extend Bur Oak Avenue to Highway 7 by
December 2005.
·
Requirement of an east-west road connection between
Bur Oak Avenue and (existing) Markham By-Pass
·
An acknowledgement by the Landowners Group that
completion of the Region’s infrastructure improvements within the prescribed
time limits is required to support development phasing as set out in the
phasing plan.
·
An acknowledgement from the Landowners Group that
should there be any delay in the completion of the Region’s infrastructure
improvements, the Landowners Group will consider options, financial and
otherwise, to ensure the delivery of required infrastructure keeps pace with
the development objectives outlined in the Phasing Plan, or to adjust their
development schedule accordingly.
·
An acknowledgement from the Landowners Group that the
Town reserves the right to update the phasing plan to reflect any changes to
existing and projected conditions
BUSINESS
UNITS CONSULTED AND AFFECTED:
The development
phasing plan has been prepared in consultation with various Town departments
and external agencies.
ATTACHMENTS:
Figure 1 -
Applicant/Agent and Location Map
Figure 2 – Development
sequencing - 1997 Phasing Plan
Figure 3 - Proposed Development Sequencing
Appendix ‘A’ –
Development Phasing Plan Update
|
|
|
Valerie Shuttleworth,
M.C.I.P., R.P.P. Director of Planning &
Urban Design |
|
Jim Baird, M.C.I.P., R.P.P. Commissioner of Development
Services |
DOCUMENT # Q;\development\planning\appl\cornell\phasing\Dec 9 03 report
APPLICANT/AGENT: Al Bishop Tel:
(905) 624-1250
ReDevco Management Fax:
(905) 624-1257
4339 Garnetwood Chase
Mississauga, Ontario
L4W 2H1
LOCATION MAP: