RECOMMENDATION:
THAT the report dated March 2, 2004, to
Development Services Committee, entitled “Up-fronting of the Design and Construction a
Neighbourhood Park by 1473092 Ontario Ltd. in Metrus
Development Inc.’s Upper Cornell” be received.
AND THAT Council approve the request by 1473092
Ontario Ltd. to up-front the cost of design, construction and contract
administration of the 4.72 acre neighbourhood park in Upper Cornell (Cornell
Phase 6) subject to the following conditions:
- That 1473092 Ontario
Ltd. up-front the cost of the design, construction and contract
administration of the neighbourhood park to minimum value of $95,000.00
per acre which totals approximately $448,400.00 inclusive of all
applicable taxes;
- That, subject to
compliance with these terms and conditions, the Town of Markham
reimburse 1473092 Ontario Ltd. up to $448,400.00 towards this project from
development charges for park development under the understanding that 1473092
Ontario Ltd. may contribute additional funds, which will not be reimbursable
by the Town, towards the development of this park;
- That the Town reimburse
1473092 Ontario Ltd. for invoices paid on a single lump sum basis for all
approved costs associated with the design, construction and contract
administration, including all applicable taxes, of the neighbourhood park up
to a maximum of $448,400.00, less the 10% holdback to be released to them
upon final assumption of the park by the Town, after sufficient
Development Charges for park development have been collected (90% of a
maximum of $448,400) at the building permit stage for residential lots
within the Cornell Community to warrant repayment in full to the maximum
allowable. No interest on such invoices shall be payable by the Town;
- That owners /
developers within the Cornell Community, including 1473092 Ontario Ltd. not
receive any credit towards park development charges and continue to pay
the park development charge at the building permit stage for all present
and future development phases of subdivisions within the Cornell Community;
- That 1473092 Ontario
Ltd. hire a landscape architect who is a full member of the OALA, and
approved by the Town, to provide professional design, contract document,
and contract administration services to the satisfaction of the Town;
- That 1473092 Ontario
Ltd. conform with the Town’s standard park and open space approval process
which includes development of several design concepts, holding community
input meetings, presentation to selected Standing and Advisory Committees,
as well as review and approval by the Planning and Urban Design Department in
consultation with the Parks Operations Department. This process will also
be informed by the Town’s on-going Recreation Master Plan Update Study
which will establish park facility requirements and priorities;
- That 1473092 Ontario
Ltd. agree to the deferral of the design approval of all other parkettes and urban open spaces within Upper Cornell
so that these elements can be designed, reviewed and approved in a
coordinated manner with the design of this park. The construction of these
specific elements, prior to the Town assuming the subdivision, are an
obligation of 1473092 Ontario Ltd. as set out within the subdivision
agreement;
- That 1473092 Ontario
Ltd. tender out the construction of the park works in accordance with
Markham’s Purchasing By-law, including a minimum of three bidders to the
satisfaction of the Town and a 2 year detailed maintenance contract for
the park to the Town’s satisfaction as part of the tendered works. Costs
for the 2 year maintenance contract are the responsibility of 1473092
Ontario Ltd.;
- That, notwithstanding
the requirements noted above in Condition (8), 1473092 Ontario Ltd. shall
also maintain the park to Town standards, from the time that it is built until
such time as the park would normally have been built in accordance with
the Town’s park development strategy for Cornell (which normally coincides
with the time when sufficient Development Charges for park development
have been collected within the Cornell Community to warrant starting park
construction). The Town will not reimburse 1473092 Ontario
Ltd. for costs associated with this additional maintenance obligation for the
park;
- That this park be
included in the Urban Design, Development Services Commission, 2005 Capital Budget submission;
- That these terms and
conditions be included in the Subdivision Agreement for this draft plan.
PURPOSE:
This
report seeks approval for 1473092 Ontario Ltd. to up-front the costs of design,
construction, and contract administration associated with development of a 4.72
acre neighbourhood park in Upper Cornell.
BACKGROUND:
As
part of the overall parks and open space master plan for Cornell Neighbourhood
Phase 6 (Upper Cornell), a 4.72 acre neighbourhood park is to be developed as
part of a 10.472 acre school/park campus located at Bur Oak and Country Glen Road,
just east of Ninth Line and north of 16th Avenue.
This neighbourhood park is intended
to be a focus for Upper Cornell and will provide for community gatherings and
events. A preliminary concept or facility fit plan for the park is attached
which shows entry ways, a gazebo, seating areas, a children’s play area, a
soccer field (on school property), a softball pitch, and tree and shrub planting.
OPTIONS/DISCUSSION:
In a letter
dated November
7, 2003, Mr. Nic Mracic of Metrus Developments
Inc. on behalf of 1473092 Ontario Ltd., requested permission from the Town to
allow Metrus Developments Inc. to proceed with the
design and construction of the neighbourhood park in advance of the Town’s
projected schedule. 1473092 Ontario Ltd. is motivated to build this park early
for marketing reasons and as such is hoping to start construction later in 2004
if possible.
As part of
the draft plan for Cornell, Phase 6, 1473092 Ontario Ltd. is required to convey
and build, at their cost, certain parkettes and urban
open spaces. So that these elements can
be designed, reviewed and approved in a coordinated manner with the design of
the neighbourhood park, it is recommended that the design approval of these
spaces within Upper Cornell be deferred and included as part of the park and
open space approval process.
In
consideration of this request, this report seeks Council’s approval for the
early delivery of this park by 1473092 Ontario
Ltd. in accordance with the recommendations noted herein.
FINANCIAL CONSIDERATIONS:
The
Finance Department has reviewed this report and are in agreement with its
recommendations.
BUSINESS UNITS CONSULTED AND AFFECTED:
The
Finance and Legal Departments have been consulted in the development of this
report.
ATTACHMENTS:
Appendix
A:Letter from Mr. Nic Mracic, Metrus
Developments Inc.
Appendix
B: Key Map
Appendix
C: Preliminary Park Concept Plan by The MBTW Group
|
|
|
Valerie Shuttleworth, M.C.I.P., R.P.P.
Director of Planning & Urban Design
|
|
Jim Baird, M.C.I.P., R.P.P.
Commissioner of Development Services
|
Q:\Development\Design\linda\Parks\MetrusParkReport.doc