RECOMMENDATION:

That the Box Grove Community Development Phasing Plan, dated March 2004, completed by KLM Planning Partners Inc, Stantec Consulting Ltd. and URS Canada Inc, and attached as Appendix ‘A’, be endorsed:

 

That the Commissioner of Development Services be authorized to modify the Box Grove Community Development Phasing Plan as outlined in the report, and as may be necessary to permit development to occur in keeping with the intent of the Box Grove Secondary Plan and Memorandum of Understanding, as well as to reflect the implementation of key transportation infrastructure and servicing requirements including water and sewage allocation, and any requirements of the Region of York;

 

That Council be kept appraised of any modifications to the Development Phasing Plan that would have a significant effect on the overall delivery or allocation of municipal services, roads or facilities, or the timing of approval of development;

 

And further that the Mayor and Clerk be authorized to execute a phasing agreement with the Box Grove Developers Group outlining the phasing requirements and associated implementation measures, to be fully executed prior to the release of any plans of subdivision for registration.

 

PURPOSE:

The purpose of this report is to recommend endorsement of the Box Grove Community Development Phasing Plan, and to seek authorization for the Mayor and Clerk to execute a Phasing Agreement with the Box Grove Developers Group, to secure the key phasing requirements.

 

BACKGROUND:

The Box Grove Community is bounded by Highway 407 to the north, the CP Havelock Rail Line and Reesor Road to the east, the CN York Rail Line to the south, and 9th Line and the Rouge River to the west (Figure 1).  The community is approximately 320 hectares in size and includes the former Box Grove Hamlet, which is approximately 45 hectares in size.

 

It is anticipated that the community will be comprised of approximately 2,600 residential units when fully developed.  The Box Grove developers propose to begin servicing the site (Phase Once) in summer/fall of 2004, and building construction of Phase One (1,365 units) is proposed to commence in the spring of 2005.

 

Development Phasing Plan required by Secondary Plan

On November 18, 2003 the Ontario Municipal Board approved the Box Grove Planning District Secondary Plan (OPA 92). The Box Grove Secondary Plan requires that a Development Phasing Plan be prepared to the satisfaction of the Town, in consultation with the Region and any applicable agencies, prior to approval of any development within the area.  The Secondary Plan also sets out the matters to be addressed in the Phasing Plan.

 

Phasing Plan based on principles/directions set out in Memorandum of Understanding and the Secondary Plan

The Development Phasing Plan prepared for the Box Grove area is guided by the principles/directions set out in the Memorandum of Understanding and the Secondary Plan. The Owners entered into a Memorandum of Understanding with the Town of Markham and the Region of York on June 13, 2002, which in part outlines the developer’s obligations towards transportation and servicing improvements for the Box Grove community.  The memorandum of understanding includes commitments by the developers to:

 

  • Install municipal water to the property line of each remaining lot in the existing Box Grove Hamlet, as part of the preservicing of the first phase of subdivision which is draft plan approved and zoned within the Box Grove Planning District.

 

  • Oversize sanitary sewers to accommodate existing properties in the Box Grove Hamlet, as part of the underground servicing for the Secondary Plan area.

 

  • Realign 9th Line south of Highway 407 to the east around the existing Hamlet of Box Grove to relieve north-south traffic through the existing hamlet, and to improve the functioning of the intersection at existing 9th Line and 14th Avenue.

 

  • Construct a road that could form part of the Markham By-Pass as an unlit two lane rural cross-section within a 20 metre right-of-way commencing from the point of intersection where the 9th Line By-Pass meets the CPR Havelock Line, northeast to a point of connection with the Markham By-Pass approach ramp to Highway 407.

 

The studies in support of the Development Phasing Plan are completed and currently being finalized.

 

Water Supply to existing Box Grove Hamlet expected this year

As noted above, the Developers are required under the Memorandum of Understanding to install municipal water to the property line of each remaining lot in the existing Box Grove Hamlet, coinciding with the first phase of preservicing in the area.  The applicant’s engineer has advised that preservicing is expected to commence in late summer/early fall of this year. 

 

The Box Grove developers have prepared a Development Phasing Plan, which proposes 3 phases of development

The Development Phasing Plan (DPP) is a mechanism established as part of a larger program for growth management by the Town.  The DPP’s primary function is to describe the intended sequence of development within the Box Grove area as it relates to:

 

·        supporting infrastructure (9th Line By-Pass, Markham By-Pass, realignment of 14th Avenue)

·        community facilities (Community Park, schools)

·        treatment of significant natural features (tributaries ‘A’ and ‘B’, woodlot)

·        municipal water to service the existing community

·        sanitary sewer to be sized to accommodate existing community

 

The draft Development Phasing Plan, attached as Appendix ‘A’ establishes 3 phases to ensure the orderly sequencing of development.  Phase 1 includes lands within three proposed draft plans of subdivision (Box Grove Hill Developments & Box Grove North, Balgreen Holdings & Winter Garden Estates Inc. and Animate Construction Ltd.), which are close to draft approval, as well as lands owned by Ibrans Development Inc., which recently submitted applications for rezoning and draft plan approval (Figures 2 & 3).  A separate report to deal with draft plan approval for the three proposed draft plans of subdivision noted above is being brought forward to Development Services Committee meeting on May 18, 2004, to recommend draft plan approval.  

 

The timing of development for subsequent phases (Figures 2 & 3) will depend on confirmation by the Region of York and the Town of Markham on the availability of water supply and sanitary sewer capacity.  The third phase may be required to allow development on lands that are currently not participating in the development process.  The following is a brief outline of the phasing concept for the Box Grove area:

 

PHASE 1:  (Proposed construction of 1,365 residential units)

 

Water

  • Water allocation of 1,365 units
  • Extend existing water servicing infrastructure at 9th Line and 14th Avenue into the development area
  • Extend 14th Avenue watermain from McCowan Road if required by the Town
  • Construct local watermain network for the existing homes in the Box Grove Hamlet (Individual home owners will be responsible for the cost to connect their house to the municipal connection located at the property  line on the respective municipal road right-of-way)

 

Sanitary Sewers

  • Sewage allocation of 1,365 units, subject to confirmation in writing by the Region of York
  • Construct connection to York Durham Sanitary Sewer at 14th Avenue and realigned 9th Line to service lands north of 14th Avenue
  • Construct a deep connection and subtrunk to York Durham Sanitary Sewer at realigned 9th Line, north of CP Rail to service lands south of 14th Avenue
  • Sanitary sewers will be sized to accommodate flows from the existing Box Grove Hamlet (Rouge Circle & Ridgevale Drive), Phases 1 and 2 lands
  • Sanitary sewers will be sized to accommodate flows from lands at Steeles/9th Line (Barry Little’s property), subject to satisfactory financial arrangements

 

Stormwater Management Ponds

  • Construction of SWM Ponds 1, 3 , 4  and 6 and all associated infrastructure
  • Relocate a section of the 9th Line Tributary west towards the 9th Line By-Pass, in accordance with approvals from the regulating authorities
  • Relocate the 9th Line tributary in the Community Park between SWM Ponds 1 and 2 to accommodate the SWM ponds

 

Roads

  • Construct collector roads (Streets ‘4’, ‘5’ located north of 14th Avenue and Streets ‘5’ and ‘6’ located south of 14th Avenue) and with connections to boundary roads and internal roads
  • Construct 9th Line By-Pass (Regional Road) as a four-lane road from a point on existing 9th Line north of the former Box Grove Hamlet and extending southeast to the existing 9th Line south of the Hamlet and CNR
  • Construct employment collector from 9th Line By-Pass to a point east of Tributary ‘A’
  • Provide an interim connection from Rouge Bank Drive in Legacy subdivision, to the 9th Line By-Pass
  • Relocate traffic signals from Rouge Bank Drive and existing 9th Line to the new employment collector road intersecting with the realigned 9th Line
  • Signalize intersection of realigned 9th Line and 14th Avenue
  • Transfer of existing 9th Line within the Box Grove Secondary Plan area from the Region to the Town

 

Parks and Open Space

  • Parkland (Community Park and parkettes) and open space blocks (woodlot and tributaries ‘A’ and ‘B’) to be dedicated to the Town prior to the registration of the plans 
  • Neighbourhood parks will be developed and available to the Community when approximately 25% of the population in Phase 1 is in place subject to sufficient development charges held by the Town

 

Schools

  • 2 elementary school sites will be available to the respective School Boards

 

 

 

PHASE 2:  (785 units to be built when water and sewage allocation is granted):

 

Water

  • Improvements to external watermain on 14th Avenue (McCowan Road to Boxwood Crescent) to service the full buildout of the Box Grove Community
  • Obtain water allocation for a minimum of 785 units

 

Stormwater Management Pond and storm sewers

  • Expand internal collection system sized to accommodate contributing drainage area
  • Construction of SWM Pond 5.  If Phase 2 is developed prior to relocation of 14th Avenue by the Region, an interim SWM Pond 5 together with an interim SWM facility upstream of the employment collector road will be required

 

Sanitary Sewers

  • Extend sanitary sewers from Phase 1 sewer network
  • Size internal collection system south of 14th Avenue to accommodate future contributing flows from the existing hamlet of Box Grove, and lands at Steeles Avenue and 9th Line
  • Obtain sewage allocation for 785 units

 

Roads

  • Extension of internal road network from Phase 1
  • Construct balance of employment collector road, extending easterly from Tributary ‘A’ to Town Arterial Road (possible Markham By-Pass)
  • Intersection improvements (Traffic signals and turning lanes to be provided by the City of Toronto at 9th Line and Steeles Avenue when warranted (likely before Phase 2 construction). The cost of improvements is to be addressed as part of the establishment of Region of York/City of Toronto Boundary Agreement)
  • Construct a 2 lane Town arterial road (20 metre right-of-way), and protect sufficient right of way for a possible full Regional arterial road (36 metre right-of-way) corresponding to possible alignment of Markham By-pass, from Highway 407 to the 9th Line By-Pass 

 

Parks

  • Three parkettes

 

PHASE 3

  • Construction of SWM Pond 2

 

 

Water/Sewage Allocation

The terms of the Memorandum of Understanding commit the Town and the Region to certain matters including the granting of water and sanitary sewer allocation for 1,365 units to accommodate Phase One of the Box Grove developments, with the balance of the allocation to accommodate future phases to be granted on or before December 31, 2004, subject to Regional allocation to the Town of Markham.  While water allocation for 1,365 units has been set aside for Box Grove to date, additional water allocation is dependent on the Region confirming additional water supply to the Town of Markham. 

 

In addition, Region of York staff have recently identified emerging sanitary sewer capacity issues which will have a bearing on the phasing of development in Box Grove.

 

The Region of York report dated May 5, 2004, received by the Transportation and Works Committee entitled, “Strategic Approach to Managing Impact of Infrastructure Approval Delays” outlined sanitary capacity constraints in the York/Durham Sanitary Sewer Trunk (YDSS) and population/development restrictions to + 2008, when the 16th Avenue Phase II and Southeast Collector Sewer are proposed to be constructed.   The Region outlined a preliminary indication of proposed population caps for each municipality to 2008, which will be reviewed with area municipalities.  Town staff have consulted the Region relative to the emerging sanitary sewer capacity constraints, and Regional staff have advised that they are not requesting that any restrictions be placed on the draft plan approval for Phase One of the Box Grove area relative to sanitary sewer. Prior to draft approval being issued, the Region should be requested to provide confirmation in writing that sanitary sewage capacity is currently available for the 1365 units in Phase 1 of the Box Grove community, and that this allocation is in addition to sanitary sewer capacity for previously approved draft plans and site plans in the Town of Markham.  Further discussions with the Region will be required as to future phases of development in Box Grove.

 

Lands required to be expropriated in order to construct Town Arterial Road and connection from 9th Line By-Pass to the Legacy Community

As noted above, the Secondary Plan and the Memorandum of Understanding require the developers to construct certain roads within the Box Grove area, including:

 

  • A Town Arterial Road (possible road alignment option for Markham By-Pass) as a two-lane rural collector road within a 20 metre right-of-way from the 9th Line By-Pass where it meets the Canadian Pacific Railway Havelock Line northeast to the Highway 407/Markham By-Pass interchange ramps; and
  • Interim or ultimate connection between the realigned 9th Line and Rouge Bank Drive.

 

Certain sections of these proposed roads are located within lands owned by non-participating landowners (Figure 4). The developers, through the Memorandum of Understanding have committed to constructing these roads, at no cost to the Town, subject to the Town acquiring the lands.   The Memorandum of Understanding further specifies that any such land acquisition would be at no cost to the Town, and is to be financed through Development Charges, which are currently being incorporated by the Town into the Development Charges Background Study scheduled for Council approval in August, 2004.

 

Town arterial road / Markham By-pass link construction schedule

The Secondary Plan has identified a right-of-way and route alignment for a Town Arterial Road, from the realigned 9th Line where it meets the CPR Havelock Line northeast to the Highway 407/Markham By-Pass ramp/interchange, which could potentially accommodate a portion of the required Planned Link for the Markham By-Pass, subject to its confirmation as the most appropriate route through an Environmental Assessment Study.  The Secondary Plan also calls for the first stage of the Town Arterial Road, consisting of a minimum two lane rural collector road to be constructed and operational concurrent with the completion of the interchange.

 

As noted earlier in the report, the Memorandum of Understanding (MOU) also requires the developers to construct a two-lane rural collector road (i.e. as a first stage of the Town Arterial Road) within a time frame to the satisfaction of the Town, “such time frame to be linked to the release of lands for development in accordance with the Development Phasing Plan to be approved”.

 

The Highway 407 /Markham By-pass interchange is currently under construction and is expected to be completed by early 2005. In addition, the Region of York is currently in the process of finalizing the terms of reference for an Environmental Assessment Study to determine the ultimate location for the Markham By-Pass south of Highway 407.  The Region of York anticipates that public meetings for the EA will be held in the fall of this year or early 2005.  It is expected that a recommendation on the preferred route of the By-pass will be made by spring of 2005 and the EA filed with the Ministry of Environment.

 

The Box Grove Developers propose to construct the Town arterial road (potential Markham By-Pass) as part of Phase 2 of the Box Grove area developments when there is a better understanding of the ultimate location for the Markham By-Pass and when non-participating properties can be secured.  Staff would support a schedule that would see the road completed by the end of 2006, for the following reasons:

 

·           Construction of the road as currently envisioned would require the acquisition /expropriation of the necessary road right-of-way by the Town from non participating properties and this process will involve time frames which will take at least to 2006 to accomplish.

 

·           The Region’s EA Study is expected by Spring 2005, and is required as part of the needs and justification component of expropriation process by the Town.

 

·           Actual construction of a two lane cross section from Highway 407 to the realigned 9th Line, once the land is fully available, would be in the order of some 4 months, weather permitting.

 

The developer (Box Grove Hill Developments Inc. and Box Grove North Inc.) has committed to applying for draft plan approval for the remainder of the employment lands within their ownership, in the near future, which would dedicate the owner’s portion of the lands necessary to construct the two lane rural road from Highway 407 to realigned 9th Line.  Staff recommend the Owner be required to commit in the Phasing Agreement and Subdivision Agreement to complete construction of the   road from Highway 407 to the 9th Line By-Pass by no later than December 31, 2006 subject to the availability of properties. The Town may need to expropriate required section(s) of roadway from non-participating owner(s), and if required this would be at no cost to the Town,  to be financed through Development Charges.  The Development Phasing Plan must be updated to reflect the timing of this road construction.   

 

Required parkland located on lands owned by non-participating owners

The parkland and open space blocks within the proposed draft plans of subdivision will be dedicated to the Town of Markham with the registration of the first plans of subdivision for each landowner (Phase 1).  The Phasing Plan for Box Grove requires that neighbourhood parks be constructed and delivered when 25% of the population in Phase One is achieved, subject to sufficient Development Charge reserves held by the Town.

 

According to the requirements of the Secondary Plan, the three proposed draft plans of subdivision (Phase 1) are required to provide a total of 14.24 ha (35.18 acres) of parkland, whereas 13.68 ha (33.8 acres) are being provided, for an under dedication of 0.569 ha (1.405 acres) of parkland.  This under dedication is at the Town’s request so that the 0.569 ha (1.405 acres) of parkland can be located on lands west of the Community Park, on non-participating lands.  There are some grading constraints on the proposed Community Park block and these additional lands are required in order to program the Community Park to accommodate all the necessary active recreational facilities. 

 

It should be noted that the draft Box Grove Developers Group Agreement currently does not contain provisions to address the securing of parkland under dedication within the subject plans. The Phasing Plan should address how the developers are going to secure the remainder of the lands required to complete the Community Park.

 

Proposed Box Grove Development Phasing Plan must be modified to address additional matters

The Box Grove Secondary Plan sets out matters to be addressed in the Development Phasing Plan.  Staff have reviewed the Box Grove Community Phasing Plan as it relates to the requirements of the Secondary Plan and the Memorandum of Understanding, and have determined that some items identified in the Secondary Plan have not been addressed in the Phasing Plan.  In addition, the Engineering Department has noted additional matters, which must be addressed in the Phasing Plan.  The following is brief outline of the items that need to be addressed in the Box Grove Community Phasing Plan, prior to final approval:

 

  • Dependence on future sewage and water allocation
  • Phasing plan should acknowledge that certain lands will have to be expropriated (see discussion above) in order to construct certain required roads
  • Schedule relative to improvements to 14th Avenue through the existing community
  • Schedule for construction and funding of full ramps at Highway 407 at 9th Line and Markham By-Pass (i.e. completion of full interchanges during Phase 1 and 2 respectively)
  • Traffic management measures and routes intended for construction vehicles
  • Phasing Plan to be provided to Fire Department to assist them in establishing relative  response times from existing fire stations
  • Woodlot Management Plan, as well as Landscape Plans related to the Tributaries to be provided to the Town as part of mitigative planting for these areas
  • Schedule for the realignment of 14th Avenue at the CPR Havelock Line
  • Phasing plan should address how the developers are going to secure the remainder of the lands required to complete the Community Park, which are located on lands owned by non-participating owners (see discussion below)
  • Completion of Town Arterial Road (possible Markham By-pass) no later than December 2006
  • Completion of a permanent connection from Rouge Bank Drive to Legacy subdivision, to the 9th Line By-Pass

 

The Region of York is currently in the process of reviewing the Development Phasing Plan, and there may be additional items required to be addressed by the developers, prior to final approval of the Development Phasing Plan. 

 

It should be noted that a provision has been included in the conditions of draft plan approval for the subdivisions noted above that are located within Phase 1, requiring finalization of the Box Grove Development Phasing Plan in accordance with the items noted above (i.e. requirements set out in the Box Grove Secondary Plan, Memorandum of Understanding, requirements of the Region of York, and modifications noted in this report), prior to registration of any plans.  

 

Development Phasing Agreement required to secure phasing requirements

It has been the Town’s practice to require developers groups to enter into a development phasing agreement with the Town, to secure the recommendations of the approved development phasing plan.  The Box Grove Secondary Plan requires that the developers enter into a Development Phasing Agreement with the Town and the Region regarding the implementation of the Development Phasing Plan.  The Development Phasing Agreement for Box Grove will formalize the items identified in the Secondary Plan and the Memorandum of Understanding, including, among other items, the following:

 

  • Requirement to construct 9th Line By-Pass and Town Arterial Road
  • Requirement to construct a road connection from Rouge Bank Drive (Legacy Community) to 9th Line By-Pass
  • Requirement to provide water connections to the property line of existing homes within the Box Grove Hamlet
  • Oversize the sanitary sewers to accommodate the existing Box Grove Hamlet

 

It should be noted that a provision has been included in the conditions of draft plan approval for the subdivisions noted above that are located within Phase 1, requiring the Developers Group to enter into a Development Phasing Agreement with the Town and the Region of York, prior to the registration of any phase of development.

 

The Development Phasing Plan is recommended for endorsement

The Box Grove Community Development Phasing Plan provides for the development of lands owned by both participating and non-participating landowners, and identifies the required infrastructure and community facilities to be delivered during each phase of development.  The Box Grove Community Development Phasing Plan can be endorsed in principle subject to the revisions outlined in this report.  It is recommended that the Commissioner of Development Services be authorized to approve the Development Phasing Plan, modified as recommended in the report, and that the Commissioner of Development Services be further authorized to modify the Development Phasing Plan as necessary to permit development to occur in keeping with the overall intent of the Box Grove Secondary Plan and Memorandum of Understanding, as well as to reflect the implementation of key infrastructure and servicing requirements including water and sewage allocation, and any requirements of the Region of York.  Staff will bring the Development Phasing Plan back to Development Services Committee for further direction should further modifications be required to the Development Phasing Plan that would have a significant effect on the overall delivery of services, roads or facilities, or the timing of approval of development.

 

FINANCIAL CONSIDERATIONS:

In accordance with the Memorandum of Understanding, the Town is required to expropriate the lands over non-participating landowners in order to facilitate the construction of the Town Arterial Road, and the road connection from 9th Line By-Pass to Rouge Bank Drive (Legacy Community).  These costs will be included in current update of  Town Development Charges.

 

LEGAL CONSIDERATIONS: 

The Legal Department will be responsible for carrying out the necessary legal proceedings to expropriate the lands over non-participating landowners, in order to facilitate the construction of necessary roads within the Box Grove area.

 

BUSINESS UNITS CONSULTED AND AFFECTED:

The Box Grove Community Development Phasing Plan has been circulated to the relevant agencies, including the Region of York.  All comments will be incorporated into the Development Phasing Plan, prior to final approval by the Commissioner of Development Services.

 

 

 

 

 

 

Valerie Shuttleworth, M.C.I.P., R.P.P.

Director of Planning & Urban Design

 

Jim Baird, M.C.I.P., R.P.P.

Commissioner of Development Services

 

 

 

                                                                       

Alan Brown, C.E.T.

Director of Engineering

 

                                                                                                                        FIGURE 1

 

FILE:  Q:\Development\Planning\APPL\SUBDIV\03 115555_BoxGroveHill\DSC_BGPhasingPlan.doc

 

 

ATTACHMENTS:

Figure 1:           Location Map

Figure 2:           Phasing Plan – North of 14th Avenue

Figure 3:           Phasing Plan – South of 14th Avenue

Figure 4:           Lands required to be expropriated

 

Appendix ‘A’   Box Grove Community Development Phasing Plan

 

 

APPLICANT/AGENT:            KLM Planning Partners Inc.                  Tel: (905) 669-4055

                                                c/o Roy Mason                         Fax: (905) 669-0097