TO: |
Mayor and Members of Council |
|
|
|
|
FROM: |
Jim Baird, Commissioner of Development Services Valerie Shuttleworth, Director of Planning
& Urban Design |
|
|
|
|
PREPARED BY: |
Mavis Urquhart Senior Planner Markham Centre Team |
|
|
|
|
DATE OF MEETING: |
2004-Jun-15 |
|
|
|
|
SUBJECT: |
East Precinct Plan and Principles - Status Update Markham Centre |
|
|
|
RECOMMENDATION:
THAT
the report entitled “Markham Centre East Precinct
Plan” - Status Update”, dated
PURPOSE:
This report is an update on
the status of the Markham Centre East Precinct Plan and the anticipated process
and timing for adoption of that Plan. The East Precinct Plan is a guideline
intended to provide a graphic illustration of a redevelopment scenario and
principles which shall be considered by the Town in reviewing all future
development applications.
Figure 1 to this memorandum
identifies the location of lands included in the East Precinct area.
BACKGROUND:
In February, 2004, Planning Staff retained the
consulting firm of Urban Strategies Inc., to prepare a Precinct Plan for the
area referred to as the “East Precinct” within Markham Centre. The “East
Precinct”, as shown on Figure 2, consists of the all the lands contained in the
Centre East District being approximately 50 hectares – 121 acres. The
boundaries of this area are: GO Transit/CN rail line, Highway 407,
Development of the East
Precinct Plan and principles is being undertaken by staff and a consultant,
rather than the area landowners because:
·
Planning for Markham Centre’s supporting infrastructure (design of
·
there is a need to finalize stormwater management, parkland and transit
requirements;
·
certain Owners in the area would like to proceed with development of
their lands now; and,
·
applications have been received, including the site plan application
for the YMCA and zoning and site plan applications for Cooperators Development
Corporation Limited.
The Precinct Plan will
identify the key elements of development in the area, notably: land uses,
including parkland and a place of worship; density distribution;
environmentally protected areas (woodlot); street, block and lot patterns; the
location of the major and connecting roads; transit; the location of stormwater
management facilities; pedestrian and bike connections; building
orientation/placement; parking solutions; open space elements and linkages; and
other important design elements. Preparation of a Precinct Plan is a
requirement of the Markham Centre Secondary Plan (OPA 21) and is intended as a
guideline for assessing development applications. The Precinct Plan is a
non-statutory document, intended to complement policy and regulations. The East
Precinct Plan and principles will identify the key elements of the Plan, which
will be based upon engineering, planning and urban design input, with the
assistance of the consultants. The Markham Centre Steering Committee, all
landowners and the public will be consulted when formulating the final Plan as
described in this report.
OPTIONS/DISCUSSION:
The study area is the Centre East District in the
Secondary Plan (OPA 21) and is technically composed of two Precincts as shown
on Figure 2 to this report. The subject lands are currently developed with low
intensity commercial and industrial uses, the GO station, a heritage building,
and the golf course. The ownership for much of the area is fragmented and the
configuration of many of the land holdings is narrow and deep. Figure 3
identifies the study area parcel fabric and addresses.
The purpose of preparing this Precinct Plan is to
provide guidance for the urbanization of the lands in a comprehensive manner,
and sets out guidelines for development that is consistent with the vision for
Markham Centre. Much of the direction for development of this Plan will be
drawn from the work and principles done to date in planning for Markham Centre,
including the Performance Measures.
Work Completed to Date
The Engineering components that have been
undertaken/completed in the East Precinct are:
These components will form the underlying
community structure to the Plan.
Several Options have been developed
To date,
several options have been developed by the consultant to address issues
surrounding the future high school. The York Region School Board has acquired
the golf course lands with intention of constructing a high school building in
the initial stage and an integrated sports complex in the second phase, with a
projected construction start date in 2005. Staff and the consultant are working
to ensure established criteria of the Secondary Plan are met by providing
options/opportunities for the school to be:
Staff has met on several occasions to discuss the
site layout and the school’s relationship to
Finally, the consultant is also working on
identifying a park location(s), place of worship and establishing the
distribution of densities of development within the East Precinct. It is
anticipated that a draft Precinct Plan should be ready for discussion and review
in several weeks.
Next Steps:
Stage One in this study is the
development of base mapping and project initiation. This involves background
technical work and research, as well as meeting with Town staff and the School
Board to discuss issues surrounding development of the future high school.
Consultation with staff/agencies and development of background mapping
(opportunities and constraints plan, massing assumption plan, street cross
section plan, block plan, etc.) by the consultant will be a prerequisite to
creation of the draft Precinct Plan and principles. This work is well underway.
Stage Two involves Town staff who
will be undertaking consultation and addressing implementation issues including
consultation with landowners, the public and a presentation to Development
Services Committee and Council.
Final Plan and Principles
It is anticipated that
landowner and public consultation will be undertaken during the summer and that
staff will report further on the results of this consultation on the Precinct
Plan in the fall.
FINANCIAL CONSIDERATIONS:
The consultant was retained to complete the
development of the East Precinct Plan. Payment for the consultant will come
from the 2004 operating budget, account 620-998-5603 (Planning Studies).
ENVIRONMENTAL CONSIDERATIONS:
This application will be reviewed in light of environmental policies
including small streams and protection requirements for the woodlot and input
from the Metro Toronto Conservation Authority.
ACCESSIBILITY
CONSIDERATIONS:
Accessibility considerations will be addressed at the site plan
stage.
ENGAGE 21ST
CONSIDERATIONS:
The
proposed Precinct Plan aligns with the following key Town of Markham Corporate
Goals: Managed Growth, Quality Community and Infrastructure Management by
providing guidance for development of the area.
BUSINESS UNITS CONSULTED AND AFFECTED:
Internal
departments and external agencies will be contacted for input and comments in
the formulation of the Precinct Plan and principles.
CONCLUSION:
The
East Precinct Plan and principles will set out a community structure which
implements and supports the vision of Markham Centre. It will provide an
opportunity to unlock the potential of these lands and develop a mixed use
community as part of Markham Centre. The road pattern, public services and
facilities are intended to be delivered through a co-ordinated and cost-shared
approach, through landowner contributions, Development Charges and Developer
Group arrangements.
|
|
|
Valerie Shuttleworth, M.C.I.P., R.P.P. Director of Planning &Urban Design |
|
Jim Baird, M.C.I.P., R.P.P. Commissioner of Development Services |
FIGURE
1
DOCUMENT:Q:\Development\Planning\Teams\Markham Centre\East
Precinct\dsc0707mu.doc
ATTACHMENTS:
Figure
1 Location Plan
Figure
2 Excerpt from OPA 21 Districts
and Precincts (Schedule”EE”)
Figure
3 Land parcels and addresses
superimposed on Aerial Photo
APPLICANT/AGENT: n/a
LOCATION PLAN: