DEVELOPMENT SERVICES COMMITTEE

 

 

 

 

 

TO:

Mayor and Members of Council

 

 

 

 

FROM:

Jim Baird, Commissioner of Development Services

Valerie Shuttleworth, Director of Planning and Urban Design

 

 

 

 

PREPARED BY:

Gary Sellars, Senior Planner, East Development District

 

 

 

 

DATE OF MEETING:

June 21, 2005

 

 

 

 

SUBJECT:

RECOMMENDATION REPORT

Borron Construction Inc. (Fram Building Group)

Lakeside Vista Way, Swan Lake Village

Blocks 9 and 26, Plan 65M-3482

Applications for Official Plan/Secondary Plan and Zoning By-law amendments, and site plan approval to permit 82 condominium townhouse units.

File No.’s: OPA 04 009862, ZA 04 009845 and SC 04 023810

 

 

 


 

RECOMMENDATION:

That the applications submitted by Borron Construction Inc. (Fram Building Group) to amend the Swan Lake Secondary Plan (PD 30-1) and Zoning By-law 177-96, as amended to permit 82 condominium townhouse units within Swan Lake Village be approved and the draft Official Plan/Secondary Plan and Zoning By-law amendments attached as Appendices ‘A’ and ‘B’, be finalized and enacted;

 

That the application submitted by Borron Construction Inc. (Fram Building Group)

for Site Plan Control approval to permit 82 condominium townhouse units within Swan Lake Village be approved subject to the following conditions:

 

1.      That the final site plan and elevation drawings be submitted to the satisfaction of the Commissioner of Development Services, including:

 

·        a revision to the site plan to incorporate the extension of Street ‘A’ to Bur Oak Avenue

 

2.      That the Owner comply with all requirements of the Town and authorized public agencies, to the satisfaction of the Commissioner of Development Services;

 

3.      That the Owner enter into a site plan agreement with the Town, containing all standard and special provisions and requirements of the Town and public agencies;

 

4.      That the site plan approval shall lapse after a period of three years commencing June 7, 2005 in the event a site plan agreement is not executed within that period.

 

And that Borron Construction Inc. (Fram Building Group) be granted servicing allocation for 82 units from the existing Town reserve (322 units).

 

PURPOSE:

The purpose of this report is to recommend approval of the applications to amend the Swan Lake  Secondary Plan (PD 30-1) and Zoning By-law 177-96 and site plan approval to permit 82 condominium townhouse units within the existing gated Swan Lake Village; and to recommend the granting of servicing allocation for 82 units from the existing Town reserve.

 

BACKGROUND:

Property and Area Context

The subject lands are comprised of approximately 4.6 hectares (11.4 acres) within Swan Lake Village (condominium community) (Figures 1 and 2).  The lands are currently vacant.

 

To the west and east are existing bungalows and townhouses within Swan Lake Village. To the south, across Lakeside Vista Way, is the Swan Club (private community centre), vacant lands on either side of the community centre and Swan Lake.  To the north and west are vacant lands owned by Fram Building Group and Daniels Corporation, for which townhouse development has been approved.  Further to the north abutting Bur Oak Avenue are vacant lands owned by Sierra Homes and Daniels Corporation; both Sierra and Daniels have submitted site plan control applications to permit condominium stacked townhouses on these lands, outside the Swan Lake Village. The Greensborough community abuts the Swan Lake community to the north, west and east.

 

Official Plan and Zoning By-law

The lands are designated Medium Density (Area II) Housing by the Swan Lake Secondary Plan (PD 30-1).  This designation permits a variety of dwelling types having an average net site density within the range of 37 to 80 units per hectare (15 to 32 units per acre).  The lands are zoned Residential Two - Hold (R2*1 [H]) by By-law 177-96. The zoning includes a site specific provision which restricts permitted uses to apartment buildings only.

 

Proposal 

The applicant is proposing to construct 82 condominium townhouse units (one storey with loft) on the lands.  A north/south collector road through the lands will connect Lakeside Vista Way to Bur Oak Avenue. An open space/walkway area is proposed on the eastern portion of the lands (Figure 4).    

 

The applicant has submitted the following applications to implement this proposal:

 

  • application to amend the Secondary Plan to redesignate the lands from Medium Density (Area II) Housing to Low Density (Area II) Housing. The requested designation provides for a variety of dwelling types having an average net site density within the range of 17 to 37 units per hectare (7 to 15 units per acre). The proposed townhouse development has a density of 18 units per hectare (8 units per acre)

 

  • application to amend the Zoning By-law to permit the proposed townhouse units

 

  • application for site plan approval

 

An application for draft plan of condominium approval will be submitted following execution of a site plan agreement.

        

DISCUSSION:

 

The redesignation of the subject lands will facilitate the completion of Swan Lake Village

The original master plan for Swan Lake Village comprised a mix of residential unit types including detached, townhouse and apartment units.  Two apartment buildings have been built at the eastern boundary of the community; the remainder of the community that has been built to date is comprised of detached and townhouse units.

 

The applicant has advised the current market for apartment units in this community is small whereas the market for detached and townhouse units is strong. 

 

The requested redesignation of the subject lands will therefore facilitate completion of a portion of Swan Lake Village which has remained vacant for several years and has become a concern to abutting unit owners. 

 

Swan Lake Village representatives expressed their support for the proposal at a Public Meeting held on June 15, 2004 

Representatives of the Swan Lake Village condominium corporations (Village Amenity Committee) and those unit owners abutting the subject lands have been consulted by the applicant and expressed their support for the proposed development at the Development Services Committee Public Meeting for this proposal.

 

The proposed site plan and building elevations are acceptable

A north/south collector road through the lands will connect Lakeside Vista Way to Bur Oak Avenue and an open space/walkway area is proposed on the eastern portion of the lands.  The proposed road pattern and open space system are in accordance with the Swan Lake Village Urban Design and Master Plan.  The proposed townhouse units (one storey with loft) are similar to existing units in the Village. The townhouses are faced with brick and accents are provided through the use of vinyl siding and vinyl shingle on architectural features.

 

The extension of Street ‘A’ to Bur Oak Avenue has been included as a condition of approval

The Fire Department has advised that Street ‘A’ is to be completed to Bur Oak Avenue and that it must be accessible by the Fire Department.


 

This development will receive municipal curb side collection of waste and recyclables

Swan Lake Village is currently receiving municipal curb side collection of waste and recyclables on 6m wide private roads. The Waste Management Department has advised the continuation of 6m wide private roads in this portion of Swan Lake Village, which will complete the Village road pattern, is acceptable to accommodate municipal curb side waste collection.  The future condominium corporation will be responsible for snow removal and all landscape, private utilities, and road maintenance.

 

Servicing allocation from the existing Town reserve is proposed to allow this development to proceed 

The November 2000 subdivision agreement between Swan Lake Markham Community Ltd./Daniels SLV Corp. and the Town includes a clause allocating sanitary sewer capacity and water supply for a total of 1500 people within Swan Lake Village.   Swan Lake Village is currently comprised of 511 units, with approval for an additional 44 units which represents a total of 999 persons based on the 1.8 persons/unit as per the Swan Lake Secondary Plan.  The Town Solicitor has advised that pursuant to this clause in the subdivision agreement the Town is committed to providing servicing allocation for the remaining 501 persons which represents 278 units.  Pursuant to this legal commitment, staff recommend that Borron Construction Inc. (Fram Building Group) be granted servicing allocation for 82 units at this time, from the existing Town reserve (322 units).  An additional 178 unit allocation pursuant to the Swan Lake Subdivision Agreement is addressed in two other reports on this Agenda (Sierra and Daniels SLV).

 

Official Plan/Secondary Plan Amendment is exempt from Regional approval

The Region of York has advised the proposed Official Plan/Secondary Plan amendment is a matter of local significance and is exempted from approval by Regional Planning Committee and Council.

 

FINANCIAL CONSIDERATIONS:

No financial implications are to be considered in this report.

 

ENGAGE 21ST. CONSIDERATIONS:

Managed Growth

The development of these lands represents an orderly completion of Swan Lake Village.

 

ACCESSIBILITY CONSIDERATIONS:

Accessibility for physically/mentally challenged persons will be considered as a component of site plan approval.

 

BUSINESS UNITS CONSULTED AND AFFECTED:

The requirements of other Town Departments and agencies have been incorporated into the site plan and recommended conditions of approval.


 

ATTACHMENTS:

Figure 1 - Applicant/Agent & Location Map

Figure 2 - Area Context/Zoning

Figure 3 - Air Photo

Figure 4 - Site Plan

Figure 5 - Building Elevations

Figure 6 - Building Elevations

 

APPENDICIES:

Appendix ‘A’ - Draft Zoning By-law Amendment

Appendix ‘B’ - Draft Official Plan/Secondary Plan Amendment

 

 

 

 

 

 

Valerie Shuttleworth, M.C.I.P., R.P.P.

Director of Planning and Urban Design

 

Jim Baird, M.C.I.P., R.P.P.

Commissioner of Development Services

 

 

 

                                                                                                                                   


 

FIGURE 1

 

DOCUMENT #  Q:\Development\Planning\APPL\ZONING\04 009845 Borron Construction\rdscgsJune2005.doc

 

 

 

 

APPLICANT/AGENT:            Mark De Souza                                   

                                                Fram Building Group                            Phone: (416) 747-9661           

                                                141 Lakeshore Road East                    Fax:     (416) 747-9899

                                                Top Floor

                                                Mississauga, Ontario

                                                L5G 1E8

 

                                                Sandra Wiles

                                                KLM Planning Partners Inc.                  Phone: (905) 669-4055

                                                64 Jardin Drive                                     Fax:     (905) 669-0097           

                                                Concord, Ontario

                                                L4K 3P3

 

 

 

 

LOCATION MAP: