RECOMMENDATION REPORT Borron Construction Inc. (Fram Building Group) Blocks 9 and 26, Plan 65M-3482 Applications for Official Plan/Secondary Plan and Zoning By-law
amendments, and site plan approval to permit 82 condominium townhouse units. File No.’s: OPA 04 009862, ZA 04 009845 and SC 04 023810 |
|
|
|
RECOMMENDATION:
That the applications submitted by Borron Construction Inc. (Fram Building Group) to
amend the Swan Lake Secondary Plan (PD 30-1) and Zoning By-law 177-96, as
amended to permit 82 condominium
townhouse units within Swan Lake Village be approved and the draft Official Plan/Secondary
Plan and Zoning By-law amendments attached as Appendices ‘A’ and ‘B’, be finalized and enacted;
That the application submitted by Borron Construction Inc. (Fram Building Group)
for Site Plan
Control approval to permit 82 condominium
townhouse units within
1. That the final site plan and
elevation drawings be submitted to the satisfaction of the Commissioner of
Development Services, including:
·
a revision to the site plan to incorporate the
extension of Street ‘A’ to
2. That the Owner comply with all
requirements of the Town and authorized public agencies, to the satisfaction of
the Commissioner of Development Services;
3. That the Owner enter into a
site plan agreement with the Town, containing all standard and special provisions
and requirements of the Town and public agencies;
4. That the site plan approval shall lapse
after a period of three years commencing June 7, 2005 in the event a site plan
agreement is not executed within that period.
And that Borron Construction Inc. (Fram Building Group) be granted
servicing allocation for 82 units from the existing Town reserve (322 units).
PURPOSE:
BACKGROUND:
Property and Area Context
The subject lands are comprised of
approximately 4.6 hectares (11.4 acres) within
To the west and east are existing bungalows
and townhouses within
The lands are designated Medium Density (Area
II) Housing by the Swan Lake Secondary Plan (PD 30-1). This designation permits a variety of
dwelling types having an average net site density within the range of 37 to 80
units per hectare (15 to 32 units per acre).
The lands are zoned Residential Two - Hold (R2*1 [H]) by By-law 177-96.
The zoning includes a site specific provision which restricts permitted uses to
apartment buildings only.
Proposal
The applicant is proposing to construct 82 condominium townhouse units
(one storey with loft) on the lands. A north/south collector road through the
lands will connect
The applicant has submitted the following applications to implement this
proposal:
An application for draft plan of condominium approval
will be submitted following execution of a site plan agreement.
The redesignation of the subject lands will facilitate
the completion of Swan Lake Village
The original
master plan for
The applicant has advised the current market for apartment units in this community is small whereas the market for detached and townhouse units is strong.
Representatives of the
The proposed site plan and
building elevations are acceptable
A north/south collector road
through the lands will connect
The extension of Street ‘A’ to
The Fire Department has advised that Street ‘A’ is to be completed
to
This development will
receive municipal curb side collection of waste and recyclables
Servicing allocation from
the existing Town reserve is proposed to allow this development to proceed
The November 2000 subdivision agreement between Swan
Lake Markham Community Ltd./Daniels SLV Corp. and the Town includes a clause
allocating sanitary sewer capacity and water supply for a total of 1500 people
within
Official Plan/Secondary
Plan Amendment is exempt from Regional approval
The Region of York has advised the proposed Official Plan/Secondary Plan amendment is a matter of local significance and is exempted from approval by Regional Planning Committee and Council.
FINANCIAL CONSIDERATIONS:
No
financial implications are to be considered in this report.
ENGAGE 21ST. CONSIDERATIONS:
Managed
Growth
The
development of these lands represents an orderly completion of
ACCESSIBILITY CONSIDERATIONS:
Accessibility
for physically/mentally challenged persons will be considered as a component of
site plan approval.
BUSINESS UNITS CONSULTED AND AFFECTED:
The requirements
of other Town Departments and agencies have been incorporated into the site
plan and recommended conditions of approval.
ATTACHMENTS:
Figure
1 - Applicant/Agent & Location Map
Figure
2 - Area Context/Zoning
Figure
3 - Air Photo
Figure
4 - Site Plan
Figure
5 - Building Elevations
Figure
6 - Building Elevations
APPENDICIES:
Appendix
‘A’ - Draft Zoning By-law Amendment
Appendix
‘B’ - Draft Official Plan/Secondary Plan Amendment
|
|
|
Valerie
Shuttleworth, M.C.I.P., R.P.P. Director
of Planning and Urban Design |
|
Jim Baird, M.C.I.P., R.P.P. Commissioner
of Development Services |
FIGURE 1
DOCUMENT #
Q:\Development\Planning\APPL\ZONING\04
009845 Borron Construction\rdscgsJune2005.doc
LOCATION MAP: