TO: |
Mayor and Members of
Council |
|
|
|
|
FROM: |
Jim Baird,
Commissioner of Development Services |
|
|
Valerie Shuttleworth,
Director of Planning & Urban Design |
|
|
|
|
PREPARED BY: |
Sabrina Bordone,
Planner ext. 8230 |
|
|
West
District Team |
|
|
|
|
DATE OF MEETING: |
|
|
|
|
|
SUBJECT: |
Recommendation Report
|
|
|
Application for Site
Plan Approval |
|
|
Wemat Four Limited |
|
|
Proposed |
|
|
Southeast corner of
Highway 7 and |
|
|
SC 05 016629 |
THAT the Site Plan
application (SC 05 016629) submitted by Wemat Four Limited for an eight-storey
professional office building at 80 Minthorn Blvd, be endorsed in principle,
subject to the following conditions:
1.
THAT site plan approval be delegated to the Director
of Planning & Urban Design or her designate, to be issued following
execution of a site plan agreement. Site
Plan approval issues only when the Director has signed the site plan
“approved”.
2. THAT the owner will enter into a site plan agreement with the Town of Markham containing all standard provisions and requirements of the Town and public agencies, including;
a) Provision for payment by the Owner of all applicable fees, recoveries and development charges;
b) Provisions for satisfying all requirements of the Town’s Departments and external agencies, including the Regional Municipality of York Transportation and Works Department.
3.
THAT this endorsement shall lapse and site plan approval will not be issued, after a period of three
years commencing February 7, 2006, in the event that the site plan agreement is
not executed within that period;
4. THAT prior to approval of the site plan, the Owner shall: a) Submit drawings, to the satisfaction of the of the Director of Operations, showing the location and size of the internal garbage room/recycling room;
b) Submit a revised site plan, to the satisfaction of the Fire Chief, indicating fire department connections, the location of fire hydrants, and the location of Fire Access Route Signs;
c) Meet with the fire department to finalize the location of the Fire Department connection, private hydrant, fire access route signage and rapid entry key box, to the satisfaction of the Fire Chief;
d) Submit a revised site plan, to the
satisfaction of the Director of Engineering, showing that the centreline of the
proposed driveway to the subject development has been revised to align with the
driveway of the existing development situated on the opposite side of
e) Provide a revised site plan and building elevations, to the satisfaction of the Director of Planning and Urban Design, which shows:
i) A key map;
ii) Compliance with the minor variances obtained from the Committee of Adjustment;
iii)
Strengthened pedestrian
connections throughout the site, particularly at the intersection of Highway 7
and
iv) Specification of building materials, additional detail for the primary building entrance, stronger cornice treatment on the building, and screening of roof top heating, air conditioning and ventilation equipment.
f) Submit a Landscape Plan, to the satisfaction of the Director of Planning and Urban Design, prepared by a Landscape Architect having O.A.L.A. membership, with emphasis on the landscape treatment along the Highway 7 and Leslie St frontage and the required street tree planting in the boulevard.
g) Obtain all necessary approvals from the Regional Municipality of York (Transportation and Works Department);
f)
Obtain approval from the Committee of Adjustment for appropriate permanent
easements or rights-of-way with the adjoining landowner to the east (
The purpose of this report is to review and
endorse an application for Site Plan Approval for an eight-storey professional
office building at
BACKGROUND
Property and Area
Context
The subject property is approximately 2.95 ha (7.3 ac) in area and is located at the southeast corner of Highway 7 and Leslie St, municipally known as 80 Minthorn Blvd. The site is presently vacant with no significant vegetation or natural features (Figure 1).
Abutting the subject property to the east is a professional office
building, which was also developed by the owner. To the north, across Highway 7, are the
Official Plan and Zoning
The Official Plan designates the subject property Business Park Area, which provides for the proposed use. This designation is intended to accommodate a mix of high quality business activities including corporate head offices and research facilities.
The subject property is zoned Select Industrial with Limited Commercial [M.C.(70%)] by By-law 165-80, as amended, which permits a variety of industrial uses as well as commercial uses including, but not limited to, business and professional offices (Figure 3).
The parking provided for the proposed development demonstrates compliance with the parking standards as outlined in the Town’s Parking Standards By-law 28-97, as amended, in terms of both the number of parking spaces provided and the size of the parking stalls. A total of 532 parking spaces are required and the owner is proposing to provide a total of 670 parking spaces, all of which will be provided at grade. A majority of the parking is provided in the rear yard of the subject property.
Proposal
The owner is proposing to construct an eight-storey professional
office building. The proposed office
building will be 15,970 m2
(171,909 ft2) in gross floor area and 37 m in height, with a penthouse level that will be used to store mechanical
equipment. Access to the proposed office building will
be facilitated through a two-way drive off of
OPTIONS/DISCUSSION:
Siting of proposed building enhances the southeast corner of Highway 7
and Leslie St
The building is generally
rectangular in built form and is oriented to the intersection of Highway 7 and
There will be two pedestrian
entrances to the building: one fronting
onto the intersection of Highway 7 and
The proposed development complements the Highway 7 streetscape
The proposed development will
visually emulate the existing eight-storey office building that is situated
immediately to the east, which was also developed by the owner. Maintaining the visual attractiveness and
consistent imaging is consistent with the planned functions of the Business
Park Area designation as outlined in the Official Plan. The buildings are consistent in scale and
massing, as well as building materials.
Similar to the building to the east, the exterior façade of the proposed
building will be faced with green reflective glazing, pre-cast concrete panels
and reflective glass spandrel panels (Figure 5). Staff are generally
satisfied with the building materials and the proposal as submitted by the
owner. Minor modifications may need to
be made, particularly in respect of the landscape plans which will complement
and supplement the built form. These can
be resolved at the staff level, subject to the approval of the final plans to
the satisfaction of the Director of Planning &
Urban Design. The owner expects to begin construction in
the summer of this year.
Minor variances approved for reduced landscaped strip and increase in
building height
During the preliminary site plan
review, it was identified that the width of the landscape strip along the
In addition to the reduction in
the landscaping strip along
Compliance with the Toronto/Buttonville Airport Zoning Regulations has
been satisfied
Section 2.1.2. of the
Official Plan stipulates that lands surrounding
CONCLUSION:
Staff are generally satisfied with the
proposal and recommend that it be endorsed, subject to the conditions outlined
in this report.
FINANCIAL
CONSIDERATIONS:
There are no financial considerations associated with this application.
ENVIRONMENTAL
CONSIDERATIONS:
The subject lands are presently vacant and do not support any significant vegetation or natural features.
ACCESSIBILITY
CONSIDERATIONS:
The site plan shows eleven handicap parking
spaces, all of which are located within close proximity to the base of the
building.
BUSINESS UNITS CONSULTED AND
AFFECTED
The proposal has been circulated to other Town Departments and public agencies and their comments have been incorporated into this report and the approved conditions.
|
|
|
Valerie Shuttleworth, M.C.I.P., R.P.P. Director of Planning & Urban Design |
|
Jim Baird, M.C.I.P., R.P.P. Commissioner of Development Services |
DOCUMENT
FILE PATH: Q:\Development\Planning\APPL\SITEPLAN\05 016629 -
Wemat Four Limited\DSC Rec Report for Wemat.doc
ATTACHMENT
FILE PATH: Q:\GEOMATICS\NEW OPERATION\2005
AGENDA\SC\SC05016629
ATTACHMENTS: Figure 1 - Owner/Agent and Location Map
Figure
2 - Air Photo, 2002
Figure
3 - Area Context and Zoning
Figure 4 - Site Plan
Figure 5 - Elevations
AGENT: Kaik Barucha
Archxes Design Inc. Architects
L3R 9R9
Tel: (905) 475-3706
Fax: (905) 475-3574
Figure 1