Report to: Development Services Committee   Date Report Authored: December 13, 2010

 

 

SUBJECT:                         Markham Centre Mobility Hub

PREPARED BY:              Alan Brown, Director of Engineering, Ext. 7507

                                            Sepideh Majdi, P.Eng. Development Engineer, Ext. 2414

 

 

RECOMMENDATION:

1)                  That the December 13, 2010 report entitled “Markham Centre Mobility Hub” , be received;

 

2)                  And that staff be authorized to issue a purchase order to VIVA, on a preferred supplier basis, for their detailed analysis of alternative alignment options at the Markham Centre Mobility Hub, in the upset amount of $100,000 including HST, and in accordance with Purchasing By-law 2004-341, Part II, Section 7 (2)(b);   

 

3)                  And that the purchase order for the VIVA review be funded by the Remington Group and be eligible for a Development Charges Credit;

 

4)                  And that the Mayor and Clerk be authorized to execute a development charge credit agreement with the Remington Group to the satisfaction of the CAO and Town Solicitor, and in accordance to the Town’s Development Charge Credit / Reimbursement Policy;

 

5)                  And that VIVA be requested to establish a technical working group for the Mobility Hub review;

 

6)                  And that staff be authorized to issue if necessary a purchase order to Ministry of Transporation, on a preferred supplier basis, for their peer review of alternative alignment options at the Markham Centre Mobility Hub, in the upset amount of $70,000 including HST, and in accordance with Purchasing By-law 2004-341, Part II, Section 7 (2)(c);   

 

7)                  And that the Engineering Department create a new project in the 2010 Capital Budget to include the VIVA/GO Transit/MTO review at a cost of $170,000 to be funded by the Remington Group ($100,000) and Town wide hard Development Charges ($70,000);

 

8)                 And that staff be authorized and directed to do all things necessary to give effect to this resolution.

 

 

 

1. Purpose                     2. Background                     3. Discussion                         4. Financial       

 

5. Others (HR, Strategic, Affected Units)                                   6. Attachment(s)

 

PURPOSE:

The purpose of this report is to update Council on the YRTC (VIVA) and Ministry of Transportation (MTO) response to Markham’s June 22, 2010 request to review an alternative transit mobility hub concept and transit alignment options for the Markham Centre Mobility Hub.

 

 

BACKGROUND:

In July, 2003, Council granted draft plan approval to the Remington Group’s “Downtown Markham” project. This project with a projected 20 plus year build-out, provides for the introduction of Viva rapid transit along a dedicated alignment within the Civic Mall (“Simcoe Promenade”), and reserves another block for the future 407 transitway. Remington has engaged Calthorpe Associates to review and update Remington’s Markham Centre precinct plan, which includes consideration of the 407 and Viva transit alignments and interface with the Unionville GO Station and Mobility Hub. In May, 2010, Calthorpe presented their preliminary concept for potential alternative transit alignments and Mobility Hub station location to Markham staff, MTO and Viva. MTO and Viva representatives indicated that a Markham Council resolution would be required in order for them to review the Calthorpe concept in the context of their Environmental Assessment studies and approvals and seek direction from their respective ministries and/or boards.   

 

In June 22, 2010 staff submitted a Markham Centre Mobility Hub Station and Transit Alignment report to Council for their consideration. Through this report Council requested that the Ministry of Transportation and York Region Rapid Transit Corporation review and report back on a potential alternative 407 Transitway alignment, Viva rapidway route and Mobility Hub station location in Markham Centre (Attachment “A”). Both agencies were requested to report back as to their Ministry and/or Board direction regarding review of the Calthorpe alternative.  Further review of street and block patterns and possible transit alignment options, is ongoing in the context of Markham Centre Precinct Plan studies

 

 

OPTIONS/ DISCUSSION:

VIVA’S Response

VIVA at its September 16, 2010 Board Meeting authorized the Corporation to conduct a study to determine the implications of the proposed Calthorpe concept subject to receipt of funds to undertake such a study.

 

As per VIVA’s enclosed report and resolution (Attachment “B”) VIVA staff also outlined the following issues;

 

a)      Any changes to the VIVA alignment due to the Calthorpe concept will require an amendment to the approved EA which will require consultant funding, stake holder involvement and agency approval.

 

b)      The Calthorpe concept has a number of technical issues such as;

-  The length of the VIVA transitway would be increased by approximately

   500m which would increase capital cost, and have longer travel

   time.    

-  Interface and connection to Kennedy Road needs to be resolved.

-  The need for a crossing of a Rouge River tributary east of

 Birchmount Road may not be required and needs to be reviewed

 further.

-  The implication of future conversion to Light Rail technology needs  

   to be reviewed.

                

c)    Need to review the impact on pedestrian access, ability to service residents, business and students;

 

d)   Review of  local bus facilities including the bus terminal at the mobility hubs including joint use development;

 

e)    Review of the interface between VIVA, GO Transit, 407 Transitway and YRT required.

 

VIVA has advised of a number of financial considerations

VIVA in their report also advised of the potential financial considerations to implement the Calthorpe concept including;

o   Cost to amend the approved Environment Assessment study

o   Cost already incurred on preliminary design from Sciberras Road to Kennedy Road

o    Cost expensed for the existing underground structure at the GO Line

o    Increased length of the VIVA rapidway of approximately 500m

o   Additional cost for a grade separated connection to Kennedy Road

o   Additional capital costs associated with the VIVA station at the mobility station hub

 

The extent of the above additional VIVA costs has not been determined and needs to be defined as to extent and funding source.

 

VIVA has indicated in their report that a more detailed review by VIVA is required at a cost of ± $100,000 which they are prepared to undertake subject to receipt of funding from the Town of Markham or Markham Centre Developers.

 

Technical Working Group

Staff recommend that VIVA establish a technical working group consisting of VIVA staff, Town staff, other agencies (MTO, GO Transit, Metrolinx) and Markham Centre Developers to provide a collaborative approach to the VIVA work program.

 

MTO Response                      

“The Ministry of Transportation draft Environmental Assessment study has included that  

  MTO recognizes that there are ongoing studies within this section of the Transitway

  including Richmond Hill/ Langstaff and Markham Centres. Should significant changes to

     land use plans and planned transit alignments be  agreed to, in the future by all parties,

     MTO will modify the 407 Transitway Environmental Project Report as required.”

 

We anticipate that MTO will want to be compensated for their consultant services to review in detail the Calthorpe concept and a $70,000 allowance is recommended.

 

Pan Am Pool

The Town of Markham has been selected to host the 2015 Water Polo and Badminton events as part of the Pan Am Games. The Town will be moving into a design build process with the Pan Am Bid Committee and Infrastructure Ontario this fall for the Town owned lands in Markham Centre, and needs to be in a position to confirm the preferred building placement, grading and site requirements. As noted the conceptual layout for the Pan Am Pool overlaid in the MTO’s 407 alignment (Attachment “C”) reveals that the 407 alignment needs to be realigned to the south to facilitate construction of the Pan Am complex in 2013/2014. 

 

In order to ensure that the Town’s objectives and schedule are appropriately addressed a preliminary design of the road and servicing infrastructure of the abutting area is required for the area so Infrastructure Ontario can proceed with the detailed site plan and design of the Pan Am facility. Staff retained on a preferred supplier basis, McCormick Rankin Ltd to undertake the preliminary design of the road and servicing infrastructure for the East Precinct at an upset amount of $80,000 funded through Development Charges in the Engineering Department’s 2010 Capital Budget. 

 

McCormick Rankin Corporation has completed the majority of design work in the East Precinct area for the Town and has the background resources and expertise to assist the Town in a condensed schedule.  

 

 

 

FINANCIAL CONSIDERATIONS AND TEMPLATE: (external link)

Financial

Staff had requested an allowance of $250,000 (D.C. Funded) in the Engineering Department’s draft 2011 Capital Budget for the preliminary design of the Markham Centre Mobility Hub civil engineering infrastructure (road, bridges, sewers, watermains etc). In order to meet the Pan Am schedule, staff is requesting Council’s approval to advance funding and create a new 2010 capital budget amount to include the VIVA/GO Transit/ MTO review so the Mobility Hub conceptual design can proceed immediately.

 

Staff have met with the Remington Group regarding funding of the VIVA study. They have agreed to finance the VIVA review ($100,000) subject to future Town Wide Hard Development Charge Credits. A credit agreement will be required which staff are requesting approval for.   The balance of required funding for the matters outlined in this report ($70,000) is requested from the Town wide hard development charges.

 

The $80,000 for the preliminary road and servicing requirements has been approved (McCormick Rankin) on a preferred supplier basis, in accordance with the Towns Purchasing by-law and funded by Development Charges in an existing Capital Budget account.

 

 

ALIGNMENT WITH STRATEGIC PRIORITIES:

This report aligns with the Growth Management; Transportation/Transit; Environment and Integrated Leisure Master Plan of the strategic priorities of Council.

 

 

 

 

 

 

BUSINESS UNITS CONSULTED AND AFFECTED:

Planning, Finance and Community Services have been consulted in the preparation of this report.

 

 

 

 

RECOMMENDED BY: 

 

 

 

 

________________________                                    ________________________

Alan Brown, C.E.T.                                                    Jim Baird, M.C.I.P., R.P.P.

Director, Engineering                                                  Commissioner, Development Services

 

 

 

ATTACHMENTS:

Attachment “A” Markham Council June 22, 2010 Resolution

Attachment “B” YRRT – September 16, 2010 Report

Attachment “C” layout for the Pan Am Pool overlaid in the MTO’s 407 alignment

 

 

Q:\DEVELOPMENT\ENGINEERING\REPORTS\2010\DECEMBER\MARKHAM CENTRE MOBILITY HUB DECEMBER 13, 2010 REPORT.DOC