TRANSPORTATION COMMITTEE

 

 

 

 

 

TO:

Mayor and Members of Council

 

 

 

 

FROM:

Alan Brown, Director of Engineering

 

 

 

 

PREPARED BY:

Lloyd Fernandes, Senior Transportation Engineer

 

 

 

 

DATE OF MEETING:

2004-Jan-26

 

 

 

 

SUBJECT:

Cycling Implementation Plan - Phase I/Phase II Work Plan

 

 

 


 

RECOMMENDATION:

PHASE I

THAT the Phase I Cycling Implementation Plan (draft October 2003) be endorsed and updated as required, with input from the Cycling and Pedestrian Advisory Committee (CPAC);

 

AND THAT subject to the approval of the Engineering Department’s 2004 capital budget, staff be authorized to proceed with the Phase I implementation plan (estimated at $125,000);

 

AND THAT the Region of York be requested to work with Town Engineering staff to implement segments of bike facilities on the Regional roads as recommended in this report;

 

PHASE II

AND THAT subject to approval of the Engineering Department’s 2004 capital budget, staff be authorized to:

 

 

§         Establish the Cycling and Pedestrian Advisory Committee ($20,000 in 2004 budget);

 

 

PURPOSE:

Engineering staff was directed by Transportation Committee in late 2002 to proceed with the development of a cycling implementation plan.  A two-phase approach was undertaken to balance the need to:

 

§      Determine components of the plan that could be implemented in the short-term and

§      Develop a more comprehensive long-term strategy.

 

This report outlines the details of the Phase I Cycling Implementation Plan (draft October, 2003), completed with consultant assistance.  In addition, the report also outlines the framework of the proposed Phase II work program to establish the longer-term cycling implementation plan.  Initiation of the Phase I works, Phase II study and the initiation of the Cycling and Pedestrian Advisory Committee is subject to 2004 capital budget consideration and availability of staff and consultant resources. 

 

 

BACKGROUND:

Engineering staff provided an overview of the 1998 Town-wide Bicycle System Study in late 2002 to Transportation Committee.  The overview illustrated that the 1998 study is a “Cycling Master Plan”, which sets the vision for the Town and provides a solid base to develop a cycling network.  However, a detailed plan is required to ensure the various components are implemented in an appropriate manner based on timing, budget and priority.  As a result of the overview presentation and report, Transportation Committee authorized Engineering staff to initiate work on a cycling implementation plan (as per the short-term action plan indicated in the MTPS-2002 which was completed and endorsed by Council in June of 2002).  In addition to the initiation of a cycling implementation plan, Transportation Committee also requested that Engineering staff report back on the establishment of a Town of Markham Cycling and Pedestrian Advisory Committee.

 

At the September 29th, 2003 Transportation Committee meeting, the Engineering Department outlined, in a staff report, the details required to initiate, establish and manage a Town of Markham Cycling and Pedestrian Advisory Committee.  Transportation Committee endorsed the recommendations and provided amendments including clarification of resource requirements to be considered in the 2004 budget process.

 

 

DISCUSSION:

The Cycling Implementation Plan

A multi-phase approach was developed in order to initiate interest and momentum in this alternative mode of travel as soon as possible (Phase I) while at the same time being able to ensure that a detailed Town-wide plan would be developed (Phase II).

 

The Engineering Department has identified Phase I requirements with consultant assistance (Bikeway Implementation Strategy Phase I: Spine Network, Draft October 2003, Marshall Macklin Monaghan Ltd.).  The key components of the proposed Phase II study have also been identified based on the experience gained from the development of the Phase I plan.

 

Details of each of the phases including findings and requirements are provided below.

 

 

 

 

 

A)        Phase I

 

Phase I - Approach

The first phase outlines those improvements which can be realized within the next two years (i.e. 2004 & 2005).  These improvements include the establishment of a spine network, which is comprised of bike routes (i.e. bicycle route marker signs only) and bike lanes.  In both cases the spine network components will include only those improvements that require installation of signage and line painting and/or re-adjustments to line painting.

 

It is recognized that special area studies and development applications are underway in various locations within the Town (i.e. Milliken Main Street Study, Markham Road Corridor Study, etc.).  Further co-ordination with respective Town staff will be undertaken to best incorporate the proposed bike facilities in these areas.

 

Phase I – Highlights of Implementation Strategy

The Phase I strategy has been developed based on two primary goals:

 

§         To develop a visible and connected cycling network in the Town of Markham that is easily accessible and actively used by all types of cyclists; and

§         To connect, integrate and enhance the existing transportation network to include on and off-road cycling network as a means of facilitating the use of bicycles for leisure, tourism and utilitarian purposes such as commuting, shopping, school and errands.

 

The key highlights of the draft Phase I Bicycle Implementation Strategy Phase 1: Spine Network (October 2003) are listed below:

 

§         Two-year implementation plan (2004 – 2005).

§         The 2004 components are estimated at $125,000 with the 2005 components estimated at $176,000 based on typical industry unit costs.

§         Includes goals, objectives and route selection criteria to guide the selection of candidate routes for the “spine” bikeway network for the more urban area of Markham

§         Establishes bikeway route selection criteria based on quantitative and qualitative criteria to guide the selection and alignment of proposed cycling routes for the spine network.

§         Develops a set of road retrofitting guidelines to assist staff in implementation of the proposed spine network.

§         Identifies a preferred bikeway spine network that when completed will consist of 114 km of bikeways and will include three facility types: Bike Lanes (26 km), Signed Bicycle Routes (70 km) and Signed Bicycle Routes with Wide Curb Lanes (18 km).

§         Includes a digital database that is linked to digital maps and details of proposed routes, facility type and sign type by location and bikeway segment for the entire spine network which will assist Town staff in network implementation. 

§         Establishes network implementation priorities and implementation costs for 2004 and 2005

§         Recommends the need for the creation of a Cycling and Pedestrian Advisory Committee (CPAC) to address the needs and priorities of pedestrians and cyclists in Markham and to assist in the proposed Phase II study. (Transportation Committee and Council approved the establishment of the CPAC in principle in October 2003.)

§         Indicates the need for the Engineering Department to work with other Town Departments to ensure that the implementation of signs and pavement markings are initiated in the Spring of 2004.

§         Suggests the Town issue to the media and post on the Town’s website a media release and map of the spine network to inform the public on the Town’s efforts to begin to implement bikeway facilities in Markham.

§         Recommends the Town enter into discussions with the Region of York regarding bikeway spine segments proposed for sections of Regional roads.

 

Phase I – Schedule

As noted above, the report outlines a two-stage development process which would see approximately half of the routes completed in Year 2004 and the remaining in 2005.

 

B)        Phase II

 

Phase II – Approach (proposed)

The second phase is expected to include the development of a set of routes and lanes, which will build on the spine network established in Phase I and serve to update the Town-Wide Bicycle System Study completed in 1998.  The Phase II work will also cost and prioritize the implementation such that appropriate funds can be budgeted annually in the 10-year capital improvements program taking into account the updated development charges program.  Such an approach will clearly establish the Town’s commitment to developing a balanced transportation system, which establishes a road network and transportation system that supports cycling, in addition to walking, public transit and automobile use.  Such work would see co-ordination between Town departments, with public input via the Cycling and Pedestrian Advisory Committee (CPAC).  Accordingly, the interests of both cyclists and pedestrians can be protected and on-road and off-road facilities can be developed.  The Phase II work would be expected to be initiated at the earliest in Summer 2004, subject to the 2004 budget process.

 

Phase II – Key Components of Draft Work Plan

Phase II will build on the Phase I work.  However, the main focus will be on the development of comprehensive mid-term (2005 to 2010) and long-term (2010 to 2020) implementation strategies.  The key components to be included should be:

 

§         A preferred set of bikeway routes will be identified, feasibility assessed and facility types confirmed or revised, costed and prioritized.

§         Policies will be reviewed, detailed on and off-road bikeway and trail facility design guidelines and best practices developed and a formal implementation process and structure proposed.

§         Public participation component to be hosted by the Town through the proposed Cycling and Pedestrian Advisory Committee (CPAC).

 

Phase II -  Schedule

The proposed Phase II workplan is suggested to be initiated in Summer/Fall 2004 and is estimated to require nine to twelve months to complete.  With this estimated timeline a final report would be completed and presented to Transportation Committee at earliest in Summer/Fall 2005 pending the 2004 budget approval process.

 

Please note the CPAC development should be targeted to begin at least two to three months in advance of the initiation of Phase II work in order to engage prospective members, appoint members and confirm the committee’s mandate.  This initiation will allow sufficient time for CPAC to be fully mobilized and therefore able to contribute to the development of the Phase II implementation study.

 

Initiation of the CPAC development and Phase II work is subject to the 2004 capital budget process.

 

 

FINANCIAL/RESOURCE CONSIDERATIONS:

The financial and consultant resource considerations related to the Cycling Implementation related work (including Phase I, Phase II and the Cycling and Pedestrian Advisory Committee) for the 2004 budget process are listed below:

 

Bike Implementation Plan - Phase 1 (installation of bike signs and pavement markings)

§         An initial estimate of $125,000 in 2004 to implement 70 km of primarily signed bicycle routes.

 

§         The above estimate is based on typical industry based unit costs.  The Operations and Asset Management Department have advised that they do not have sufficient resources to undertake such works.  Additional contracting costs may be incurred and will be confirmed subject to a formal quotation for manufacturing and installation of the signs.

 

§         The draft 2004 capital budget indicates funding by tax rate and development charges at 50 percent each.

 

Bike Implementation Plan - Phase 2 (proposed study)

§         The Engineering department will initiate a request for proposals to undertake the Phase II cycling implementation study as per the purchasing by-laws.  The work is anticipated to not exceed the $100,000 and thus requires quotations from three qualified consultants.

 

§         The Engineering Department currently has $50,000 available in the 2003 capital budget (Acct No. 83-5350-5225-005).  Accordingly, a request for an additional $50,000 is currently requested in the 2004 budget process.

 

§         The development charges study update is scheduled to be completed by August 2004.  Included in this study will be a sensitivity analysis to determine the impact on the growth related portion of the funding to support a balanced transportation system.

 

Cycling and Pedestrian Advisory Committee (Endorsed in principle at Sept 29th Transportation Committee Meeting)

§         As indicated in the September 29th, 2003 “Cycling and Pedestrian Advisory Committee” report to Transportation Committee additional resources were indicated with respect to the initiation, implementation and management of the Advisory Committee.  For clarity, these requirements are iterated below.

 

§         Appropriate budget for advisory committee activities should be allocated for the costs associated with not only the preparation of meeting material but also outreach to the community.  This outreach is expected to include deliverables such as brochures to communicate the attributes of walking and biking and maps to illustrate the evolution of the cycling and pedestrian network.  In addition, it will also include time and staff involvement as well as marketing/advertising expertise to promote cycling and pedestrian facilities and usage by way of events, workshops and conferences for residents, employees and businesses in Markham.  As previously indicated $20,000 should be considered in as an annual capital budget item starting in 2004 to support the efforts of the committee.

 

§         From a staffing perspective, resources are limited based on current and projected workload for 2004 as a result of demands in the development and transportation engineering sections.  In addition to the projected workload, the Development Charges Update Study was initiated late in 2003 and is expected to require at minimum half the time of the transportation staff member involved in the transportation component of the study for a period of 6 to 8 months.  It is understood that the Development Charges Update Study is a corporate priority.  It is with the understanding of the existing and projected commitments of staff resources, including that required for the Development Charges Update Study, that consultant assistance to the maximum amount of $25,000 is requested in the 2004 capital budget to assist with project management and the demands related to liaison with the CPAC.

 

Overview of Financial/Resource Requirements

 

The following table summarizes the funding and resource issues related to Phase I and Phase II and the Cycling and Pedestrian Advisory Committee (discussed in September 29th, 2003  “Cycling and Pedestrian Advisory Committee” staff report).

 

Phase/Work

Magnitude/Issue

Funding (est.)

Comments/Staff Resources

Phase I

2004 ~ Installation of signage

$125,000

 

- Estimated in current 2004 draft capital budget -Operation and Asset Department to contract out manufacturing and installation

-Final costs will be subject to a formal quotation from qualified contractors and need for contract administration.

2005 ~ Installation of signage and pavement markings

$176,000

-Subject to 2005 budget process

-Same as above

Phase II

Phase II Bike Implementation Study

$50,000* ($50,000 approved **)

-*Based on estimated additional allocation requested in the 2004 capital budget process.

-**Portion available in 2003 capital budget to the amount of $50,000 – Acct. No. 83-5350-5225-

 

005

(-This long-term project is a significant addition to Engineering staff workload – i.e. technical review, project management)

CPAC requirements (as per Sept 29th 2003 staff report)

$20,000

-To be considered in 2004 capital budget

(-This long-term committee is a significant addition to Engineering staff workload – i.e. project management of CPAC and involvement in public outreach activities.)

Consultant assistance to liaise with CPAC (as per Sept 29th 2003 staff report)

$25,000

-To be considered in the 2004 capital budget

(-Will assist in offsetting limited staff resource issues of the Engineering Department in the interim with respect to CPAC related work.)

 

Based on the above table the total 2004 budget request equates to an estimated $220,000.  With the current ratio of tax rate to development charges (i.e. 50:50) this would equate to $110,000 to be accommodated by the tax rate and the equivalent by development charges.

 

ATTACHMENTS:

Phase 1 – Extracts from Bikeway Implementation Strategy Report (Draft October 2003)

1.Overall Phase I spine Network

2.Phase I Spine Network – proposed 2004 works

3.Phase II Spine Network – proposed 2005 works

 

 

 

 

 

 

 

Alan Brown, C.E.T.

Director of Engineering

 

Jim Baird, M.C.I.P., R.P.P.

Commissioner of Development Services

Q:\Development\Engineering\REPORTS\2004\Jan\bikeplanphase.doc