|
|
|
|
|
|
|
|
|
|
TO: |
Mayor and Members of Council |
|
|
|
|
FROM: |
Jim Baird, Commissioner Development Services Alan Brown, Director of
Engineering |
|
|
|
|
PREPARED BY: |
Arup Mukherjee, Manager of Transportation Domenic Smarrelli, Supervisor,
Traffic Operations |
|
|
|
|
DATE OF MEETING: |
2004-Feb-23 |
|
|
|
|
SUBJECT: |
Neighbourhood
Transportation Committee 2004 Projects - Budget and Resource Impact. |
|
|
|
RECOMMENDATION:
That the NTC 2004 programme be deferred pending
the outcome of the Safe Streets Task Force.
PURPOSE:
This report outlines the
budget and resource impacts of the Safe Street Task Force (SSTF) on the 2004
Neighbourhood Transportation Committee (NTC) traffic calming projects.
BACKGROUND:
On
OPTIONS/DISCUSSION:
Speeding on local roads and resultant safety for residents has been a
concern for several years in
Given that the 2003 NTC programme was deferred due to the high tender
price, there are now 3 primary
initiatives that staff are being asked to undertake in 2004 related to speeding
and safety:
·
The SSTF
·
NTC 2002/3
·
NTC 2004
A discussion of each of these initiatives, the key tasks and staff
commitments are discussed in the following sections.
As background to the staff resource discussions, a copy of the
organizational chart and business plan summary for the Transportation Division
of the
1. Safe Streets Task Force (SSTF)
The SSTF has been identified as a
multi-faceted approach to affect driver behaviour and
improve community safety. The key
components of the SSTF include Education, Enforcement and
· Prepare presentation material for all task force meetings.
Changing driver behaviour is
not an easy task and significant effort will be required for this task force to
be successful in delivering the message and launching a public awareness event
in the Fall. Given the public outreach
and the effort required in developing a successful programme,
it is expected that approximately 1.25 FTE of supervisory/senior staff time
will be required to assist the task force for the 6-8 months required to
undertake this initiative.
2. Neighbourhood Transportation Committee (NTC) 2002 / 2003 Staff
Commitments
In 2003, staff completed the full EA studies for 9 projects identified
for the 2003 NTC programme. Eight of
these projects were from 2003 and one project (
As a result of these issues, the 2002/3 tender was one of the largest
and detailed traffic calming programmes tendered by staff. Unfortunately, the Town received only one
bid, and given the higher than expected price, Transportation Committee
recommended that the projects be re-tendered for Spring, 2004
construction. At the time of this
report, the new tender had been released.
Staff will update Transportation Committee on the tender as results
become available. Subject to a
favourable bid, staff will manage the contract this year and key tasks include:
·
Ensure
safe construction conditions for pedestrians and motorists.
·
Provide
approvals of construction layouts and materials.
·
Oversee
construction inspection.
·
Coordination
of contractor with Town activities and other agencies.
·
Liaison
for resident concerns.
·
Control
construction costs.
·
Uphold
construction schedule.
·
Record
and provide payment certificates.
This being the largest set of traffic calming projects to date, coupled
with the complexity of the proposed traffic calming devices including raised
intersections and chicanes, will require close supervision of the contractor
and construction of the devices. The use of new decorative materials for all
traffic calming devices will also require close supervision. As a result, it is
expected that this contract will require approximately 0.2 to 0.4 FTE of
supervisory/senior staff time to ensure
quality and the timely completion of the contract and respond to public issues
as they arise.
3. Neighbourhood Transportation Committee (NTC) 2004 Projects
The NTC 2004 project budget has been reduced as a result of the higher
costs associated with the two projects in the 2003 programme (
While there is a marginal reduction in staff time due to the need for 6 projects versus 8, it is still expected that about 0.5 to 0.75 FTE of supervisory/senior staff time would still be required to manage and approve the full EA requirements of the projects.
Options to proceed with NTC 2004 Programme
As noted above, the three initiatives of the SSTF, NTC 2002/3 and NTC 2004 would significantly exceed available staff resources. There are insufficient staff resources to undertake all 3 initiatives in 2004. Council has already directed staff to proceed with both the NTC 2002/3 and the SSTF projects in 2004. The following options are available for the NTC 2004:
Option 1 – Staff undertake additional
project
As noted earlier, the SSTF and NTC 2002/3 will more than take up the entire supervisory/senior staff allocation for traffic calming projects. It should be noted that if the 2004 NTC projects are to be implemented in the Fall, the NTC process would need to start immediately. The management of traffic calming projects requires staff at a supervisory/senior level given the amount of public consultation, analysis required for EA studies, report writing, liaison with Ministry staff and design review and modification. The Traffic Operations group has one Supervisor and four Technicians. Given the supervisory staffing needs for the SSTF and the NTC 2002/3 projects, there are no other supervisory/senior staff available to manage the EA studies for the NTC 2004. Technicians are not qualified to take on the management of EA studies and furthermore, they are required to respond to the daily safety and operational needs. Requests for stop signs, crossing guards, signals and school traffic safety must be investigated in a timely manner to ensure safe operations on our roadways. It is the role of Technicians to undertake all fieldwork, data collection and analysis to respond to these requests.
In addition, staff are expected to proceed with the Anti-whistling project as a priority in 2004. This project will require substantial liaison and coordination with CN Rail, the public and other agencies to coordinate approval and implementation.
Therefore, there are insufficient staff
resources to undertake the NTC 2004 programme in addition to the SSTF and NTC
2002/3 project and other traffic operational projects.
Option 2 – Retain Consultant
This option would require a consultant to manage the process, in its entirety, which includes all activities shown in “NTC 2004 Projects”. Staff would provide direction and information to the consultant as required.
The late start of this program this year would delay the activities required to fully complete the EA process. In addition, further delay will occur due to the execution of the consultant quotation period and their availability to undertake the program. It is expected that as a result of these delays, the construction will need to be undertaken in Spring, 2005.
Consultant’s fees for previous traffic calming projects of one street ranged from $15,000 to $35,000. Considering the NTC 2004 projects will include 6 streets, consultant’s fees is estimated to be in the range of $60,00 to $85,000. Currently the only budget identified for traffic calming is $130,000 for the 2004 programme. If the consultant fees are taken from this budget it will leave approximately $45,000 to $70,000 for capital construction of the 6 projects (excluding Wards 3 and 7). These remaining funds are not sufficient to implement an effective traffic calming programme.
Should Council select this option,
funding for the consultant would be required in addition to the currently
allocated funding for traffic calming.
Furthermore, the consultant fees are only estimates by staff at this
time. In accordance with purchasing
policy, staff would need to undertake bids to secure an exact price.
Option 3 – Defer 2004 NTC Programme
pending SSTF
The SSTF has been initiated by Council to consider additional measures to address speeding. While some of these possible measures such as photo radar, red light cameras and special constables may take some time, there are other measures such as dedicated police enforcement and community programmes that can be implemented this year. It is recommended that the $130,000 currently allocated in the 2004 Capital Budget for NTC 2004 be retained at this time. This would be prudent until we know the final contract price for the large set of 2003 NTC projects, and also as a possible additional source of funding for SSTF priority projects that may emerge involving alternative measures of traffic calming other than speed humps.
In September, 2003 YRT outlined a draft
policy recommending that speed humps not be considered as a traffic calming
option on YRT routes. YRT has
established a task force to consult with municipalities and agencies to
finalize their draft policy on traffic calming.
A number of issues such as damage to low floor buses and passenger
safety and comfort are being considered by the YRT traffic calming task force,
and will also be addressed through
Developer related projects:
The developers in South Cornell have
allocated funding to undertake traffic calming along
FINANCIAL CONSIDERATIONS:
Funding in the amount of $130,000 has been
identified in the
ATTACHMENTS:
Attachment A – Transportation Section
Organizational Chart and Business Plan
Attachment B –
June, 2003 extract regarding funding of 2003 NTC
|
|
|
Alan Brown, C.E.T. Director of |
|
Jim Baird, M.C.I.P., R.P.P. Commissioner of Development Services |
P:\Development\Engineering\REPORTS\2004\Feb\TC NTC
2004 BUDGETARY AND RESOURCE IMPACTS 3.doc