Region of York 2005 and 10 Year Capital Program |
|
|
|
RECOMMENDATION:
That the staff report entitled
“Region of York – 2005 and 10 Year Capital Program” dated
That the Region of York be requested to
incorporate into their 2005 and 10 Year Capital Programs, Markham’s
requirements as noted in the May 17, 2004 staff report and Council’s March 9,
2004 resolution;
And that the Region of York be requested to
prepare in consultation with area municipalities a 10 Year Program for signal
and intersection improvements;
And that Kees Schipper, Commissioner,
Transportation and Works be advised accordingly and thanked for seeking
municipal input into their Capital Program;
And that Ms. R. Burkholder, Markham Board of Trade,
Ms. A Yip, Scarborough/York Chinese Business Association, and Mr. K. Schipper,
Commissioner of Works, Region of York, be advised accordingly.
PURPOSE:
To provide
EXECUTIVE SUMMARY:
The Region of York is seeking local
municipalities input on their 2005 and 10 Year Capital Program. Based on
BACKGROUND:
In the past, municipalities have not had the
opportunity to provide input into the Region’s Capital Program until it was
submitted to their Transportation and Works Committee, at which time there was
little opportunity to make meaningful comments or seek any significant changes.
2005
and 10 Year Capital Program
Staff previously submitted to the Region’s
Transportation Committee on
In addition to the
ROADS
Advanced
Projects Proposed
Revisions
·
Hwy 7 -
·
·
·
·
9th Line -
Hwy 407 →Markham/Scarborough Link,
(4 lane diversion) 2010 → 2007/2008
·
Woodbine By-Pass - Major
Mackenzie to
Deferred Projects
·
·
·
York/Durham Line -
New Projects
·
Hwy 407/Markham By-Pass,
Northbound ramps 2005/2006
·
Hwy 407/9th Line Northbound
ramps 2005
WATER
We have requested a detailed summary from the
Region of water supply/allocation by year to
WASTEWATER
A separate process with a technical and
political working group to review the status of the 16th Avenue
Phase II and southeast collector sanitary sewer projects is currently underway,
and scheduling issues will be dealt with under that process.
FINANCIAL CONSIDERATIONS:
ATTACHMENTS:
Attachment A, Region of York,
Attachment B, 2004 Road Program Summary
Attachment C, Council’s
|
|
|
Alan Brown, C.E.T. Director of Engineering |
|
Jim Baird, M.C.I.P., R.P.P. Commissioner of Development Services |
Q:\Development\Engineering\REPORTS\2004\May\Region
of York 2005 Capital Program.doc